Reorder point and safety stock formulas
reorder point = use during the lead time + safety stock
safety stock = z × σ of weekly use × √(lead time in weeks)
- z
- 1.28 covers about 90% of reorder cycles, 1.65 about 95% and 2.33 about 99%
- σ of weekly use
- the standard deviation of weekly use: how far one week strays from another
- Lead time
- the whole wait, in weeks, from the reorder point to the part on the shelf
How to calculate reorder point and safety stock
- Enter the weekly use. The average, and how far it strays, from a year of counts.
- Enter the lead time. The whole wait, from noticing to the part on the shelf.
- Pick a service level. How often you accept running out.
Reorder point example: a bearing used every week
A made-up plant uses 4 of a bearing a week on average, and delivery takes 2 weeks.
4 × 2 weeks
1.65 × 1.54 × √2 = 3.59
8 + 4
When the count on the shelf reaches 12, order more.
What your reorder point tells you
- Decide how many to order. The EOQ calculator gives the size for a steady part.
- Look again when use changes. A new line or a changed schedule makes last year's figures wrong.
Lead time is the whole wait
Count the days before anyone notices, the approval, the order, the delivery and the putting away. A supplier who ships in two days is a one-week lead time if your orders go out on Fridays.