Key points
- Safety stock is part of the reorder point, not a second trigger.
- At a 95% service level, z is 1.65: the shelf runs dry in about one cycle in twenty.
- Lead time is the whole wait, from the count reaching the reorder point to the part on the shelf.
- In the worked example, a bearing used about 4 a week gets a reorder point of 12.
- For parts used less than about once a month, a judgment rule does better than the formula.
Safety stock vs reorder point: the difference
Safety stock is a quantity: the extra you keep for surprises, such as a late delivery or a week with more breakdowns than usual. The reorder point is a trigger: the count at which you place the next order, and it already includes the safety stock.
reorder point = use during the lead time + safety stock
So safety stock is part of the reorder point, not a second trigger. In an average reorder cycle, the delivery arrives just as the count comes down to the safety stock; a late delivery or a busy stretch eats into it.
On a stock record, the reorder point is a line the count sits above or below.

For parts used every week, the formulas below work. For critical spares used every year or two, they give a fraction of a part, and a judgment rule does better.
Reorder point formula and safety stock formula
With use counted per week and lead time in weeks, the reorder point is average weekly use × lead time in weeks + safety stock. Safety stock is the cushion for the waits that go worse than average:
safety stock = z × σ of weekly use × √(lead time in weeks)
- z
- how often you accept running out: 1.28 covers about 90% of reorder cycles, 1.65 about 95% and 2.33 about 99%
- σ of weekly use
- the standard deviation of weekly use: how far one week strays from another
- Lead time
- the whole wait, in weeks, from the reorder point to the part on the shelf
The z values come from the normal distribution, as the NIST table of the standard normal distribution shows. A 95% level means that in about 19 reorder cycles out of 20, the shelf does not run dry before the delivery arrives.
Lead time is the whole wait
Count from the day the count drops to the reorder point until the part is on the shelf: the days before anyone notices, the approval, the order, the delivery and the putting away. A supplier who ships in two days is a one-week lead time if your orders go out on Fridays.
Every day a breakdown waits for a part is added to its repair time, which is where a stockout shows in mean time to repair.
When the lead time itself swingsThe version of the formula for a part that takes 4 to 12 weeks to arrive.
If the lead time varies a lot, as with a part from overseas, use the version that adds its spread, where σ is the standard deviation:
safety stock = z × √(lead time × σ of use² + average use² × σ of lead time²)
For a local supplier the simple version is enough.
The reorder point says when to order, not how many. How many is the order quantity: the supplier’s box, a case, or the economic order quantity for a steady consumable.
Min and max are the same pair under other names: min is the reorder point, and max is the reorder point plus the order quantity.
Reorder point example: a bearing used every week
A made-up plant uses 6205-2RS ball bearings in its conveyor rollers. Every figure here is invented. Twelve weeks of work orders show this use:
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Bearings used | 3 | 5 | 2 | 4 | 6 | 3 | 4 | 2 | 5 | 4 | 3 | 7 |
The local distributor delivers in two days, but orders go out once a week and receiving takes a day, so the lead time is taken as 2 weeks.
| Step | Working | Result |
|---|---|---|
| Average weekly use | 48 ÷ 12 | 4.0 |
| Standard deviation of weekly use | A spreadsheet’s STDEV of the twelve weeks | 1.54 |
| Use during the lead time | 4.0 × 2 | 8 |
| Safety stock at 95% | 1.65 × 1.54 × √2 = 1.65 × 1.54 × 1.414 | 3.59, round up to 4 |
| Reorder point | 8 + 4 | 12 |
| Order quantity | The distributor’s box | 10 |
| Max | 12 + 10 | 22 |
The standard deviation by handHow 1.54 comes out of the twelve weeks.
The weeks differ from the average of 4 by −1, +1, −2, 0, +2, −1, 0, −2, +1, 0, −1 and +3. Squared and added, that is 26. Divide by 11, one less than the number of weeks, and take the square root: √(26 ÷ 11) = 1.54.
When the count falls to 12, order a box of 10. You expect to use 8 while you wait, which leaves 4 for a bad fortnight. In about 19 two-week waits out of 20, that is enough.
Count the everyday use
Count breakdowns and routine replacements. A one-off project, such as rebuilding a whole conveyor, is known ahead: order for it when it is planned, and leave it out of the history.
When the safety stock formula breaks: slow-moving spares
For parts used less than about once a month, a judgment rule does better than the formula. Decide with this table.
| The part | Keep on the shelf | Order when the count falls to |
|---|---|---|
| Rarely used, and a stockout stops nothing that matters, or a workaround exists | None. Write down the supplier and the lead time | Nothing to order |
| Rarely used, a stockout stops a line, a building system or a safety device, and the lead time is long | 1 | 0: order the day it is used |
| As above, and shared by two or more machines, or it has failed twice within one lead time before | 2 | 1 |
| Used monthly or more often | The formula’s reorder point plus the order quantity | The reorder point |
The same made-up plant has two rarely used critical spares:
- A mechanical seal kit, shared by its two identical clean-in-place (CIP) pumps, with an 8-week lead time. If a seal fails and no kit is on the shelf, the plant cannot clean, so it cannot run. It used 4 kits in 24 months: 2 for failures and 2 in a planned shutdown rebuild.
- A gearbox on its only filler, used twice in five years, with a 10-week lead time.
The number to judge them by is the chance that the part is needed again before its replacement arrives.
With one seal kit on the shelf, about one failure in seven would find it empty, because the last kit has not been replaced yet. At one failure a year, that is roughly once every seven years, and each time the plant could be without cleaning for up to 8 weeks. The kit is critical and shared by two pumps, and that chance is too high, so the plant keeps 2 and orders when 1 is left.
With one gearbox on the shelf, about one failure in 14 would find it empty, or roughly once in 34 years. One spare is plenty, ordered the day it is used.
The spare parts inventory guide has a criticality shortlist for deciding which parts reach this table at all.
Why the formula fails on slow movers
The formulas assume use that is steady and spread evenly around its average, like a bell curve. Slow-moving spares break that in four ways.
Safety stock for a critical seal kit: the formulas worked throughOne planned job moves the answer from 1 to 2, and both start as a fraction of a kit.
The pump maker quotes 8 weeks, about 2 months. Twenty-four months of use:
- Month 4: 1 kit, seal leaking, replaced
- Month 11: 2 kits, both pumps rebuilt in the planned shutdown
- Month 20: 1 kit, seal failed
- The other 21 months: none
The same formulas, by the month, with a lead time of 2 months, once with all use and once with the planned shutdown left out:
| Step | All use | Failures only |
|---|---|---|
| Average monthly use | 4 ÷ 24 = 0.167 | 2 ÷ 24 = 0.083 |
| Standard deviation of monthly use | 0.48 | 0.28 |
| Use during the lead time | 0.167 × 2 = 0.33 | 0.083 × 2 = 0.17 |
| Safety stock at 95% | 1.65 × 0.48 × 1.41 = 1.12 | 1.65 × 0.28 × 1.41 = 0.65 |
| Reorder point | 0.33 + 1.12 = 1.45, round up to 2 | 0.17 + 0.65 = 0.82, round up to 1 |
One planned job moves the answer from 1 to 2, and both answers start as a fraction of a seal kit. That is the formula saying it does not fit this part.
The chance of needing a second spare: the sumsWhere one in seven and one in 14 come from.
The Poisson distribution, which describes how many rare, independent events happen in a stretch of time, gives the chance that a part is needed again before its replacement arrives:
chance of another use during the lead time = 1 − e^(−uses per year × lead time in years)
The seal kit, counting failures only: about 1 use a year, and a lead time of 8 weeks, which is 0.154 of a year. 1 − e^(−0.154) = 0.14.
The gearbox: 0.4 uses a year, and a lead time of 10 weeks, which is 0.19 of a year. 0.4 × 0.19 = 0.077, and 1 − e^(−0.077) = 0.074.
A reorder point needs a true count
A reorder point is only as good as the count it is compared with. If the record says 12 and the shelf holds 7, the order goes out late every time; cycle counting keeps the two in step.
Setting the reorder level in Maintensor
In Maintensor, each location that holds a part has its own On hand and Reorder level. A part shows Below reorder level when any location’s count is at or below its level, and Out of stock when there is none anywhere. The To reorder view lists both. The results go straight in:
If a part is kept in two storerooms, work out each level from the use that draws on that storeroom.
A part’s History tab lists every movement and says how many were used this year, which is where the average comes from. On Max, a part’s On order figure names the purchase order that will refill it. The spare parts inventory management software page shows the screens.
What it does not do
There is only a reorder level: no lead time, no min and max, no order quantity and no automatic reordering. Keep those on your own list, and choose how many to order each time.
The flag reads the shelf, not what is on order, so a part stays in To reorder until the delivery is received. Each work order is checked on its own: a line says how many it is short when its location holds less than it needs, but two jobs that need 8 each from a shelf of 12 are both shown as covered. Before a heavy week, add up the jobs yourself.