What is root cause analysis? Steps and a maintenance example

Root cause analysis (RCA) is a structured look at why a failure happened, carried past the broken part to the condition or habit that let it happen, so the fix holds.

By MaintensorUpdated 11 min read

Key points

  • Causes come in three layers: physical, human and system. A system fix covers every machine it reaches.
  • Save it for repeat failures, safety events, long stops and expensive repairs, one or two at a time.
  • Six steps: contain, collect the facts, find the causes, verify them, fix, and check that the fix held.
  • A cause stays on the list only if evidence supports it and it explains all of the facts.
  • In the conveyor example, 7 tracking work orders in 12 weeks fell to none in the 90 days after.

What root cause analysis is

A root cause analysis asks why a failure happened, and keeps asking until it reaches something you can change so that it does not fail that way again. A repair only fixes the failure in front of you.

What OSHA and the EPA call a root cause

Their joint fact sheet, The Importance of Root Cause Analysis During Incident Investigation, describes a root cause as a basic, system-related reason an incident happened, one that points to failures in the system you can correct. They add that there is often more than one.

The fact sheet is written about safety incidents, but the idea works the same way for a machine that keeps breaking.

In maintenance, causes usually come in three layers:

Physical cause
The part or condition that failed. A bearing ran dry, a belt stretched, a seal cracked.
Human cause
What someone did or did not do. The bearing was greased with the wrong grease, or skipped.
System cause
The gap that made the human cause likely. The lubrication route has no grease type on it, or the bearing is not on the route at all.

Replacing the bearing fixes the physical cause. Fixing the route fixes it on every machine the route covers.

When a small crew should do one

A small crew should do one for repeat failures, safety events, long stops and expensive repairs. A crew of five cannot investigate every breakdown, and should not try. These thresholds are a reasonable start; set them to fit your site.

Trigger A threshold to start with
Repeat failure The same problem on the same asset 3 times in 90 days, or the same part replaced 3 times in a year
Safety event Any injury, near miss, or unexpected release of energy, oil, steam or refrigerant
Long downtime A critical asset stopped for more than one shift
Expensive repair Above a figure you set, for example a month of the crew’s overtime

A repeat failure often shows in the machine’s own list of work orders.

A conveyor's work orders: four open with their due dates, a note that a V-belt has been used on it 10 times this year, and the latest finished jobs with their parts cost.
A conveyor's work orders, with the warning that a V-belt has been used on it 10 times this year and a prompt to check for a recurring fault.

When not to bother

A one-off failure whose cause is plain and recorded: a forklift backed into a guard, and the driver reported it. Cheap items you have decided to run to failure, such as a light fixture. Write the cause on the work order and move on. A small crew does well to carry one or two investigations at a time and finish them.

How to do a root cause analysis in six steps

  1. Contain it. Make the equipment safe, and keep the operation going with a temporary fix if you can do it safely. Keep the evidence: bag the failed part, take photos before anything is cleaned, and write down readings before anyone changes them.
  2. Collect the facts. Write the problem as something you could measure: not “conveyor problems” but “belt ran off to the left 7 times in 12 weeks, mostly at start-up”. Read the asset’s work order history and talk to the operator and each technician who worked on it.
  3. Find the possible causes. List every cause that could explain the facts, not only the favorite, with the tool that fits the problem (next section).
  4. Verify them. A cause stays on the list only if evidence supports it and it explains all of the facts. Ask, “If this were the cause, what else would we see?” and go and look.
  5. Fix it. Write one action for each confirmed cause, at each level: physical, human and system, each with an owner and a date. Prefer actions that change the machine or the method over “retrain” or “be more careful”.
  6. Check that it held. Set a date 30 to 90 days out to count recurrences. If the failure is back, the analysis missed a cause: reopen it.

Work it out in the browser: root cause worksheet.

Root cause analysis tools: 5 whys, fishbone, fault tree and Pareto chart

For most repeat failures on one machine, start with the 5 whys.

Tool How it works Best for Watch out for
5 whys Ask why, answer with evidence, and ask why of the answer Most repeat failures on one machine One chain hides other causes
Fishbone (Ishikawa) diagram The problem at the head; causes sorted onto six bones (below) A group session where people would otherwise fix on one idea Produces a list of possibilities, not proof
Fault tree Works down from the failure through AND and OR gates to every combination that could cause it Systems with backups: two boilers, two pumps Takes longer; needs someone who knows the system

A Pareto chart comes first

Use it to choose what to investigate. Count a year of repair work orders by asset, or one machine’s repairs by problem, and draw the counts as bars from tallest to shortest. The tallest bars are the repeat failures worth an investigation; the long tail of one-offs can wait.

The six fishbone categoriesMachine, method, materials, people, measurement and environment, read for maintenance

The fishbone categories, read for maintenance:

MachineWear, design, the parts in it.
MethodThe procedure, or the lack of one.
MaterialsParts, lubricants, the product being run.
PeopleTraining, staffing, shifts.
MeasurementWhat is checked and what is not.
EnvironmentHeat, dust, water, vibration.

FMEA is the same thinking run forward: it asks how a machine could fail before it does, and plans the checks that would catch it.

Root cause analysis example: a mistracking conveyor belt

In this made-up distribution center, a conveyor belt that kept walking off traced back to worn pulley lagging and a preventive checklist that never looked at the pulleys. Every name and number is invented. C-4 is an incline belt conveyor with a rubber-lagged drive pulley at the head end and screw take-ups on the tail pulley.

Over 12 weeks, the belt walked off to the left and rubbed the frame 7 times. Each time a technician tracked it at the tail take-ups and closed the work order as “tracked belt”. On the seventh, the belt edge frayed along about 6 feet (1.8 m) and the line stopped for 3 hours. The supervisor, Greg Thompson, called it a repeat failure and opened an investigation with the technician Tyler Jensen and the shift lead, Maria Santos.

Contain: track the belt, and add a daily look at the belt edge until the fix is in.

Facts collected:

Fact How it was found
7 tracking work orders in 12 weeks, about 9 labor hours C-4’s finished work orders
Every adjustment was at the tail take-ups; the left screw is now 1 1/4 inches (32 mm) further out than the right Measured both sides with a tape
The belt runs straight empty and walks left under load, worst when C-4 restarts loaded after a jam Watched three start-ups with the shift lead
The original 7-year-old drive pulley lagging is worn through to the steel across the right third of the face; the left keeps nearly its full depth Guard off, locked out, photographed
The monthly checklist covers the belt, the idlers and the gearbox oil, and nothing on the pulleys or the take-ups Read the procedure

Causes, verified:

Possible cause Evidence Verdict
Idlers out of square or seized All square to the frame, all turn freely Ruled out
Belt splice cut out of square Splice measured square Ruled out
Uneven lagging wear on the drive pulley A face worn to different depths is no longer the same diameter across, and steers the belt; the walking is worst under load, when the belt relies most on the drive pulley’s grip Confirmed
Tail pulley skewed by repeated take-up adjustments 1 1/4 inches difference side to side Contributing: each adjustment hid the problem for a few days
Restarting loaded after a jam Belt seen slipping on the drive pulley at loaded restarts Contributing: slip glazes and wears the lagging

Root causes, in the three layers:

Physical
Worn, uneven lagging on the drive pulley.
Human
Tracking at the take-ups and closing each job without a cause, which kept the pattern out of sight for weeks, and restarting loaded after jams.
System
Nothing in the preventive maintenance looked at pulleys or take-up positions.

Actions, each with an owner and a date:

  • Re-lag the drive pulley in the Saturday shutdown (Tyler).
  • Set both take-ups equal and track the belt at the idlers, as the conveyor maker’s manual describes (Tyler, in the same shutdown).
  • Add three steps to C-4’s monthly checklist (Greg, by Friday): lagging condition with a photo, take-up position left and right, and belt clearance under load. The conveyor belt maintenance checklist has more checks of this kind.
  • Change the restart (Maria, by Monday): clear a jam and run C-4 empty for a minute before loading.
  • Write the cause (Greg, by Friday): what was adjusted, and why, goes on every tracking work order.

The check: count the tracking work orders before and after.

7Tracking work orders
in the 12 weeks before
0Tracking work orders
in the 90 days after the fix

The investigation took about 5 labor hours and the re-lag one 6-hour Saturday job, against 9 labor hours and a 3-hour stop every 12 weeks before it.

A one-page RCA record

Keep it to one page, so it gets filled in. The record is free to download as a PDF to print or a Word file to type into. Below it, the same record filled in for the conveyor.

The blank root cause analysis record on one Letter page: the problem, containment, facts, causes ruled out, root causes, actions with owners, and the check.
The record filled in for conveyor C-4Every field, from the problem to the 90-day check
Field C-4 example
Problem: what, where, when, how much Belt walks left under load and rubs the frame, mostly at loaded restarts; one 3-hour stop
Containment Tracked belt; daily look at the belt edge
Facts and evidence Lagging photos, take-up measurements, history
Causes ruled out Idlers, belt splice
Root causes: physical, human, system Worn lagging; tracking at the take-ups; no pulley check in the PM
Actions, each with an owner and a date Re-lag (Tyler, Saturday); checklist steps (Greg, Friday); restart practice (Maria, Monday)
Check: date, measure, result 90 days: no tracking work orders. Closed

Mistakes that keep the failure coming back

  • Stopping at “operator error”. Ask what made the mistake easy: a missing step, a confusing control, no time, no training.
  • Stopping at the part. “Bearing failed” is a physical cause. Ask why the bearing failed.
  • Settling for one cause. Many failures have a main cause and one or two that made it worse, like the skewed tail pulley on C-4.
  • Guessing. An answer nobody checked is an opinion.
  • Weak actions. “Remind the crew” changes nothing a month later. A new checklist step, a guard or a different part does.

When the operators were blamed

The OSHA and EPA fact sheet gives the example of an employer who blamed operators for several releases that came before a fatal one. A deficient mechanical integrity program and malfunctioning instruments had left the operators unable to prevent them.

Counting unplanned downtime is how you pick which failure to investigate first. Writing a cause on every repair, as failure codes do, is how a pattern like C-4’s gets seen in weeks.

Root cause evidence and follow-up in Maintensor

What Maintensor holds is the evidence and the follow-through, kept the way equipment maintenance software keeps it: on each asset. It helps most with picking the candidates:

  • Most problematic assets. In Reporting (Pro and Max, for Admins), the Assets view lists the five assets with the most unplanned downtime in the period, each with its reactive work orders, MTBF and repair cost. Below the Max plan, repair cost is parts only.
  • A part that keeps going on. When one part has been used on an asset three or more times this year, the asset’s record warns you to check for a recurring fault. A tracking job that uses no part never trips that warning, so read the asset’s list of finished work orders too.

For the facts and the fix: a work order’s notes stay in its History with a name and a time, a failed inspection check asks for a note and a photo before the next step, though the job can still be closed without them, and a change of an asset’s status can take a reason. Each action is a work order, and each new check is a step in a procedure on a work order that repeats.

What it does not do

There is no root cause analysis tool, no cause or remedy field on a work order, and no failure codes. The RCA record and its reasoning stay in your own document or spreadsheet.

Questions

What people also ask.

More in the blog, or see the whole product on the features page.

What are the levels of root cause in maintenance?

Most investigations find three. The physical cause is the part or condition that failed, such as a worn bearing. The human cause is what someone did or did not do, such as greasing it with the wrong grease. The system cause is the gap that allowed it, such as a lubrication route with no grease type on it. Only a fix at the system level stops the same failure on the next machine.

How long should a root cause analysis take?

Size it to the problem. A repeat nuisance on one machine can be worked through in an hour at the machine with the technician who fixed it. A long stop on a critical asset may take a few hours spread over a week. An injury or a near miss deserves a formal investigation with whoever leads safety at your site.

Is root cause analysis the same as the 5 whys?

No. Root cause analysis is the whole process: containing the problem, collecting facts, finding and verifying causes, fixing them and checking the result. The 5 whys is one tool for the cause-finding step, and a good one for simple problems. A fishbone diagram or a fault tree does the same job when the problem has several possible causes.

Who should take part in a root cause analysis?

The technician who did the repairs, the operator or user who sees the equipment every day, and the supervisor who can change schedules and procedures. One person who was not involved helps, because they ask the obvious questions. Keep it to three to five people: a large group turns into a meeting and the facts get argued instead of checked.