Corrective maintenance by how a fault is found and how soon it is fixed
Two questions sort every corrective job: how the fault was found, and how soon it is fixed.
| Found by | Fixed | Example | Often called |
|---|---|---|---|
| A breakdown | Now | Conveyor motor seizes mid-shift | Reactive, breakdown, emergency |
| A breakdown | Later | Dock door opener fails; the door runs by hand until the new opener comes Friday | Reactive, deferred |
| An inspection | Now | Forklift horn fails the pre-shift check; the truck is parked until fixed | Immediate corrective |
| An inspection | Later | Gearbox seal found weeping, replaced at the weekend | Planned or deferred corrective |
Many crews use reactive and corrective as one word. Strictly, reactive is the top half of the table, and the bottom half is where a good preventive program moves the work.
Corrective maintenance example: 30 jobs, 40% found before failure
A made-up plant closes 30 corrective work orders in a quarter: 18 start with a breakdown, costing 41 hours of stopped equipment, and 12 with a fault found on an inspection or by an operator, each booked for a break or a weekend. The supervisor adds a weekly walk of the two machines that broke down most.
12 ÷ 30 jobs
down from 41
15 ÷ 28 jobs
The count of repairs barely moved; what changed is how much of it happened on the crew’s terms.
The follow-up work order
When an inspection finds a fault, the fix gets its own work order instead of being done quietly on the inspection. The inspection then closes on time with its finding, the repair gets its own parts, time and priority, and the asset’s history shows the fault, so a repeat is visible.
One fault, one work order
Two problems on one record means one gets forgotten. Write what was found and, if known, why it failed: “Replaced” is not a finding. The work order guide covers writing one a technician can act on.
Corrective vs preventive, run-to-failure, emergency and deferred work
- Preventive work is done before a fault, on a schedule; the types of maintenance guide sets the two side by side.
- Run to failure is corrective work by design: nothing is done until the item breaks.
- Emergency maintenance is corrective work that cannot wait.
- Deferred maintenance is work put off past its due date, where corrective repairs that can wait often end up.
From a failed check to a follow-up work order in Maintensor
In Maintensor, an Inspection check answered Fail shows “This step failed”, and the technician cannot move on until they add a note and a photo. They can then press Create follow-up work order, and it is created as a Reactive work order.
It comes filled in: a title naming the failed step and the asset, a priority (High unless changed to Medium or Low), the same asset and location, and a description naming the work order and step it came from, with the note.

There is no separate Corrective type, and no failure codes or cause fields: the cause goes in the notes.