Spare parts inventory management

Spare parts inventory management is keeping the parts your crew needs on the shelf, in a known place, with a count you can trust: enough that a breakdown does not wait a week, and no more.

By MaintensorUpdated 10 min read

Key points

  • A storeroom holds three groups: critical spares, wear and PM parts, and supplies, each handled differently.
  • Score each candidate part 1 to 3 for stockout consequence and for lead time, then multiply.
  • A score of 6 or 9 means stock it; 1 or 2 means keep the supplier's number instead.
  • Every part that leaves the storeroom should leave against a work order.
  • Once a year, list parts unused in two or three years and ask whether any machine still uses them.

What a maintenance storeroom is for

A maintenance storeroom holds parts against failures nobody can schedule. An empty shelf does not lose a sale, as it would in a shop: it leaves a machine, a line or a building system waiting.

What sits on the shelves, together called MRO inventory, falls into three groups:

Group Examples How use behaves How to manage it
Critical spares A gearbox for the only filler, a seal kit for the boiler feed pump, a control board for a freight elevator Rare and random; may sit for years Decide one by one; keep one or two; reorder the day one is used
Wear and PM parts Bearings, V-belts, filters, wear strips Steady, often scheduled A reorder point from use and lead time
Supplies Grease, fasteners, fuses, wire ties, gloves Steady, cheap, many items A simple level, or two bins

Most of the thinking goes into the first group, and most of the counting into the second. A parts list is where that counting shows: what each part has on hand, and its reorder level.

The parts list: two parts below their reorder level at the top, one of them short for open work orders, then five in stock with their counts and minimums.
A parts list: two parts below their reorder level at the top, one of them short for open work orders, then five in stock. Min is the reorder level.

What to stock: a criticality shortlist

Start from what has broken and what the makers say to keep, not from a catalog.

  1. List the candidates. Go through a year of breakdown work orders and write down every part replaced. Add the recommended spare parts list from each important machine’s manual, and ask the crew which part they have waited for most.
  2. Score the consequence of a stockout, 1 to 3, on the scale below.
  3. Score the lead time, 1 to 3, from the moment you know you need the part to the moment it is on the shelf.
  4. Multiply. The score runs from 1 to 9.
  5. Decide. 6 or 9: stock it. 3 or 4: stock it if it is cheap or used more than about twice a year; otherwise write down where to get it fast. 1 or 2: do not stock it, and keep the supplier’s number with the machine.
  6. Set how many. For a critical spare, usually one, reordered the day it is used. For a part used every month, work out a reorder point and safety stock.
Score Consequence of a stockout Lead time
3 It stops a line, a building system or a safety device, with no workaround More than two weeks, or made to order
2 It slows things down, or a workaround exists (a second machine, a bypass, a rental) Two days to two weeks
1 Nobody outside maintenance would notice for a week The same or the next day, from a local supplier

The machine’s own rank matters too: a part for a machine that ranks low in an asset criticality analysis rarely scores 3 on consequence. Two more checks before you buy:

One spare for several machines
A part that fits several machines (one bearing size across a conveyor, a common motor frame) is cheaper to stock, because one spare covers them all.
A part dearer than the downtime
It may be better covered by a supplier who holds it for you, or a repair shop with exchange units.

A worked shortlist for a made-up plant

A made-up food plant with two packing lines and a crew of four. Every part, count and lead time is invented.

The seven parts, scoredFrom a gearbox kept on the shelf to a door closer not stocked
Part Used on Used in 12 months Consequence Lead time Score Decision
Gearbox, filler infeed conveyor Line 1 filler 0 3: line stops 3: 10 weeks 9 Keep 1, reorder the day it is used
Seal kit, mechanical, CIP pump Both cleaning pumps 1 3: no cleaning, no production 3: 8 weeks 9 Keep 2, since two pumps share it
Touch screen, palletizer Palletizer 0 2: manual mode works 3: 6 weeks 6 Price it against a supplier exchange
Sensor, photo-eye Case packer 3 3 1: next day 3 Keep 1: cheap, and it stops the line
Bearing, ball, 6205-2RS Conveyor rollers, 3 machines About 200 2: a roller can wait a shift 1: same day 2 Stock it anyway: work out a reorder point
V-belt, B48 Air compressor, two fans 10 2 1 2 Stock it: used most months
Door closer Offices 1 1 1 1 Do not stock

The score sorts the list; people make the last call

Three parts break the rule on purpose. The 6205 bearing and the V-belt score 2, but stocking them saves a trip a week, so they get a reorder point instead of a criticality decision. The palletizer’s touch screen scores 6, but it is expensive and the palletizer runs in manual mode: whether a spare beats an exchange agreement is a price call the score cannot make.

Organizing a small storeroom

  • One room or one cage, with one owner. If some parts must live by the line, treat that spot as a storeroom of its own, with its own count.
  • Give every shelf an address, such as A-03-2 for aisle, unit and shelf, on the label and on your parts list.
  • Group by kind, not by machine, so a part used on three machines lives in one place. Critical spares are the exception: tag each with its machine, so the filler’s gearbox does not end up on something else.
  • Heavy low, light high. Motors and gearboxes go on the bottom shelves.
  • Oldest first. Rubber belts, hoses and seals age on the shelf, and so does grease. Put new stock behind old, write the date received on the box, and follow the maker’s storage advice.
  • Flammable liquids in their own cabinet. Solvents and other flammable liquids have rules of their own.

What the storage rules say

OSHA’s materials handling rule, 29 CFR 1910.176, says storage must not create a hazard, that stacked material must be stable and secure against sliding or collapse, and that storage areas must be kept free of tripping, fire and pest hazards.

For flammable liquids, 29 CFR 1910.106 limits, among much else, how much may be kept in one storage cabinet. In Canada, provincial workplace rules and fire codes apply. Check the rule that covers your site.

Names and part numbers

Give each part one name, because the commonest storeroom fault is the duplicate: one bearing under three names, so the record says zero while two boxes sit in another aisle.

  • Noun first, then the details, so that sorted by name, all the bearings sit together.
  • Use the trade’s own number in the name where one exists: the bearing size, the belt section and length, the filter’s dimensions.
  • Record the maker’s part number and the supplier’s. The maker’s lets you buy it anywhere; the supplier’s makes reordering quick.
  • An internal number is optional. Keep it plain: a type prefix and a sequence, such as BRG-0012. Do not build meaning into it (the machine, the aisle, the year), because meanings change.
Name as found Name that sorts and searches
Belt for compressor V-belt, B48
Roller bearing (blue box) Bearing, ball, 6205-2RS
Prox Sensor, inductive proximity, 18 mm

Issuing parts to work orders

Every part that leaves the storeroom should leave against a work order. That one habit keeps the count right, puts the part in the machine’s history, and shows which machine eats bearings.

The work order lists the parts it needs and the storeroom each comes from. When the job is closed, what was used comes off the count, and what was not used goes back on the shelf.

When nobody is in the storeroom

For the night shift, keep a sign-out sheet by the door: date, part, quantity, machine and name. Someone enters it against a work order the next morning.

The same part on the same machine three times in a year is a fault to find, not a stocking problem.

A shared spreadsheet can hold the counts while one person enters every movement. Once several people take parts, maintenance software that takes parts off stock as jobs are closed keeps up better.

Kitting for preventive jobs

A kit is the parts for one planned job, gathered into a bag or tote and labeled with the work order number. Pull one a week ahead for each of next week’s preventive jobs. A kit saves the technician a walk, and it shows a shortage days early: anything you cannot kit, order today or move the job.

Keep the kits together on one shelf, and leave kitted parts on the count until the job is closed, so the record and the shelf agree. The planning guide has the kitting steps and fits kits into the weekly cycle.

Counting, and parts nobody uses

Counting a few parts every week, the most important most often, keeps the record right all year. Cycle counting in a maintenance storeroom covers the schedule, the method and a count sheet.

95% or higher

The U.S. Government Accountability Office’s guide to accurate inventory counts says experts agree that inventory record accuracy goals should be 95% or higher.

Clearing out dead stock

When a machine is retired, its unique parts become dead stock. Once a year, list the parts with no use in two or three years and ask of each whether any machine on site still uses it.

What you find What to do
No machine on site uses it Return it for credit, sell it or scrap it, and take it off the list
A machine uses it, but it is not critical and is easy to buy Use it up, and do not reorder
A critical spare, unused for years Keep it: that is its job. Check it still fits the machine as it is today
The same part under another name Merge the two into one count

Write down why each slow part is kept, so the next person does not throw out the gearbox.

Storerooms, reorder levels and parts on jobs in Maintensor

In Maintensor, each storeroom is a location with its own On hand and Reorder level for a part. The To reorder and Out of stock views cut the list to what needs a decision. Parts and purchasing shows each screen.

  • Parts on a job. A work order lists its parts and the location each comes from, and a line says how many it is short when its location holds less than it needs. Stock comes off when the work order is completed.
  • Parts taken outside a work order. They come off through Restock with Remove stock, which asks for a note, and every movement is listed on the part’s History.
  • Parts no machine uses. An Admin can archive a part. It leaves the pickers, keeps its stock history, and can be restored.
  • A part that keeps coming back. When one part is used on the same asset three times or more in a year, the asset’s Work orders tab says so and suggests checking for a recurring fault.

What it does not do

There is no lead time, no min and max (only a reorder level), and no automatic reordering. Each work order line is checked on its own, so two jobs that each fit, but not together, are not flagged. A location’s stock can have an Area, its shelf or bin, but the parts list does not search or filter by it, and the app reads no barcodes already printed on parts.

A parts list kept in Excel or CSV can be imported on Pro and Max, with the count on hand and the reorder level for each location. Vendors come on every plan; purchase orders with approval and partial receiving come with Max, on the pricing page.

Questions

What people also ask.

More in the blog, or see the whole product on the features page.

What is a critical spare part?

A critical spare is a part whose absence would stop something that matters, such as a production line, a building's heat or a safety system, for longer than you can accept, usually because it takes weeks to get. It may be used once in several years. It is kept as insurance, so a critical spare that sits unused is doing its job.

How many spare parts should a maintenance team keep?

There is no right total. Decide part by part. A critical spare with a long lead time is worth one on the shelf even if it is used every few years. A part you can buy across town the same day usually is not, unless you use it every week. Parts used often get a reorder point worked out from their use and lead time.

Should the maintenance storeroom be locked?

A storeroom anyone can walk into at any hour ends up with counts nobody trusts. Locking it need not slow the night shift: give the shift lead a key, keep a sign-out sheet by the door, and enter what was taken against a work order the next morning. What matters is that every part that leaves is written down.

Who should run the storeroom in a small maintenance team?

One named person, even if it is only part of their week. They receive deliveries, put parts away, enter what came in, raise orders and do the weekly counts. Anyone on the crew may take parts, but one person owns the counts and the names. When everyone owns the storeroom, nobody does.

Know what is on the shelf before the job starts.