What is mean time to failure (MTTF)?

Mean time to failure (MTTF) is the average time a non-repairable item, such as a bearing, seal or lamp, runs before it fails. For a machine you repair and put back into service, the matching measure is MTBF.

By MaintensorUpdated

The MTTF formula, and why it is for parts you replace

MTTF = total operating hours ÷ number of failures

Total operating hours
hours run by every item in a group of identical parts, failed or running
Failures
the items in the group that failed
MTTF calculatorType your own numbers and see the answer, with the sum shown.

The dependability vocabulary, IEC 60050-192, defines it as mean operating time to failure. A conveyor is repaired, so its figure is MTBF. The bearing in its head pulley is thrown away and replaced, so the bearing’s figure is MTTF.

MTTF example: six conveyor bearings, two still running

Six made-up conveyors each run the same head pulley bearing. Four have failed; two are still running.

53,000 hHours on all six
30,600 failed + 22,400 running
4Failures
CV-1 to CV-4
7,650 hFailed bearings only
30,600 ÷ 4, too low
13,250 hMTTF
53,000 ÷ 4

Leaving out the two running bearings understates the life: each has outlasted at least three of the four that failed. Counting their hours is the usual simple estimate, but it assumes a steady failure rate, so with six bearings treat it as rough.

The six bearings, line by lineHours on each bearing since it was fitted, two shifts a day, five days a week.
Conveyor Hours on this bearing Status
CV-1 9,200 Failed
CV-2 6,800 Failed
CV-3 3,100 Failed
CV-4 11,500 Failed
CV-5 12,000 Still running
CV-6 10,400 Still running

Every number is made up.

An outlier is a cause to find

CV-3’s bearing lasted 3,100 hours while the others ran two to four times as long: something shortened it, such as a belt that tracks to one side, a misaligned drive or a missed grease point.

Rated life is not MTTF

  • Bearings. Timken describes the L10 life as the life that 90 percent of a group of identical bearings will reach before a fatigue spall develops: the point where 10% have failed, not the average. Bearings failing well short of it point at lubrication, contamination, alignment or fitting.
  • Lamps. A maker’s rated average life for metal halide lamps is the point at which half of a test group is still burning, on a set burn cycle: a median.

MTTF, MTBF and useful life

  • Not MTBF. MTBF is for machines you repair, and MTTR is how long each repair takes.
  • Not useful life. Useful life is a planning figure: how long an asset is worth keeping, which depends on cost and obsolescence as well as failures.

The guide to MTTR and MTBF shows MTTF for a fill valve seal next to MTBF and MTTR for the machine it sits in.

Using MTTF to stock spares and to replace before failure

Six bearings that each run 4,160 hours a year (80 a week), with an MTTF of 13,250 hours, need about 6 × 4,160 ÷ 13,250 = 1.9 replacements a year; the reorder point and safety stock guide turns that into a shelf count.

If a part wears out and its failure stops a line, replace it on a schedule shorter than its typical life; if not, keep a spare and run it to failure.

The trail in Maintensor for working out MTTF by hand

Maintensor has no MTTF figure and no run-hour meters, so operating hours come from your shift pattern. Each asset lists the parts it uses and its work orders, and each work order lists the parts that went into it, so the dates give you the gaps between replacements.

When one part has been used on the same asset three or more times this year, the asset shows a warning to check for a recurring fault.

Questions

What people also ask.

More in the glossary, or see the whole product on the features page.

Can MTTF be used for repairable equipment?

In theory, yes, if each repair leaves the machine as good as new, and the international vocabulary notes that case. In practice a repaired machine is rarely as good as new, so maintenance teams use MTBF for machines they repair and keep MTTF for parts they throw away and replace.

How many failures do you need to work out MTTF?

More than you will usually have. With four or five failures the figure is a rough guide that one more failure can move a long way. Use it to spot parts that fail far earlier than they should, which needs few failures, rather than to set exact replacement intervals, which needs many.

Start with the machine that gives you the most work.

Start the trial, add that one asset with its location and nameplate, and write its first work order. Its history builds from there, job by job.

30-day free trial. No credit card.