How to choose a maintenance strategy for each asset

A maintenance strategy is the rule that decides when an asset gets work: after it fails, on the calendar, when an inspection finds a problem, or when measured trends predict one.

By MaintensorUpdated 9 min read

Key points

  • Choose it asset by asset, from what a failure costs and how the failure shows up.
  • There are four choices: run to failure, preventive on the calendar, condition-based and predictive.
  • Hidden failures, such as standby pumps and emergency lights, need a test on the calendar.
  • The made-up 12-asset sauce plant comes to 15 recurring jobs, three of them usually bought in.
  • Most small plants end up with calendar work and condition checks on what matters, and some things run to failure.

What a maintenance strategy is

A maintenance strategy is chosen per asset, and sometimes per way an asset fails, not once for the whole site. Choose it from two answers: what a failure costs (safety, production, or only the repair) and how the failure shows up (with age, with warning, at random, or hidden until needed).

The compressor that feeds every line and the restroom exhaust fan should not be looked after the same way. Treat them alike and you overspend on the fan or gamble with the compressor.

There are four choices.

Strategy What it needs Fits
Run to failure A spare, or a quick way to get one Cheap items whose failure hurts nothing
Preventive on the calendar The maker’s interval, by date or usage count, and a schedule Parts that wear with age or use: filters, belts, lubricant
Condition-based A check that can see the problem coming Failures that give warning: leaks, noise, heat, visible wear
Predictive Instruments, training and history Large machines whose early warning only instruments can see

Most small plants end up with a mix: calendar work and simple condition checks on what matters, and a few things run to failure on purpose.

Three answered steps of a checklist: a filter check passed, with the technician's note and a place to add a photo, a supply air temperature of 14 °C, and Yes chosen for a clear drain pan.
Condition checks as checklist steps: a filter check passed with the technician's note, a temperature reading, and a yes or no question.

How to choose a maintenance strategy: the decision table

Find the row for how the failure shows up and the column for what it costs.

In the last row, hidden means nobody knows it has failed until the day it is called on, such as a standby pump or a relief valve.

How it fails Safety or environment Stops production or service Repair cost only
Wears with age or use Calendar, at a cautious interval Calendar, at the maker’s interval Calendar if cheap, otherwise run to failure
Gives warning Condition checks at short intervals; predictive tools if only instruments see it Condition checks on a route; predictive tools for the biggest machines Run to failure, or a glance on rounds
Random, no warning Redesign or add a backup Backup or a spare on the shelf, then run to failure Run to failure
Hidden until needed Test on the calendar Test on the calendar Test now and then, or run to failure

Two things override the table

If a rule or the maker’s warranty sets an interval, follow it. And if nothing in a row works for a safety failure, maintenance cannot fix it: the design has to change.

Where the consequence is hard to call, score the asset’s criticality first.

Run to failure in this table is a strategy only when it is chosen. NASA’s reliability-centered maintenance guide for facilities calls it “a conscious decision” that is acceptable for some equipment, such as non-critical small motors, comfort cooling and restroom exhaust fans.

The same guide says a reliability-centered analysis has only four possible outcomes: work at an interval, work on condition, repair after failure or, when no maintenance helps and failure is not acceptable, a redesign or a backup.

The two questions behind the table

The table rests on what a failure costs and how it shows up.

1. What does a failure cost?

Safety or environment
Someone could be hurt, a fire could start, something could be released.
Production or service
A line stops, product spoils, rooms close, trucks do not leave.
The repair, and nothing else
Someone is inconvenienced and there is a bill.

A working backup lowers the cost of a failure: two pumps where one will do turns a stopped process into a switch-over. Only a backup that works counts, which is why hidden failures get a test.

2. How does the failure show up?

  • It wears out with age or use. Filters load up, belts stretch, brake pads and tires wear. NASA’s guide notes that simple, single-piece items often show a direct link between age and failure, while most complex machines show no clear wear-out age.
  • It gives warning. A noise, heat, a leak, a rising temperature, a falling pressure, visible wear. The time between the first sign and the failure sets how often to look; the P-F curve is the name for that window. To build a trend, NASA’s guide also suggests at least three looks before the failure is expected.
  • It fails at random, without warning. Control boards, some electrical parts, damage from outside. A calendar task does little here.
  • It is hidden until needed. Standby pumps, relief valves, emergency lights, fire extinguishers, a backup machine. Nobody knows they have failed until the day they are called on. NASA’s guide calls the test for these a failure-finding task.

The line between condition-based and predictive is blurry: the US Department of Energy’s O&M Best Practices Guide uses the two as one name. This guide splits them by the tool: condition-based maintenance is a person checking against a limit on a route, while predictive maintenance trends instrument readings to forecast when.

Maintenance strategy example: 12 assets at a sauce plant

A made-up plant that cooks and bottles sauces on two filling lines, one shift, ends up with 15 recurring jobs across 12 assets. Its only air compressor gets calendar service and weekly readings, a kettle motor and the main electrical panel get contractor surveys, the fire extinguishers and a backup labeler get tests on the calendar, and its restroom fans and office lights run to failure. Every asset, interval and result here is invented to show the method.

The 12 assets, one line eachWhat happens if each one fails, how it fails, the strategy and the work
Asset If it fails How it fails Strategy The work
Air compressor 1, the only one Every line stops Wears (filters, oil) and warns (heat, noise) Calendar and condition Service at the maker’s intervals, every 3 months here; weekly reading of discharge temperature and pressure
Filler, Line 1 Line 1 stops Valve seals wear with use Calendar Seal kit at the maker’s interval, every 6 months here
Conveyor 1 gearbox Line 1 stops Warns: noise, heat, oil leaks Condition Monthly: listen, check oil level, read case temperature against the maker’s limit
Conveyor 1 belts Line 1 stops Wear, visibly Condition Monthly tension and wear check; replace when worn
Kettle 1 agitator motor A batch is lost Bearing wear shows early only to instruments Predictive Vibration readings by a contractor every quarter
Main electrical panel Fire, or the whole plant goes dark Loose, hot connections show only to instruments Predictive Infrared scan by an electrical contractor once a year
Walk-in cooler Product is thrown out Warns: temperature creeps up Condition and calendar Temperature read twice a day; condenser coil cleaned every quarter
Forklifts 1 to 3 Someone is hurt Wears (tires, brakes, chains), and some faults warn Calendar Examined before use each day; the maker’s service, every 3 months here
Fire extinguishers (14) A small fire grows Hidden Calendar test Monthly visual check; yearly maintenance
Backup labeler Line 2 stops when the main labeler is also down Hidden until needed Calendar test Run it for an hour once a month
Rooftop unit, offices Offices get warm Filters and belts wear Calendar Filters and belt check every quarter
Restroom exhaust fans and office lights A nuisance At random Run to failure One spare fan motor and a box of lamps on the shelf

Forklifts and extinguishers: set by rule, not by choice

In the US, OSHA requires powered industrial trucks to be examined before being placed in service, at least daily (after each shift where they run around the clock). Portable fire extinguishers must be visually inspected monthly and given an annual maintenance check.

Read the rules that apply to your site and the makers’ manuals; in Canada, check your province’s or territory’s rules.

Added up, the plan is 15 recurring jobs: 2 daily, 1 weekly, 4 monthly, 5 quarterly, 1 twice a year and 2 yearly. The two daily ones, forklift examinations and cooler temperatures, are done by operators and kitchen staff, who each need a Full user seat to answer them in the app.

3Usually bought in
vibration, infrared, extinguisher maintenance
0Jobs for the restroom fans and office lights
15Recurring jobs in all

A plant this size does not need to own a vibration analyzer or an infrared camera. It can hire the surveys it needs, as this plan does.

How to tell a strategy is wrong

  • The same failure keeps coming back between services. The interval is too long, or the failure is random and a calendar task cannot reach it.
  • A check finds nothing for two years and no rule sets it. Lengthen the interval or drop it, unless it tests something hidden until needed, such as a standby pump or a relief valve. That test is expected to pass, so keep it.
  • A condition check passed and the machine failed a week later. The check cannot see this failure, or the interval is longer than the warning.
  • Something left to run to failure stopped a line. Its consequence was misjudged; move it to a costlier column.
  • Failures rise right after scheduled overhauls. NASA’s guide warns that an arbitrary preventive task can raise the failure rate by putting a machine back into its break-in period.

Review an asset’s strategy after each of these, and the whole list once a year. Reliability centered maintenance is the formal version, done failure by failure.

How Maintensor fits

Maintensor schedules preventive work by the calendar only. A work order repeats every so many days, weeks (on chosen weekdays), months or years. The next one is created when the last is completed, and its due date counts from the last due date, not the day the work was done.

Where a maker gives an interval in run hours, turn it into a calendar repeat from how many hours the machine runs. Round down, not up.

Condition checks work as steps on that recurring work:

  • An Inspection check. A procedure’s Inspection check is answered Pass, Flag or Fail, so write the limit into the step. A Fail asks for a note and a photo before the next step, then offers a follow-up work order and Mark asset down. It does not stop the job being closed.
  • A Number step. It records a reading, with no unit or limits. The value stays on that work order’s checklist: nothing charts it over time.
  • A contractor’s report. It can be attached to the work order as a file.

Run-to-failure assets still get reactive work orders. Reporting (Pro and Max, Admins only) lists the five assets with the most unplanned downtime, counted by the clock with nights and weekends included, with their reactive work orders, MTBF and repair cost. That is where a wrong call shows up, if the asset was marked down when it stopped.

What it does not do

There are no meter, run-hour or condition triggers, no sensors and nothing predictive. There is no strategy or criticality field on an asset: note the decision in its Description.

Questions

What people also ask.

More in the blog, or see the whole product on the features page.

What are the main maintenance strategies?

There are four: run to failure, chosen on purpose; preventive work on the calendar or by usage; condition-based work, where an inspection or reading against a limit triggers the job; and predictive work, where measurements are trended to forecast a failure. Reliability centered maintenance is a method for choosing among them, not a fifth strategy.

What is the difference between condition-based and predictive maintenance?

Both act on the machine's condition rather than the date. Condition-based maintenance compares a check with a limit: the belt is cracked or the temperature is over the maker's limit, so it gets fixed. Predictive maintenance trends measurements, usually from instruments such as vibration analyzers, to estimate when a fault will become a failure. Many sources use the two names for the same thing.

Is run to failure ever a good maintenance strategy?

Yes, when a failure hurts nobody, stops nothing that matters, damages nothing else and costs less to fix than to prevent. Restroom exhaust fans and office light fixtures are common examples. Make it a written decision, keep the part on the shelf if waiting for it would be a nuisance, and change the decision if the item turns out to matter.

Which maintenance strategy should a small team start with?

Start with calendar work from the makers' manuals on the assets that stop production or can hurt someone, and add simple condition checks to those visits: look, listen, feel and take a reading. Test standby equipment on a schedule. Leave the rest to run to failure on purpose. Predictive tools come later, for a few large machines, often through a contractor.

How often should a maintenance strategy be reviewed?

Look again at an asset's strategy after any failure it should have prevented, and review the whole list once a year. The signs it is wrong: the same failure returns between services, a check, other than a safety or standby test, finds nothing for years, a condition check passes days before a breakdown, or an item left to run to failure turns out to stop a line.