Run to failure as a deliberate choice, in NASA’s words
NASA’s reliability-centered maintenance guide for its facilities (2008) defines run to failure as taking no time- or cycle-based action to prevent failure after installation. Its candidates “are usually low-cost, easily repaired, and non-critical,” and the guide says plainly that run to failure “is a conscious decision and is acceptable for some equipment.”
When it is the right plan
Run an item to failure only when all five answers point that way:
NASA’s own examples include non-critical electric motors under 7.5 hp, comfort cooling, restroom exhaust fans and small, low-temperature water heaters.
A standby is not a spare until it is tested
A duty pump can run to failure only if its standby is run and switched over on a schedule: a standby fails while it sits idle, and nobody finds out until the duty pump stops. The maintenance strategy guide has a decision table for the rest.
When it is just neglect
- Nobody decided: the item is on no list, just whatever nobody got to.
- There is no spare and no supplier lined up, so a cheap failure waits three days.
- The failure is hidden, as with emergency exit lights or a basement sump pump.
- The list is never reviewed: an item that fails every month has a cause to fix, or needs another plan.
Run-to-failure example: 200 aisle lights, checked or not
A warehouse has 200 LED light fixtures in its aisles, and about 4 fail a year. Each costs $90 and takes 30 minutes to swap at $45 an hour. The numbers are made up.
a minute each: about 13 h a year at $45
4 × ($90 + $22.50)
And no check stops an LED driver from failing. Run them to failure, keep six on the shelf, and ask whoever notices a dead one to report it.
Run to failure vs reactive, corrective and preventive work
- Reactive maintenance follows any breakdown; run to failure is reactive by choice. The types of maintenance guide places it among the rest.
- Corrective maintenance is any repair of a fault; run to failure produces nothing else.
- Preventive maintenance is the alternative for items that fail any of the five questions.
Recording a run-to-failure decision in Maintensor
Maintensor has no run-to-failure setting, and an asset has no criticality field, so write the decision in the asset’s description, where anyone opening the record sees it. When the item fails, a requester reports it or a technician opens a Reactive work order on it, and marking the asset Down records the unplanned downtime, with an optional reason.
When one part has been used on an asset three or more times this year, its record warns: “Check for a recurring fault.” That is the signal to review the decision.