Key points
- Report five numbers monthly: preventive share, PM compliance, backlog, MTTR and downtime on the worst assets.
- The first three lead: they move before the breakdowns show. MTTR and downtime lag.
- Backlog in crew-weeks is estimated hours of open work divided by the crew hours free each week.
- A few machines cause most of the lost time: in the example, two caused 69% of it.
- Compare each number with your own last month, not with someone else's target.
Why five numbers, and why these five
Five numbers are enough for a small team, because each one comes from your work orders and points to a decision when it moves. They answer the plant manager’s questions:
- Are we getting ahead of failures? Share of work that was preventive, which leads.
- Are we doing the preventive work we promised? PM compliance, which leads.
- Can we keep up with what comes in? Backlog in crew-weeks, which leads.
- When something breaks, how long does it stay broken? Mean time to repair (MTTR), which lags.
- Which machines hurt us most? Unplanned downtime on the worst assets, which lags.
The first three move before the trouble shows: when PMs slip, breakdowns can follow. Together the five tell you whether a bad month was bad luck or the start of a slide.

The five, each with its formula:
The long lists
The Society for Maintenance & Reliability Professionals (SMRP) publishes more than 70 metrics and guidelines in its Best Practices. The European standard EN 15341 sets out its own long list. Both are written for plants with planners and analysts, not a crew of four.
A one-page monthly report you can copy
One page, the same layout every month, read in ten minutes at the monthly production meeting. Every number below comes from one made-up month at a small food plant: four technicians, one supervisor, and six machines the plant cannot run without.
ExampleMaintenance KPI example: October's report, filled in
| Number | This month | Last month | Direction | What we will do |
|---|---|---|---|---|
| Preventive share (by count) | 55% | 58% | Down | Catch up the 5 missed PMs in the first week |
| PM compliance | 83% | 91% | Down | Book Filler 2’s PM with production two weeks ahead |
| Backlog | 2.8 crew-weeks | 2.1 crew-weeks | Up | Contractor for the 6 guard repairs, about 30 hours |
| MTTR, machine stops | 3.0 hours | 2.6 hours | Up | Keep 2 fill valve seal kits on the shelf |
| Unplanned downtime, six machines | 33.5 hours, 11 stops | 21 hours, 8 stops | Up | Find the cause of the Filler 2 seal failures |
Under the table, three short lists:
- Worst three assets, with hours down and cause: Filler 2 (14 hours, seals), case packer (9, glue), air compressor 1 (6, fouled cooler).
- Decisions needed from the plant manager: approve the contractor; agree a fixed weekly slot for Filler 2’s PM.
- Done since last month: what happened to last month’s actions, in one line each.
Every number got worse
Taken one at a time, each has an excuse. Taken together, they say the crew fell behind on preventive work and the machines answered.
The direction column and the actions are the point. A number nobody acts on can come off the page.
Each KPI in turn: the arithmetic and what to do when it moves
1. Share of work that was preventive
In October the crew completed 120 work orders: 66 preventive, 42 reactive and 12 other (installs and moves). If the crew logs time, work it out in hours too: preventive work took 180 hours, reactive 220 and other 60.
66 ÷ 120 work orders
180 ÷ 460 hours
Breakdowns usually take longer than routine tasks, so the hours figure is usually the lower one. The planned maintenance percentage is a different count: hours on all work planned in advance, preventive or not. Pick one version and keep it: switching mid-year makes the trend meaningless.
When it falls two months running, look first at PM compliance (are PMs being skipped?) and then at downtime (are breakdowns crowding them out?).
When it rises, check it is real. Splitting one PM into three work orders, or fixing things without writing them up, raises the count without any change on the floor.
2. PM compliance
Seventy preventive work orders fell due in October, and compliance fell from 91% in September.
58 ÷ 70 due
Some sites allow a grace window, such as three days for a monthly task. That is fine if you write it down and never change it quietly. The PM compliance entry covers the variations.
When it drops, list the 12 late or missed PMs with the reason for each. The reasons are usually few:
- No time: see the backlog.
- No parts for the job.
- No access: production would not release the machine.
- Too short a slot: the task takes longer than the time it was given.
Fix the reason. Deleting PMs to lift the number is only right when the task was never worth doing.
3. Backlog in crew-weeks
Backlog here means open work other than preventive maintenance (repairs, corrective jobs found on inspections, small projects). Preventive work is taken out of the crew’s hours instead. Some sites count the PMs due in the coming weeks as backlog and divide by the full crew. Either works if you keep to one.
ExampleThe food plant's backlog on October 31
The plant had 38 open work orders that were not preventive. Thirty-two had estimates adding up to 260 hours; the 6 without one were counted at 4 hours each, so the backlog is 284 hours.
The crew is paid for 4 × 40 = 160 hours a week, but not all of it is free for backlog jobs. Preventive work took about 41 hours a week in October (180 hours over 4.4 weeks), and meetings, rounds and parts runs take about 20.
260 estimated + 6 × 4
160 − 41 − 20, rounded
284 ÷ 100
If nothing new came in, the crew would need almost three weeks to clear it.
The maintenance backlog entry goes further.
4. Mean time to repair
The six machines stopped 11 times in October, for 33.5 hours in all, so MTTR is 33.5 ÷ 11 = 3.0 hours.
The clock runs from the moment the machine stopped to the moment it ran again, waiting included. Hands-on repair time is a different number; the guide to MTTR and MTBF works through both on one machine.
When it rises, sort the stops by length and read the longest two. A long repair is usually a long wait, and each wait has its own fix:
5. Unplanned downtime on the worst assets
Add up each machine’s unplanned stops and rank them.
The six machines, ranked11 stops and 33.5 hours down, with Filler 2 the worst
| Machine | Unplanned stops | Hours down | Main cause |
|---|---|---|---|
| Filler 2 | 4 | 14.0 | Fill valve seals leaking |
| Case packer | 3 | 9.0 | Glue nozzles clogging |
| Air compressor 1 | 1 | 6.0 | Overheated, cooler fouled |
| Conveyor CV-3 | 2 | 3.0 | Belt tracking |
| Labeler | 1 | 1.5 | Bottle sensor |
| Boiler | 0 | 0 | |
| Total | 11 | 33.5 |
Two machines, Filler 2 (14 hours) and the case packer (9), caused 23 of the 33.5 hours, which is 69%. A few machines usually cause most of the lost time, and they are where a root cause is worth finding.
Report the top three with the cause and what is being done about it, not every machine. To put a dollar figure on a stop, use the worksheet in what a breakdown costs.
More maintenance KPIs with formulas: MTBF, OEE, schedule compliance and cost
Other KPIs are each useful somewhere. Add one to the monthly report only when someone will act on it. The free maintenance calculators work out several of them from your own numbers.
Fifteen more KPIsWhat each one tells you, and how to work it out
| KPI | What it tells you | In short |
|---|---|---|
| Planned maintenance percentage | Share of maintenance hours spent on work planned in advance | Planned hours ÷ all maintenance hours |
| Schedule compliance | How much of the week’s plan got done | Scheduled hours done ÷ scheduled hours |
| Reactive work | Hours on jobs that broke into the week’s plan | Reactive hours ÷ all maintenance hours |
| MTBF | How often a machine fails | Operating hours ÷ failures |
| Availability | Share of required time a machine could run | Uptime ÷ required time |
| OEE | Availability, speed and quality combined, for production equipment | Availability × performance × quality |
| Wrench time | Share of a shift spent working on the job itself | Measured by watching, not from records |
| First-time fix rate | Repairs that held the first time | Repairs not repeated within a set period ÷ all repairs |
| Work order age | How long open work has waited | Open work orders counted by age bracket |
| Completion rate | Whether the crew keeps up with what is created | Completed ÷ created in the period |
| Overtime share | How much of the work needed overtime | Overtime hours ÷ all maintenance hours |
| Repeat failures | Machines that fail the same way again | Same asset, same fault, within 90 days |
| Stock-outs | Parts needed and not on the shelf | Count per month, with the hours lost waiting |
| Maintenance cost per unit | What maintenance costs per unit made or per square foot kept | Maintenance spend ÷ output |
| Request response time | How long a reported problem waits for an answer | Time from request to approve or decline |
Mistakes that make the numbers lie
How close Maintensor Reporting gets to each of the five
Reporting, the maintenance reporting software in Maintensor, counts most of this from the work orders and asset statuses you already keep. It is on the Pro and Max plans and open to Admins. Pick a range and filter by location, assignee or category (the Assets view by location only). The headline figures stand beside the period before.
- Preventive share is the preventive ratio: the share of work orders created in the range whose type is Preventive. It counts work orders, not hours.
- PM compliance: the On time vs. late card counts every work order due in the range, done or still open. One is on time if done by the end of its due day or not yet due. Recurring work (made by a repeat, whatever its type) is split out, so “Recurring, on time” is the closest figure.
- Backlog: Open work orders and Overdue are counts. Reporting does not add up estimates into crew-weeks.
- MTTR is the average time reactive work orders completed in the range took, from creation (or the start date, if later) to completion. It is not hands-on repair time, and it counts every reactive work order, whether a machine stopped or not.
- Downtime comes from asset status: Down counts as unplanned, In maintenance as planned. The Assets view ranks only the five assets with the most unplanned downtime, and it runs by the clock, nights and weekends included, because the app does not know your shifts.
What it does not do
Reporting does not calculate OEE, wrench time or an hours-based planned maintenance percentage. There is no export, so the one-page report above is still typed by hand from the screen.