The MTBF formula, and which hours count as operating
MTBF = operating hours ÷ number of failures
- Operating hours
- scheduled hours less every hour down, planned or unplanned
- Failures
- times the machine could not do its job, counted by rules set once
Scheduled hours come from the shift pattern: two 8-hour shifts, five days a week, is 80 hours a week. Take a quarter at least, and a year for a machine that rarely fails.
The dependability vocabulary, IEC 60050-192, calls it mean operating time between failures and applies it only to items you repair.
MTBF example: six machines over one 13-week quarter
The same six made-up assets as in the MTTR entry. Four of them, worst last:
2,177 h ÷ 2 failures
1,022 h ÷ 2 failures
1,025 h ÷ 3 failures
1,033 h ÷ 4 failures
The labeler fails most often: about every three weeks of two-shift running.
The quarter's numbers, line by lineAll six machines, with the dock door and the boiler.
| Asset | Runs | Scheduled hours | Hours down, all causes | Operating hours | Failures | MTBF |
|---|---|---|---|---|---|---|
| Air compressor 1 | Around the clock | 2,184 | 7 | 2,177 | 2 | 1,089 h |
| Conveyor CV-3 | 2 shifts, 5 days | 1,040 | 15 | 1,025 | 3 | 342 h |
| Dock door 3 | 2 shifts, 5 days | 1,040 | 27 | 1,013 | 1 | 1,013 h |
| Mixer M-2 | 2 shifts, 5 days | 1,040 | 18 | 1,022 | 2 | 511 h |
| Labeler | 2 shifts, 5 days | 1,040 | 7 | 1,033 | 4 | 258 h |
| Boiler | Around the clock | 2,184 | 6 | 2,178 | 0 | none yet |
The dock door’s 1,013 hours rest on a single failure: a hint, not a measurement. The boiler had no failures, so it has no MTBF yet: report it as no failures in 2,178 hours. Hours down include planned stops such as preventive maintenance, so they are more than the hours down from failures in the MTTR entry. Every number is made up.
One machine at a time
Do not average machines into one site figure: 8,448 hours ÷ 12 failures = 704 hours describes none of them and hides the labeler.
What counts as a failure
SMRP’s metrics workshop material defines a failure as an asset being unable to perform its required function.
- Count every unplanned stop above a threshold you set once, such as five minutes, and times it ran but could not do its job.
- Do not count planned stops (preventive maintenance, changeovers, cleaning) or stops it did not cause, such as no material.
- Decide once whether failures an operator cleared without a technician count.
MTBF and its neighbors
- Not MTTR. MTBF is how often; MTTR is how long each failure lasts. Together they give availability,
MTBF ÷ (MTBF + MTTR), when MTTR is counted from failure to back in service. - Not MTTF. For parts you throw away and replace, the measure is mean time to failure.
- Not a life expectancy. An MTBF of 1,000 hours does not mean each run lasts 1,000 hours: if failures come at random, about 6 runs in 10 end sooner.
- Failure rate is its inverse. 1 ÷ MTBF: the labeler’s 258 hours is about 3.9 failures per 1,000 operating hours.
The guide to MTTR and MTBF works out MTBF, MTTR and availability on one machine over a quarter. Each quarter, put the machines that fail most often beside the hours each lost: the one high on both is the place for the next root cause analysis.
MTBF in Maintensor
Reporting in Maintensor, on Pro and Max and open to Admins, shows MTBF on the Assets view for the five assets with the most unplanned downtime in the date range. It is “running hours divided by unplanned stops”: the hours in the range, less the asset’s unplanned downtime, divided by the times it was marked Down.
The app does not know your shifts and does not subtract planned downtime, so for a two-shift machine like the labeler it reads about twice the figure above: compare an asset with its own earlier periods.