What MRO stands for, and the three groups of stock it covers
MRO stands for maintenance, repair and operations: everything a site keeps on hand to keep running, as opposed to what it makes or sells.
In aviation the same letters mean maintenance, repair and overhaul, the work of servicing aircraft and their parts; in the US, repair stations that do it are certificated under 14 CFR Part 145. This entry is about the first meaning.
Examples by setting
| Setting | Spare parts | Maintenance supplies | Operating supplies |
|---|---|---|---|
| Plant | Gearbox, bearings, proximity sensors | Grease, cutting oil, fasteners | Gloves, earplugs, shop towels |
| Warehouse | Conveyor rollers, dock door springs | Hydraulic oil, fuses, wire ties | Batteries, light bulbs |
| Building | Circulator pump, boiler igniter | Air filters, caulk, paint | Light bulbs, cleaning products |
| Fleet shop | Brake chambers, alternators | Engine oil, coolant, grease | Shop towels, gloves |
| Hotel | Faucet cartridges, a spare pool pump motor | Filters, sealant, touch-up paint | Door lock batteries |
MRO inventory example: a hotel shop’s 180 items by value
A made-up 120-room hotel’s maintenance shop holds 180 items worth $14,000 at cost.
$14,000 at cost
78% of items, 36% of value
22% of items
$9,000 of $14,000
Most of the items are cheap supplies; most of the money sits in 40 spare parts. So supplies go on two bins or a simple reorder level, and the spare parts get the attention: which are critical, how many to hold, and which belong to equipment the hotel no longer has.
The 180 items, line by lineItems and value for each of the three groups.
| Group | Items | Value | Share of items | Share of value |
|---|---|---|---|---|
| Spare parts | 40 | $9,000 | 22% | 64% |
| Maintenance supplies | 70 | $3,500 | 39% | 25% |
| Operating supplies | 70 | $1,500 | 39% | 11% |
| Total | 180 | $14,000 | 100% | 100% |
Every number is made up.
The spare parts inventory management guide has a criticality shortlist for deciding which spares to stock, and the reorder point and safety stock guide sets the reorder levels. For order sizes, see economic order quantity.
MRO inventory, spare parts and production inventory
- Not production inventory. Raw materials, work in progress and finished goods end up in the product; MRO stock is used up running the site. Keep the two on separate lists.
- Not always inventory on the books. US federal tax rules call maintenance components, fuel and lubricants “materials and supplies” (26 CFR 1.162-3). How your books treat them, in the US or Canada, is your accountant’s call.
Spares and supplies as parts in Maintensor, counted whole
In Maintensor, any of these can be a part, with a type you name (such as Bearings or Safety supplies), a unit of measure, a unit cost and a count per location with a reorder level. Quantities are whole numbers, so supplies are counted by the cartridge, box or bag.
Parts listed on a work order come off stock when it is completed; supplies used outside a work order, such as a box of gloves, come off with Remove stock and a note. Parts and purchasing shows the screens.