Maintenance KPIs: the five numbers a small team should report

Maintenance KPIs are the few numbers that show whether maintenance is getting ahead of failures or falling behind. A small team needs five, reported monthly, each counted from work orders and tied to a decision.

By MaintensorUpdated 10 min read

Key points

  • Report five numbers monthly: preventive share, PM compliance, backlog, MTTR and downtime on the worst assets.
  • The first three lead: they move before the breakdowns show. MTTR and downtime lag.
  • Backlog in crew-weeks is estimated hours of open work divided by the crew hours free each week.
  • A few machines cause most of the lost time: in the example, two caused 69% of it.
  • Compare each number with your own last month, not with someone else's target.

Why five numbers, and why these five

Five numbers are enough for a small team, because each one comes from your work orders and points to a decision when it moves. They answer the plant manager’s questions:

  • Are we getting ahead of failures? Share of work that was preventive, which leads.
  • Are we doing the preventive work we promised? PM compliance, which leads.
  • Can we keep up with what comes in? Backlog in crew-weeks, which leads.
  • When something breaks, how long does it stay broken? Mean time to repair (MTTR), which lags.
  • Which machines hurt us most? Unplanned downtime on the worst assets, which lags.

The first three move before the trouble shows: when PMs slip, breakdowns can follow. Together the five tell you whether a bad month was bad luck or the start of a slide.

On time vs. late: 93% on time, 201 work orders on time and 14 late, with recurring work 100% on time and non-recurring 93%.
On time vs. late, the closest report figure to PM compliance: recurring work 100% on time, non-recurring 93%.

The five, each with its formula:

Preventive sharepreventive work orders ÷ all work orders × 100
PM compliancePMs done by their due date ÷ PMs due × 100
Backlog in crew-weeksestimated hours of open work ÷ crew hours available per week
Mean time to repair (MTTR)total hours from stop to back in service ÷ number of stops
Unplanned downtime on the worst assetshours of unplanned stops, added up per machine and ranked

The long lists

The Society for Maintenance & Reliability Professionals (SMRP) publishes more than 70 metrics and guidelines in its Best Practices. The European standard EN 15341 sets out its own long list. Both are written for plants with planners and analysts, not a crew of four.

A one-page monthly report you can copy

One page, the same layout every month, read in ten minutes at the monthly production meeting. Every number below comes from one made-up month at a small food plant: four technicians, one supervisor, and six machines the plant cannot run without.

ExampleMaintenance KPI example: October's report, filled in

Number This month Last month Direction What we will do
Preventive share (by count) 55% 58% Down Catch up the 5 missed PMs in the first week
PM compliance 83% 91% Down Book Filler 2’s PM with production two weeks ahead
Backlog 2.8 crew-weeks 2.1 crew-weeks Up Contractor for the 6 guard repairs, about 30 hours
MTTR, machine stops 3.0 hours 2.6 hours Up Keep 2 fill valve seal kits on the shelf
Unplanned downtime, six machines 33.5 hours, 11 stops 21 hours, 8 stops Up Find the cause of the Filler 2 seal failures

Under the table, three short lists:

  • Worst three assets, with hours down and cause: Filler 2 (14 hours, seals), case packer (9, glue), air compressor 1 (6, fouled cooler).
  • Decisions needed from the plant manager: approve the contractor; agree a fixed weekly slot for Filler 2’s PM.
  • Done since last month: what happened to last month’s actions, in one line each.

Every number got worse

Taken one at a time, each has an excuse. Taken together, they say the crew fell behind on preventive work and the machines answered.

The direction column and the actions are the point. A number nobody acts on can come off the page.

Each KPI in turn: the arithmetic and what to do when it moves

1. Share of work that was preventive

In October the crew completed 120 work orders: 66 preventive, 42 reactive and 12 other (installs and moves). If the crew logs time, work it out in hours too: preventive work took 180 hours, reactive 220 and other 60.

55%By count
66 ÷ 120 work orders
39%By hours
180 ÷ 460 hours

Breakdowns usually take longer than routine tasks, so the hours figure is usually the lower one. The planned maintenance percentage is a different count: hours on all work planned in advance, preventive or not. Pick one version and keep it: switching mid-year makes the trend meaningless.

When it falls two months running, look first at PM compliance (are PMs being skipped?) and then at downtime (are breakdowns crowding them out?).

When it rises, check it is real. Splitting one PM into three work orders, or fixing things without writing them up, raises the count without any change on the floor.

2. PM compliance

Seventy preventive work orders fell due in October, and compliance fell from 91% in September.

58Done by the due date
7Done late
5Not done at all
83%PM compliance
58 ÷ 70 due

Some sites allow a grace window, such as three days for a monthly task. That is fine if you write it down and never change it quietly. The PM compliance entry covers the variations.

When it drops, list the 12 late or missed PMs with the reason for each. The reasons are usually few:

  • No time: see the backlog.
  • No parts for the job.
  • No access: production would not release the machine.
  • Too short a slot: the task takes longer than the time it was given.

Fix the reason. Deleting PMs to lift the number is only right when the task was never worth doing.

3. Backlog in crew-weeks

Backlog here means open work other than preventive maintenance (repairs, corrective jobs found on inspections, small projects). Preventive work is taken out of the crew’s hours instead. Some sites count the PMs due in the coming weeks as backlog and divide by the full crew. Either works if you keep to one.

ExampleThe food plant's backlog on October 31

The plant had 38 open work orders that were not preventive. Thirty-two had estimates adding up to 260 hours; the 6 without one were counted at 4 hours each, so the backlog is 284 hours.

The crew is paid for 4 × 40 = 160 hours a week, but not all of it is free for backlog jobs. Preventive work took about 41 hours a week in October (180 hours over 4.4 weeks), and meetings, rounds and parts runs take about 20.

284 hOpen work
260 estimated + 6 × 4
100 hFree each week
160 − 41 − 20, rounded
2.8Crew-weeks
284 ÷ 100

If nothing new came in, the crew would need almost three weeks to clear it.

The maintenance backlog entry goes further.

When it grows three months in a row
More work is arriving than the crew can do. The choices are overtime, a contractor for a batch of jobs, cutting low-value PMs, or declining low-priority requests with a reason.
When it shrinks toward zero
Either the crew has caught up or people have stopped reporting problems. Walk the floor to find out which.

4. Mean time to repair

The six machines stopped 11 times in October, for 33.5 hours in all, so MTTR is 33.5 ÷ 11 = 3.0 hours.

The clock runs from the moment the machine stopped to the moment it ran again, waiting included. Hands-on repair time is a different number; the guide to MTTR and MTBF works through both on one machine.

When it rises, sort the stops by length and read the longest two. A long repair is usually a long wait, and each wait has its own fix:

Waiting for a partA spare on the shelf.
Waiting for the one person who knows the machineA written procedure.
Waiting for a contractorA call-out agreement.

5. Unplanned downtime on the worst assets

Add up each machine’s unplanned stops and rank them.

The six machines, ranked11 stops and 33.5 hours down, with Filler 2 the worst
Machine Unplanned stops Hours down Main cause
Filler 2 4 14.0 Fill valve seals leaking
Case packer 3 9.0 Glue nozzles clogging
Air compressor 1 1 6.0 Overheated, cooler fouled
Conveyor CV-3 2 3.0 Belt tracking
Labeler 1 1.5 Bottle sensor
Boiler 0 0
Total 11 33.5

Two machines, Filler 2 (14 hours) and the case packer (9), caused 23 of the 33.5 hours, which is 69%. A few machines usually cause most of the lost time, and they are where a root cause is worth finding.

Report the top three with the cause and what is being done about it, not every machine. To put a dollar figure on a stop, use the worksheet in what a breakdown costs.

More maintenance KPIs with formulas: MTBF, OEE, schedule compliance and cost

Other KPIs are each useful somewhere. Add one to the monthly report only when someone will act on it. The free maintenance calculators work out several of them from your own numbers.

Fifteen more KPIsWhat each one tells you, and how to work it out
KPI What it tells you In short
Planned maintenance percentage Share of maintenance hours spent on work planned in advance Planned hours ÷ all maintenance hours
Schedule compliance How much of the week’s plan got done Scheduled hours done ÷ scheduled hours
Reactive work Hours on jobs that broke into the week’s plan Reactive hours ÷ all maintenance hours
MTBF How often a machine fails Operating hours ÷ failures
Availability Share of required time a machine could run Uptime ÷ required time
OEE Availability, speed and quality combined, for production equipment Availability × performance × quality
Wrench time Share of a shift spent working on the job itself Measured by watching, not from records
First-time fix rate Repairs that held the first time Repairs not repeated within a set period ÷ all repairs
Work order age How long open work has waited Open work orders counted by age bracket
Completion rate Whether the crew keeps up with what is created Completed ÷ created in the period
Overtime share How much of the work needed overtime Overtime hours ÷ all maintenance hours
Repeat failures Machines that fail the same way again Same asset, same fault, within 90 days
Stock-outs Parts needed and not on the shelf Count per month, with the hours lost waiting
Maintenance cost per unit What maintenance costs per unit made or per square foot kept Maintenance spend ÷ output
Request response time How long a reported problem waits for an answer Time from request to approve or decline

Mistakes that make the numbers lie

Changing a definition without saying so
If MTTR starts including waiting time in March, March looks worse for no real reason. Write each definition at the foot of the report.
Comparing with someone else's target
It means something only if you count the same way. Compare with yourself first.
Missing inputs
Work orders with no work type, breakdowns fixed without a work order, PMs closed without being done. Each one quietly bends a KPI.
Too many numbers
Twelve KPIs get read once. Five get read every month.

How close Maintensor Reporting gets to each of the five

Reporting, the maintenance reporting software in Maintensor, counts most of this from the work orders and asset statuses you already keep. It is on the Pro and Max plans and open to Admins. Pick a range and filter by location, assignee or category (the Assets view by location only). The headline figures stand beside the period before.

  • Preventive share is the preventive ratio: the share of work orders created in the range whose type is Preventive. It counts work orders, not hours.
  • PM compliance: the On time vs. late card counts every work order due in the range, done or still open. One is on time if done by the end of its due day or not yet due. Recurring work (made by a repeat, whatever its type) is split out, so “Recurring, on time” is the closest figure.
  • Backlog: Open work orders and Overdue are counts. Reporting does not add up estimates into crew-weeks.
  • MTTR is the average time reactive work orders completed in the range took, from creation (or the start date, if later) to completion. It is not hands-on repair time, and it counts every reactive work order, whether a machine stopped or not.
  • Downtime comes from asset status: Down counts as unplanned, In maintenance as planned. The Assets view ranks only the five assets with the most unplanned downtime, and it runs by the clock, nights and weekends included, because the app does not know your shifts.

What it does not do

Reporting does not calculate OEE, wrench time or an hours-based planned maintenance percentage. There is no export, so the one-page report above is still typed by hand from the screen.

Questions

What people also ask.

More in the blog, or see the whole product on the features page.

What is the most important maintenance KPI?

No single number tells the whole story, but for a small team PM compliance is the one to watch first. It moves before the breakdowns do, it is easy to count from the work orders, and when it drops the reason is usually one the supervisor can fix inside the week: no time, no parts, or no access to the machine.

What is the difference between a maintenance metric and a KPI?

A metric is anything you can count from your records: work orders closed, hours logged, parts used. A KPI is a metric you have agreed to watch every period and act on when it moves. Most teams track many metrics and should report only a handful as KPIs, each with an owner and a decision attached.

How often should maintenance KPIs be reviewed?

Report them once a month, with the month before and the trend beside each number. A supervisor can glance at backlog and PM compliance weekly, because those move fast and can be fixed inside the week. Reliability numbers such as MTBF need a quarter or more of history before a change means anything.

Are there industry benchmarks for maintenance KPIs?

SMRP publishes target values for top performers alongside its metric definitions, available to its members, and other bodies publish their own. Targets only compare if the definitions match, and a small site rarely counts the same way a large plant does. The most useful comparison is your own number against last month and the same month last year.