What is the P-F curve?

The P-F curve shows how a failure develops, from P, where a fault can first be detected, to F, where the machine stops doing its job. The P-F interval between them sets how often to inspect.

By MaintensorUpdated

How the P-F curve runs from a hidden fault to a failure

Draw a machine’s condition against time. The line runs flat while the machine is healthy, and a fault begins, often unseen. At P, the potential failure, the fault can first be detected. The line then falls, usually faster and faster, to F, the functional failure, where the machine no longer does its job, which can be well before it breaks.

The interval belongs to a failure and a way of detecting it together. On a rolling bearing, a vibration analyzer usually sees a defect before a temperature reading does, and a temperature reading before a noise anyone can hear: the earlier the P, the longer the interval.

How it sets inspection frequency

least warning = P-F interval − inspection interval

P-F interval
the time from the first detectable sign to the failure, for one failure and one way of looking
Inspection interval
the time between checks; at worst, the fault becomes detectable the day after one

If the inspection interval is longer than the P-F interval, some failures begin and end between two checks.

Inspect at no more than half the P-F interval

That is the usual convention in reliability-centered maintenance, and it leaves at least half the interval as warning. It is a rule of thumb, not a law: the half leaves time to act and allows for the interval being a guess, made from the crew’s memory, the maker’s guidance and your history.

P-F curve example: three ways to catch a conveyor bearing fault

A made-up conveyor’s drive bearing takes a weekend shutdown to change, and a new one takes 2 weeks to arrive. The least warning each way of finding the fault leaves, checked at half its P-F interval:

2 daysA noise someone hears
4-day P-F, listened for every 2 days
1 weekBearing temperature
2-week P-F, read weekly
6 weeksVibration route
12-week P-F, a contractor every 6 weeks

Only the vibration route leaves time to order the bearing and wait for a weekend. The weekly temperature reading works only with a spare bearing on the shelf. A monthly reading, twice its P-F interval, would miss about half of these failures. Every number is a made-up estimate.

The P-F curve vs condition-based work and scheduled replacement

  • It is the reasoning behind condition-based maintenance: it says how often condition monitoring readings must be taken to be useful.
  • Scheduled replacements, such as a filter change, take their interval from the part’s wear-out life instead.
  • It is not how often the machine fails. That is mean time between failures. A machine that fails rarely but with little warning still needs frequent checks.

The predictive maintenance guide covers the interval and its sources, including how far to shorten checks once a reading passes its alert level.

A P-F interval as a calendar repeat in Maintensor

Maintensor schedules inspections by the calendar: a recurring work order repeats Daily, Weekly, Monthly or Yearly, each every 1, 2 or more, so an interval of 6 weeks is a weekly repeat every 6. It does not know P-F intervals, takes no readings from sensors, and creates nothing from a condition.

A failed Inspection check asks for a note and a photo and offers a follow-up work order, which is how a fault found at P becomes a planned repair.

Questions

What people also ask.

More in the glossary, or see the whole product on the features page.

What is a good P-F interval?

There is no good or bad P-F interval in itself. What matters is that the warning left after your inspection interval is longer than the time you need to act: to get the part, plan the job and schedule the downtime. A short P-F interval calls for frequent checks or a technique that sees the fault earlier.

Does the P-F interval apply to every failure?

The P-F interval applies only to failures that give some warning that can be detected, such as wear, fatigue, contamination and loosening. Failures that come without warning, or that cannot be seen by any practical check, need a different answer: a scheduled replacement, a redesign, a spare, or a decision to run to failure.