Key points
- SAE JA1011 sets seven questions a process must answer to be called RCM.
- RCM can remove preventive tasks: overhauls that do not reduce failures, and checks that cannot find anything.
- In Nowlan and Heap's 1978 study, 11% of aircraft items might benefit from an age limit; 89% could not.
- Hidden failures, such as a standby pump that will not start, get a test on a schedule.
- A small plant can do a lighter version on one critical machine in about an afternoon.
What RCM is, and what it is not
RCM picks among the types of maintenance for each function of each asset.
Done in full, to the SAE JA1011 standard, RCM is a team exercise with a trained facilitator and many sessions. A small plant can do a lighter version on a critical machine in about an afternoon.
Three things RCM is not:
- Not more preventive maintenance. It can remove overhauls that do not reduce failures and checks that cannot find anything. The U.S. Department of Energy’s O&M Best Practices Guide (section 5.5) counts eliminating unnecessary maintenance or overhauls among its advantages.
- Not FMEA. A failure modes and effects analysis lists how something fails and what happens. RCM uses that list, then decides what to do about each line.
- Not predictive maintenance. RCM chooses a condition check where a failure gives warning, and predictive maintenance is one way to do that check. Where no warning exists, RCM picks something else.
What it gives a site: tasks that match how things fail, the hours back from tasks that prevent nothing, and a scheduled test for hidden failures nobody would notice.
RCM example: one pump analyzed in an afternoon
A small team can get much of RCM’s value on one asset in about four hours.
Everything in this example is made up, including the limits. A plant has two 15 hp (11 kW) centrifugal cooling water pumps, P-3A running and P-3B on standby. In the room: Ben Carter, the mechanic who repairs them; Luis Ortega, the line lead whose molding machines they cool; and Maria Chen, the maintenance supervisor, with the pumps’ last three years of work orders printed out.
- Write the function, with numbers (30 minutes). “Deliver at least 250 gpm (950 L/min) of cooling water at 55 psi (380 kPa) to the chillers of six molding machines, around the clock, without leaking onto the floor.”
- List what has gone wrong, and what could (60 minutes), from the work orders, the parts used and the people in the room.
- Effects and consequences (45 minutes). For each cause: what would we see, and what would it cost?
- Tasks and intervals (60 minutes). Pick a task for each line, from the six in the table further down, which also explains the task names used below.
- Put it on the schedule (45 minutes), each task a recurring work order with a checklist and an owner.
The worksheet they ended with:
The seven lines, with tasks and intervalsFailure mode, effect, consequence, task, how often and who
| Failure mode | Effect | Consequence | Task | How often | Who |
|---|---|---|---|---|---|
| Mechanical seal wears | Drip grows to a spray; water on the floor | Slip hazard, then operational | On-condition (a check for warning signs): look at the seal; any steady drip is a Fail | Weekly | Line lead, on rounds |
| Bearing runs short of grease or wears | Noise and heat, then a trip; P-3B must start | Operational, brief if P-3B starts | Grease to the maker’s interval and amount; on-condition: bearing temperature and sound | Greasing per the manual; reading monthly | Mechanic |
| Impeller wears or clogs | Pressure falls; molds run warm (a partial failure) | Operational: scrap and slower cycles | On-condition: discharge pressure against the 55 psi baseline; below 48 psi (330 kPa) is a Fail | Monthly | Mechanic |
| Suction strainer clogs | Flow falls; pump may cavitate | Operational | Scheduled: clean the strainer | Monthly, adjusted to what is found | Mechanic |
| Coupling insert wears | Noise, then loss of drive | Operational | On-condition: inspect the insert and check alignment | Quarterly | Mechanic |
| P-3B will not start when needed | Nothing, until P-3A fails | Hidden, then no cooling | Failure-finding: switch duty to P-3B and run it | Monthly | Mechanic |
| Motor winding fails | Motor trips and will not restart | Operational, covered by P-3B | Run to failure; keep one spare motor on the shelf | Not applicable | Supervisor, for the spare |
What changed: seven lines with reasons replaced “quarterly pump service: check everything.” One hidden failure came up, because nobody had run P-3B in a year. The old service’s yearly teardown went, because the room could name no failure mode it would catch that the new checks would not.
What the lighter version leaves out
It covers the failure modes the room could think of, not a systematic search, and it skips formal documentation of every consequence. It is not RCM under SAE JA1011.
Not for systems where a failure could hurt someone
Pressure systems, lifting equipment and fire protection follow their codes, their makers and the rules that apply to them, and deserve a full analysis.
Start at the top of your criticality ranking, one a week. Five machines reviewed this way tell you more about your maintenance strategy than a binder of generic PMs.
Review a machine again when it is modified, moved or run harder, and before its replacement is bought (see asset lifecycle management).
The seven questions of RCM, step by step
Under SAE JA1011, an RCM process must answer seven questions. The U.S. Defense Department’s RCM manual (DoDM 4151.22-M, 2011, since reissued as DoDM 4151.25) walks the same sequence.
- Functions. What must the asset do, and to what standard, in the place and way it is used now? NASA’s RCM guide for facilities (section 4.1.2) says it is not enough to say a pump moves water: state its flow, pressure and the other numbers that matter. It also notes that two identical exhaust fans, one serving a restroom and one part of a smoke purge system, need different maintenance. That setting is the operating context, and it changes what a failure means.
- Functional failures. In what ways can it fail to do that? The DoD manual separates total failures (a pump that stops) from partial ones (a pump that delivers 180 gallons a minute when the process needs 250).
- Failure modes. What causes each functional failure? A seal that wears, a bearing that runs dry, a strainer that clogs. The DoD manual limits the list to modes reasonably likely in the operating context, and names four kinds to include: modes that have happened before, real possibilities not yet seen, unlikely ones that would be severe, and modes already managed by a task.
- Failure effects. What happens when each failure occurs?
- Failure consequences. In what way does each failure matter?
- Proactive tasks. What should be done, and how often, to predict or prevent each failure?
- Default actions. What should be done if no suitable proactive task can be found?
The standard: SAE JA1011
SAE JA1011, “Evaluation Criteria for Reliability-Centered Maintenance (RCM) Processes”, sets the minimum a process must do to be called RCM. It does not prescribe a worksheet; it says what questions the process must answer. This page works from the 2009 edition, and a November 2024 revision is now listed, so check that one if you need to claim conformance.
Effects and consequences
The effect is what you would see and hear, and what stops. The consequence is how much it matters, and it drives the task. The usual groups:
- Hidden. Nobody notices the failure until something else fails too: a standby pump that will not start, a relief valve stuck shut.
- Safety and environment. Someone could be hurt, or a rule on releases could be broken.
- Operational. Output, quality or customers suffer.
- Non-operational. Only the repair costs money.
Choosing the task
The task follows from the consequence, and from whether the failure gives warning. Questions 6 and 7 come down to these six:
| Task | When it fits | Example |
|---|---|---|
| On-condition (a check for warning signs) | The warning sign can be detected, the time from warning to failure is fairly consistent, it is practical to check more often than that, and the warning leaves time to act | Monthly bearing temperature; weekly look at a pump seal |
| Scheduled restoration | Failure becomes more likely with age, most units live to that age, and restoring brings resistance to failure back to an acceptable level | A rebuild at a set number of years or hours |
| Scheduled discard | As above, but the part is replaced instead of restored | A filter cartridge or a hose with a known life |
| Failure-finding | The failure is hidden; the task tests whether a protective device still works | Running the standby pump; testing a smoke detector |
| Run to failure | No task is worth its cost, and the consequences are tolerable | A small exhaust fan with a spare on the shelf |
| One-time change | No task makes a safety or environmental risk tolerable | A redesign, a guard, a new operating procedure, training |
The first three rows follow the DoD manual. A check’s interval comes from the P-F interval: the time between the first detectable sign and the failure.
The six failure patterns
Parts fail in six patterns over their life, and only two show a clear wear-out age, so a timed overhaul helps only those and can make the rest worse. That lesson comes from the airlines.
In the 1960s and 1970s, airline engineers found that overhauling aircraft parts at fixed ages did not make many of them more reliable. In 1978 F. Stanley Nowlan and Howard F. Heap of United Airlines wrote up the method that came of it, for the U.S. Department of Defense, as Reliability-Centered Maintenance. It spread to the military, power plants, process plants and facilities.
Nowlan and Heap plotted how the chance of failure changed with age for each aircraft part United Airlines had data on, and found six patterns. Only two show a clear wear-out age, and they are mostly simple items, such as tires and brake pads. Complex items mostly show none.
NASA's guide, bluntly
“In many cases scheduled overhaul increases the overall failure rate by introducing a high infant mortality rate into an otherwise stable system.”
For most complex machines, checks of condition and careful work at installation and repair do more than a calendar overhaul.
The six patterns, with the aircraft percentagesFrom the 1978 report. They describe aircraft parts and do not transfer to your plant.
Exhibit 2.13 of the 1978 report:
- A: high when new, then steady, then rising steeply (the bathtub curve). 4% of items studied.
- B: steady or slowly rising, then a clear wear-out age. 2%.
- C: slowly rising, with no clear wear-out age. 5%.
- D: low when new or just repaired, then rising quickly to a steady level. 7%.
- E: steady at all ages (random). 14%.
- F: high when new, then dropping to a steady or very slowly rising level. 68%.
11% might benefit from an age limit; 89% could not. That is the report’s own summary: patterns A, B and C add up to 11%. Only A and B show a clear wear-out age.
These are aircraft parts from one airline, decades ago. NASA’s guide (section 4.1.5) sets them beside a 1973 study in Sweden and a 1982 U.S. Navy study: across the three, 8 to 23 percent of failures were related to age.
Do not apply the percentages to your plant.
RCM’s raw material in Maintensor
Maintensor is equipment maintenance software that holds the history behind the analysis and the tasks that come out of it. The analysis itself lives on paper or in a spreadsheet.
- The asset’s work. Its record has its work orders and its parts. When one part has been used on it three or more times this year, the record says so: a failure mode asking to be on the worksheet.
- Where to start. On Pro and Max, an admin’s Reporting lists the five assets with the most unplanned downtime, counted by the clock with nights and weekends included, with their MTBF: a fair place to choose which machine to review first.

The tasks become recurring work orders with procedures as checklists. A condition check is an Inspection check answered Pass, Flag or Fail. A Fail asks for a note and a photo before the next step and offers a follow-up work order, though the job can still be closed without them.
A Number step has no unit or limit of its own, so the limit goes in the step’s wording. Only Admins and Full users answer checklists, so the line lead’s weekly look at the seal needs a user seat if it is done in the app.
What it does not do
There is no RCM or FMEA worksheet, no failure codes and no criticality field on an asset.