What is asset criticality analysis?

Asset criticality analysis ranks equipment by how much a failure would hurt, so crew hours and spare parts go first where they matter. The simple method multiplies consequence by likelihood, each scored 1 to 5, for 1 to 25.

By MaintensorUpdated

Criticality as consequence times likelihood, on two 1 to 5 scales

criticality = consequence × likelihood

Consequence
how much a failure would hurt, from 1 to 5
Likelihood
how often a failure is expected, from 1 to 5

Write both scales down once, so two people scoring the same machine get the same answer. No scale is standard: NASA’s reliability-centered maintenance guide for facilities uses ten steps.

A starting scale, 1 to 5Adapt the words to your site.
Score Consequence of a failure Likelihood of a failure
1 Nobody notices; a small repair bill Not expected in the asset’s life
2 A nuisance; work goes on Less than once in 5 years
3 An area slows down or is uncomfortable About once in 2 to 5 years
4 A line or a service stops for hours, or product is lost About once a year
5 Someone could be hurt, something could be released, or the whole site stops Several times a year

Criticality example: six assets scored in one sitting

A made-up plant, scored by its supervisor and senior technician:

5Consequence
Air compressor 1: every line stops
3Likelihood
about once in 2 to 5 years
15Criticality
5 × 3, first of the six
The numbers, line by lineSix assets, highest score first. Every one is made up.
Asset Consequence Likelihood Score
Air compressor 1, no backup 5: every line stops 3 15
Walk-in cooler 4: product is thrown out 3 12
Boiler 5: no heat in winter, and a pressure vessel 2 10
Dock door 2 2: trucks can use door 3 5 10
Conveyor 1 gearbox 4: Line 1 stops 2 8
Rooftop unit, offices 2: offices get warm 2 4

The boiler and the dock door both score 10, for different reasons. The boiler’s 10 comes from a severe failure that is unlikely: its safety checks must never slip. The dock door’s comes from a minor failure that keeps happening: find its cause, or replace the door.

Read the consequence column first

Treat any asset with a 5 for consequence as critical whatever its likelihood, and let the multiplied score sort the rest.

What to do with the score

15 to 25, or any 5 for consequenceCalendar and condition checks, never skipped; its critical parts on the shelf; when it breaks, other work stops.
8 to 12Preventive work at the maker's interval; part numbers and lead times known; repaired the same or next day.
1 to 6Consider running it to failure; parts bought when needed; repaired when convenient.

The maintenance strategy guide turns the ranking into each asset’s preventive work; spare parts inventory management turns it into what to stock.

Criticality vs work order priority, risk-based maintenance and FMEA

  • Work order priority belongs to one job and says how soon; criticality belongs to the asset.
  • Risk-based maintenance uses the same idea to choose the maintenance itself, often failure by failure.
  • An FMEA scores each way a machine can fail, not the machine; run it on the top few.

Scoring the 30 to 50 assets that matter, and when to rescore

Do not score all 300 lines of the asset register, only the assets that could plausibly matter: two people who know the site can score 40 in about an hour and a half. Score again once a year, after a failure that surprised you, and when a backup is added or removed.

Maintensor has no criticality field on an asset, so keep the scores in a one-page spreadsheet beside the register, sorted highest first, and write the band (“High: no backup”) into each asset’s Description.

Questions

What people also ask.

More in the glossary, or see the whole product on the features page.

What makes an asset critical?

An asset is critical when its failure could hurt someone, harm the environment, stop production or service, or cost a lot to put right, especially with no backup. Likelihood adds to the score, but a reliable machine with no backup, such as the only air compressor in a plant, can still be the most critical asset on site.

What is the difference between criticality and work order priority?

Criticality belongs to the asset and changes rarely; priority belongs to one job and says how soon. A critical asset raises the priority of its repairs, but a low-criticality asset can still have an urgent job, such as a leak dripping onto an electrical panel.