What is deferred maintenance?

Deferred maintenance is maintenance and repair work that was due and was put off, most often for lack of money, people or a shutdown window. Most items cost more the longer they wait.

By MaintensorUpdated 10 min read

Key points

  • Deferred work grows: damage spreads, work done on failure costs more, and the crew falls further behind.
  • List it by walking the building system by system, one priced line per problem, redone every year.
  • The facility condition index is the cost to correct deficiencies divided by current replacement value.
  • Life safety and code items go first; score the rest on consequence times likelihood.
  • In the school example, $590,000 of deferred work on a $14 million building is an FCI of 4.2%.

What counts as deferred maintenance

Deferred work is one of the types of maintenance: work that was due and was put off to a later date.

In a building, deferred maintenance collects as a list of known problems: a roof past its life, a boiler out of service, a broken-up parking lot. That list must be written down, priced and ranked.

The US federal definition: SFFAS 42It works for any building, and it says why a new wing does not count

The federal definition: SFFAS 42

US federal accounting has a definition that works for any building. The Federal Accounting Standards Advisory Board’s standard (SFFAS 42, paragraph 7) describes deferred maintenance as maintenance and repairs “that were not performed when they should have been or were scheduled to be and which are put off or delayed for a future period.”

Paragraph 8 leaves out work that expands or upgrades an asset, so a new wing is not deferred maintenance; the worn roof over the old wing is. Management decides what condition is acceptable.

A deferral can be planned or unplanned:

Planned
Someone chose to wait, wrote down why, and set a date to look again.
Unplanned
Work that did not get done, with no decision and no date. It usually comes to light when something fails.

Even a small planned deferral can be written down, here as a declined request: who decided, why and until when.

A declined request: declined by the maintenance manager the next morning, with the reason that the contractor does floor marking in the November shutdown.
A request declined with its reason: the contractor does the floor marking in the November shutdown.

Three things get mixed up with deferred work:

  • The backlog. The maintenance backlog is all approved work not yet done, including jobs due next week. Deferred items are the part pushed past their due date, often by years.
  • A missed PM. A skipped filter change is not owed twice: you do the next one. NASA’s reliability-centered maintenance guide for its facilities draws this line in its glossary: when a task on a cycle longer than a year, such as repainting every fifth year, is missed, the work is still owed. Missed PMs still turn small faults into big items on this list.
  • Capital projects. A roof replacement paid from a capital budget is still deferred maintenance if it should have been done and was not.

In property sales the term means the repairs a buyer inherits. The idea is the same.

Deferred maintenance examples, and why work gets put off

  • Roofs. Costly, and out of sight. Small leaks wet the insulation and ceilings, then the deck.
  • Boilers, chillers, rooftop units. Still running, and replacing one needs a capital request. They fail in the season they are needed, with rentals and overtime.
  • Sealant, flashing, windows. Nobody notices until water gets in. Then water damage, mold, rot.
  • Paving. Seasonal, and looks cosmetic. Water gets under the surface and breaks up the base.
  • Plumbing. Hidden in walls. The leak is found by the ceiling below.
  • Fire alarm panels, switchgear. Works until it does not, and parts get scarce. Long outages when no part is made.
  • Floors, finishes, restrooms. Lowest on any list. Wear spreads; complaints grow.

The reasons are usually the same few:

  • The budget is set a year at a time. A budget built from the work shows what each cut stops.
  • Repairs compete with what people can see. The GAO found some school districts putting security upgrades ahead of replacing systems such as HVAC.
  • The crew is busy with breakdowns, so planned repairs slip and cause more.
  • The work needs a window: a shutdown, a school vacation, an empty floor.
  • Nobody wrote it down, so nobody knows how big it is.

41 percent of school districts

From a national survey of school districts in 2019 (GAO-20-494, published in 2020), the GAO estimated that 41 percent of districts needed to update or replace HVAC systems in at least half their schools.

Why deferred maintenance costs more the longer it waits

Waiting costs more in three ways: damage spreads, work done on failure costs more, and the crew falls further behind.

Damage spreads
At about half of the 55 schools the GAO visited for the same report, officials described HVAC problems, such as older systems that leaked and damaged floors or ceiling tiles.
Work done on failure costs more
Overtime, rush parts, rented equipment and a contractor’s emergency rate all arrive together.
The crew falls further behind
Every emergency pushes planned work back, and deferred work produces the next emergency.

ExampleA loose length of roof flashing

With made-up figures: fixed this fall, a length of loose flashing is a $1,500 job. Left for two winters, it adds wet insulation and membrane ($6,000) and ceiling tiles and paint ($2,500). That is $10,000, and a classroom closed for a week.

How to list and price a deferred backlog

  1. Walk the building by system: roof, exterior walls and windows, heating and cooling, plumbing, electrical, fire and life safety, elevators, interiors, and the site. Bring last year’s work orders and complaints.
  2. Write one line per problem: what it is, where, what you saw, and what happens if it fails. “Boiler 2 out of service, cracked section; boiler 1 carries the building” beats “boiler issues”.
  3. Note when it became due, or the year it was first written up.
  4. Price it from a contractor quote, a recent invoice or a published cost guide, and note which. Add design and permit costs to the big jobs.
  5. Rank it (below).
  6. Total it and date it. Redo it every year, adding new items and striking finished ones.

The formal version is a condition assessment: the US federal standard SFFAS 42 (paragraph 10) describes periodic visual inspections that record current condition and the estimated cost to correct deficiencies. Large owners hire engineering firms for them. A small building can do its own with the crew, plus a roofer and a boiler contractor for the parts they know best.

The facility condition index

The facility condition index (FCI) turns the priced list into one number, the share of the building’s replacement value owed in repairs:

FCI = cost to correct deficiencies ÷ current replacement value

Cost to correct deficiencies
the priced deferred list, totaled
Current replacement value
the cost to build a new building of the same size on the same site

Zero means nothing is deferred, and higher is worse. There is no single official scale, so compare a building with itself from year to year, and with your other buildings priced the same way.

Where the index comes from, and how far to trust itThe school data guide's formula and warning, and NASA's scale

The National Center for Education Statistics (NCES) gives the FCI formula in its guide to school facilities data, and notes that the college business officers (NACUBO) and facilities officers (APPA) adopted it. It works out replacement value as gross square feet × the cost per square foot to build new.

NCES points out that when the FCI of a school passes 1, it “may be more cost-effective to replace it rather than modernize it.” It also warns that both estimates are “very susceptible to manipulation”: whoever wants a new building can inflate the repairs and shrink the replacement cost.

NASA’s facilities guide notes that NASA reports FCI on a 1 to 5 scale, where 5 is the best condition, while others use a percentage.

How to prioritize deferred maintenance: life safety first, then a score

Life safety is not ranked

Life safety and code items are not ranked against anything. Fire alarm, emergency lighting, exits, sprinklers, and anything an inspector would cite go first.

Score the rest on two questions, each from 1 to 3, and multiply:

Consequence if it fails
3: it closes the building or stops the operation. 2: damage spreads or the cost climbs fast. 1: comfort or appearance.
Likelihood in the next two years
3: likely or already failing. 2: possible. 1: unlikely.

Break ties by consequence first, then by how fast the cost grows while it waits. Look for partial fixes, such as a temporary roof patch that holds until the replacement.

Deferred maintenance example: a small school, priced and ranked

Maple Ridge Elementary is made up, and so is every number below. It is a one-story school of 40,000 square feet (about 3,700 m²). At an assumed $350 a square foot to build new, its replacement value is 40,000 × $350 = $14,000,000. Hannah Lee, the facilities lead, walks it with her crew and two contractors.

The eight items, ranked and priced$590,000 in all, with the fire alarm panel first
Item System Consequence × likelihood Cost to fix
Fire alarm panel: the maker no longer supplies parts Life safety First $48,000
Boiler 2 of 2 out of service, cracked section Heating 3 × 2 = 6 $120,000
Gym roof: membrane past its life, two active leaks Roof 2 × 3 = 6 $210,000
North wall sealant and window caulk failing Exterior 2 × 2 = 4 $35,000
Parking lot cracked, two potholes Site 2 × 2 = 4 $40,000
Library rooftop unit, 26 years old Cooling 1 × 3 = 3 $65,000
Four restrooms: fixtures and partitions worn Interior 1 × 2 = 2 $52,000
Gym floor refinish overdue Interior 1 × 1 = 1 $20,000
Total $590,000
$590,000Cost to correct
the eight items
$14MReplacement value
40,000 sq ft × $350
4.2%FCI
590,000 ÷ 14,000,000 = 0.042

A low FCI can hide one bad system, so read it beside the list: this 4.2% includes a boiler out of service. The boiler and the gym roof tie at 6, and the boiler goes first: if boiler 1 fails in January, the school closes, while the roof leaks can be patched for now. The parking lot’s two potholes get patched this month from the operating budget, about $3,000.

Hannah also assumes new items will come due as other systems age, about $120,000 a year, and sets out three options for the board, ignoring inflation:

Option Spent over 3 years List after 3 years FCI after 3 years
Do nothing $0 590,000 + 360,000 = $950,000 6.8%
$100,000 a year $300,000 950,000 − 300,000 = $650,000 4.6%
$200,000 a year $600,000 950,000 − 600,000 = $350,000 2.5%

At $100,000 a year the list still grows. The do-nothing row is also too kind, because the gym roof’s repair gets bigger every winter it leaks, and it is there only to price the choice: it leaves life safety work unfunded, which nobody should accept.

A wider check is the National Research Council’s 2 to 4 percent of replacement value a year, which the GAO recommended for NASA’s facilities in 1990, here $280,000 to $560,000 for all maintenance and repair. It comes from large federal portfolios, so for one school it is a sanity check, not a budget, as the maintenance budget guide explains.

How to get deferred maintenance funded

Give a board one page and a decision, not 80 line items:

  • The total and the FCI, this year and last.
  • The top five items, each with what happens if it fails: “If boiler 1 fails in January, the school closes until a rental boiler is hooked up.”
  • The cost of waiting: temporary patches, spreading damage, rising prices.
  • Two or three funding options and the list in three years under each, as in the table above.
  • What you will do anyway: the preventive work that slows the list down.
  • What you need: a decision, and written acceptance of the risk on anything not funded.

Keeping the list from growing

  • Keep the preventive work going. An old roof needs its drains cleared more, not less. The facility maintenance checklist has the routine checks.
  • Record every deferral as a decision: who decided, why, and until when.
  • Never defer life safety.
  • See the big replacements coming. List each major system with its age and expected life, to budget for what is due in the next ten years. Asset lifecycle management covers the records.
  • Spend small money to stop big damage: a patch, a drip pan, a weekly look at the worst items.
  • Redo the list every year, and keep the old ones so the trend is visible. The facility maintenance guide covers the rest of running a building.

Tracking deferred work in Maintensor

Maintensor keeps the work, not the capital plan.

  • One work order per item, with a priority, a category such as Deferred, and no due date, so it waits in the No due date group of the active list. One already started can be put On hold.
  • One building’s list. Filter by category and location. Locations nest, by wing and room.
  • The cost to fix. Write it in the description, with where the number came from: a work order’s estimate is in hours, not dollars.

When staff report something that will wait for a shutdown, an admin can decline the request with a reason the requester reads on their own list.

On Max, contractor and other costs with their receipts add up per work order and per asset as the work gets done; below Max, an asset’s costs are parts only.

What it does not do

There is no facility condition index, no replacement values, no capital budget or multi-year plan, and no export, so the board’s page is written outside it. An asset has no purchase date, warranty or cost fields.

How a buildings team uses it day to day is on the facility maintenance software page.

Questions

What people also ask.

More in the blog, or see the whole product on the features page.

Is deferred maintenance the same as a maintenance backlog?

Deferred maintenance is not the same as a maintenance backlog, though they overlap. The backlog is all approved work not yet done, including jobs due next week. Deferred maintenance is the part that was due and was pushed back, often by a year or more, and often because it is too big for the operating budget: a roof, a boiler, a parking lot.

What is a good facility condition index?

There is no single official pass mark for the facility condition index. Lower is better: zero means nothing is deferred. Owners set their own bands, and NASA even reports it on a 1 to 5 scale. NCES notes that above 1, replacing a school may cost less than fixing it. The useful reading is your own building's trend from year to year.

How do you calculate deferred maintenance?

To calculate deferred maintenance, walk the building system by system, write down each problem that should already have been fixed, and price each one from a contractor quote, a recent invoice or a cost guide. The total is the deferred maintenance figure. Divide it by the building's replacement value to get the facility condition index, and redo both every year.

Is it ever right to defer maintenance?

Deferring maintenance is sometimes the right call: when the building will be sold, closed or renovated soon, when the work needs a shutdown that is months away, or when a cheaper temporary fix holds safely until then. Life safety work is never deferred.

Run one building through it.

Start the trial, add one building with its floors, rooftop units and boiler, and invite the people who report problems as requesters, free on every plan.

30-day free trial. No credit card.