Maintenance budget: how to build one from the bottom up

A maintenance budget is the year's planned spending on keeping equipment and buildings working: labor, parts, contractors, tools and a reserve. Build it from your asset list and last year's work orders, then track it monthly.

By MaintensorUpdated 11 min read

Key points

  • It has five lines: labor, parts, contractors, tools and training, and a contingency priced by a quote.
  • Build it from the asset list, the preventive schedule and last year's work orders.
  • Check the planned hours against the hours logged on work orders last year, not the hours paid.
  • In the worked example, the crew's pay is 74 percent of the budget and mostly stays put.
  • The 2 to 4 percent of replacement value rule was written for many buildings, not one small site.

What a maintenance budget covers

A maintenance budget is an operating budget: the money to keep what you have working for twelve months. It has five lines.

Line What it holds
Labor Straight-time pay with payroll taxes and benefits, plus overtime
Parts Preventive parts, repair parts, spares to stock
Contractors Contracts and call-outs for work your crew does not do
Tools, training and rentals Tools, courses, a rented lift
Contingency A failure you can name but cannot date, priced by a quote

Build it from the work, not from a percentage of what the site is worth, and track it monthly, so a line running over shows up in March, not December.

New equipment, expansions and big replacements usually go in the capital budget, and accounting rules draw the line. Ask your accountant which side each big job goes on before the year starts.

Repair or improvement: what the tax rules sayThe US and Canadian tests, with a link to each

Repair or improvement is a tax question too. In the United States, the IRS’s tangible property regulations treat a betterment, a restoration or an adaptation to a new use as an improvement to capitalize. They give a safe harbor for routine maintenance: recurring work that keeps property in its ordinarily efficient operating condition.

In Canada, the CRA’s business income guide asks whether a cost gives a lasting benefit, and whether it restores a property or improves it beyond its original condition.

How to build a maintenance budget in seven steps

  1. Group the assets, with a count, from your asset register: a budget needs groups, not serial numbers.
  2. Add up preventive hours and parts for each group, from your preventive maintenance schedule.
  3. Count last year’s repairs from the work orders: hours logged, parts used. Adjust for known changes, such as a machine replaced or a shift added. Take credit for fewer breakdowns only once a year of records shows it.
  4. Check the hours against the crew’s logged hours from last year. A gap becomes overtime, a contractor or a hire, and the budget says which.
  5. Price the labor. Straight time is people × paid hours × loaded rate, the loaded rate being the wage plus payroll taxes and benefits. Overtime comes from last year’s call-ins.
  6. List the contractors by trade, each with its contract, a quote or last year’s call-outs.
  7. Name the contingency: the failure most likely to land this year that no other line covers, priced by a quote.

Then set the total beside last year’s actual spending, with a sentence for each line that moved.

Maintenance budget example: a plant with a crew of three

Riverside Plant’s budget comes to $419,660. The plant and every number here are made up, and round, to show the arithmetic. It is one building with two packing lines. Maria Chen manages maintenance with three technicians: Ben Carter, James O’Neil and Ana Kovac. At this plant Maria’s own pay sits in plant overhead, so it is not in this budget. Where your manager sits is a question for finance.

The total

Line Amount
Labor $309,600
Parts $56,560
Contractors $33,000
Tools, training and rentals $8,500
Contingency $12,000
Total $419,660

Nearly three quarters is the crew’s pay (309,600 ÷ 419,660 = 74 percent). Its straight time, $299,520, hardly moves whatever the year brings. Everything else, 419,660 − 299,520 = $120,140, is where surprises land.

Here is where each line comes from.

The preventive work, from the schedule

The schedule’s seven groups come to 1,024 hours and $21,360 of parts a year.

The schedule, group by groupEach group's count, its services, its hours and its parts.
Asset group Count Schedule, each asset Hours a year Parts a year
Packing machines 8 Monthly service 4 h, yearly overhaul 16 h 8 × (12 × 4 + 16) = 512 8 × (12 × $45 + $600) = $9,120
Conveyors 14 Quarterly check 2 h 14 × 4 × 2 = 112 14 × $150 = $2,100
Air compressors 3 Monthly check 1 h, yearly service 8 h 3 × (12 × 1 + 8) = 60 3 × $900 = $2,700
Forklifts 4 Quarterly service 3 h 4 × 4 × 3 = 48 4 × 4 × $120 = $1,920
Rooftop units 6 Quarterly filters 2 h, belts once a year 6 × 4 × 2 = 48 6 × (4 × $60 + $80) = $1,920
Dock doors and levelers 6 Quarterly check 1.5 h 6 × 4 × 1.5 = 36 6 × $100 = $600
Building rounds 1 route Weekly 4 h 52 × 4 = 208 Lamps and plumbing parts, $3,000
Total 1,024 h $21,360

Repairs, from last year’s work orders

Last year the plant closed 380 reactive work orders, with 1,140 hours logged and $36,000 of parts. The oldest case packer, which took 140 of those hours and $6,000 of the parts, was replaced in December from the capital budget. The main parts vendors have announced increases of about 4 percent.

So this year’s repairs are:

  • Hours: 1,140 − 140 = 1,000
  • Parts: ($36,000 − $6,000) × 1.04 = $31,200

Only repair parts get the 4 percent, because it starts from last year’s prices. The schedule’s parts above, and the pay rates, contracts and quotes below, are this year’s. Call-outs and invoices carried from last year stay flat because no trade here has announced a rise; if yours has, raise them too.

Add 200 hours of other work (installs, moves, shutdown help), the same as last year.

Can the crew do it?

Yes. This year’s plan is 1,024 + 1,000 + 200 = 2,224 hours. Last year the technicians logged 2,320 hours on work orders, 96 more. The plan fits what the crew really delivered: no hire, no extra contractor.

Compare logged with logged

Do not compare with paid hours. The crew is paid for 3 × 2,080 = 6,240 hours, but holidays, vacation, training, walking, waiting for parts and unwritten jobs take most of that, as the wrench time entry explains.

Labor

  • Straight time: 3 technicians × 2,080 paid hours × $48 loaded rate = $299,520
  • Overtime: 180 hours of call-ins, as last year: 180 × $56 = $10,080

Together, labor is $309,600.

The $48 is a $34 wage plus payroll taxes and benefits. An overtime hour is time and a half on the wage, $51, plus $5 of payroll taxes; benefits here do not rise with overtime. In the United States, the Fair Labor Standards Act requires at least time and a half for non-exempt employees’ hours over 40 in a workweek (US Department of Labor). In Canada, each province sets its own rules.

Parts, contractors and the rest

Parts come to $21,360 preventive + $31,200 repairs + $4,000 critical spares = $56,560. The spares are a case packer gearbox at $2,600 and a conveyor motor at $1,400.

Six trades come to $33,000: the crew does not do this work.

The contractors, trade by tradeWhat each does, and whether the figure is a contract, a quote or last year's bills.
Trade What Basis Amount
HVAC contractor Spring and fall service, plus repairs Contract $7,200 + last year’s call-outs $3,000 $10,200
Fire protection contractor Sprinkler, alarm and extinguisher testing Contract $6,500
Electrician Infrared scan of the panels, plus repairs Quote $1,800 + last year’s call-outs $5,000 $6,800
Forklift dealer Repairs beyond the crew’s skills Last year’s invoices $4,000
Overhead door company Dock door springs and repairs Last year’s invoices $3,000
Roofer Inspection after winter, small repairs Quote $2,500
Contractors $33,000

Tools, training and rentals come to $8,500: $4,000 of tools and consumables, $3,000 of training, and $1,500 to rent a scissor lift for a week.

The contingency has a name

Compressor C-1 is 21 years old, runs hot in summer and leaks oil at the airend, and the dealer has quoted $12,000 to rebuild the airend. If C-1 holds out, the money stays unspent. A flat percentage is a guess; a dealer’s quote is something the approver can check.

Tracking the budget month by month

Spread each line over the months it will be spent in: the overhauls in the July shutdown, the roofer after winter. Straight-time pay needs watching only for headcount, so it stays off the monthly sheet, and so does the contingency until it is drawn.

At the end of March the made-up plant is $2,820 over budget to date.

March, line by lineBudget, actual and the reason for each line
Line Budget to date Actual to date Difference Why
Overtime $2,520 $4,480 +$1,960 C-1 tripped on two February weekends: 35 extra hours
Preventive parts $3,680 $3,540 −$140 On plan
Repair parts $7,800 $10,900 +$3,100 Conveyor CV-7 gearmotor $2,400, C-1 cooling fan $700
Critical spares $4,000 $4,000 $0 Bought in January
Contractors $8,000 $6,200 −$1,800 Electrician’s scan moved to April
Tools, training, rentals $2,000 $1,700 −$300
Total $28,000 $30,820 +$2,820

Read it in three steps:

  1. Separate timing from real. The electrician’s $1,800 scan moved to April, so that money is not saved, only late. Put it back and the quarter is over by 2,820 + 1,800 = $4,620.
  2. Find the cause. Compressor C-1 accounts for 1,960 + 700 = $2,660 of that: $1,960 of overtime after it tripped on two February weekends, and a $700 cooling fan.
  3. Carry it to the year. If the next three quarters go like the first, C-1’s breakdowns cost 4 × 2,660 = $10,640 this year, most of the $12,000 rebuild, which is still needed at the end. That is the case for drawing the contingency now.

Agree a threshold with the approver, such as 10 percent or $1,000 over budget to date, and explain each line past it. The maintenance KPIs guide has a one-page monthly report this sheet can join.

Making the case to the person who approves it

Show what a round-number cut really takes before anyone agrees to one, then argue each line at risk. An approver tends to see one number, and a cut as a percentage of it. Straight-time pay cannot give any of the cut without a layoff, so it all falls on the $120,140 that can move.

$41,966A 10 percent cut
10% of $419,660
35%Of what can move
41,966 ÷ 120,140

Argue each line at risk with four facts: what it buys, what happens without it, what that cost last time (from your records), and who accepts the risk if it goes. Three lines from the made-up plant:

The three linesA spare gearbox, a roof inspection and the C-1 rebuild: what each costs, and what going without it cost
Line Amount Without it What it cost last time (made up)
Spare case packer gearbox $2,600 The next failure waits for a courier Last spring Line 2 waited 3 hours for one, costed at about $6,000 on the downtime cost worksheet
Roofer’s spring inspection $2,500 Loose flashing is found by the next leak A storeroom leak two years ago: $1,800 of ceiling tiles, $3,200 of soaked stock
C-1 rebuild contingency $12,000 The failure is paid from other lines, or approved in a hurry Last August: call-ins, 18 h × $56 = $1,008, and a rental compressor for a week, $2,000

If a line is cut anyway, do not quietly drop the work. Put it on the deferred maintenance list with the date and its price, and ask for the decision in writing, so next year’s budget starts from a list the approver has seen.

When a percentage rule of thumb misleads

Budgets are often quoted as a percentage of what the assets would cost to replace, usually 2 to 4 percent. At a small site that percentage misleads in four ways:

It was written for many buildings
Robert Jortberg, who sat on the National Research Council committee behind the figure, told a later NRC symposium that for a small inventory, like a small county’s, 2 to 4 percent is an average over time, not necessarily a figure for any given year.
The range is too wide
Say the made-up plant’s insurer puts its replacement value at $15 million: 2 to 4 percent is $300,000 to $600,000. The bottom-up $419,660 is 2.8 percent, inside the range, as almost any number would be.
The value underneath is soft
At $12 million the same budget is 3.5 percent; at $20 million, 2.1 percent.
Low can mean deferred
A site that skips services and patches its roof looks cheap until the backlog comes due.

Use it, if at all, as a question once the budget is built: if yours is far outside the range, can you say why?

Where 2 to 4 percent comes fromThe 1990 report, what later reports said of it, and the plant metric

The 2 to 4 percent figure with a clear source is the National Research Council’s, from its 1990 report Committing to the Cost of Ownership: routine maintenance and repair for “a substantial inventory of facilities” typically takes 2 to 4 percent of their aggregate current replacement value.

A later NRC report calls it widely quoted, while noting that there is no single, agreed-upon guideline for how much is adequate. GAO recommended that NASA fund maintenance at that level in 1990.

For plants, SMRP’s metric 1.5 sets total maintenance cost against replacement asset value to compare sites. SMRP’s material on it is paid, so no target from it is quoted here.

What Maintensor records toward a budget

Maintensor keeps the hours and costs the budget sheet is built from.

  • Time, on every plan. Time runs on a work order from Start work until the job is put on hold or done, and Add time and Fix time enter or correct it by hand. That gives step 3 from records, not memory.
  • Cost, on Max. An Admin sets each person’s hourly rate. A work order adds labor cost and other costs (Contractor, Equipment rental, Travel or Other) to its parts, with totals per work order and per asset. Below Max, an asset’s costs are parts only.
  • The month’s actuals. Reporting is open to Admins on Pro and Max. The Cost and labor view, on Max, shows total cost, labor, parts and other costs for a date range, with labor utilization. Plans are on the pricing page.
Labor utilization: 27% of 1,056 available hours, 290 hours logged, with Ben Carter at 45% and four more people from 35% down to 23%.
Labor utilization in the Cost and labor view: 290 hours logged of 1,056 available, 27 percent, with Ben Carter at 45 percent and four more people from 35 down to 23.

What it does not do

Maintensor does not hold the budget: there is no budget to enter, no forecast and no export. The plan and the monthly sheet stay in your spreadsheet. Costs count in the month a work order is completed, and a yearly contract counts only if it is entered on a work order.

Questions

What people also ask.

More in the blog, or see the whole product on the features page.

How do you budget maintenance for a new machine or building with no history?

Take the preventive work from the maker's manual: the tasks, how often, and the parts each uses. For repairs, borrow the figures of your most similar asset, check what the warranty covers, and keep the line small but not zero. Log every hour and part from day one, so next year's budget rests on its own record.

Should a maintenance budget be set as a percentage of revenue?

It is a poor way to set one. Revenue moves with prices, volume and product mix; maintenance work moves with the number and age of the machines and how hard they run. A good sales year can shrink the share while the machines wear faster. Report the ratio if finance asks for it, but build the budget from the work.

Does the maintenance manager's salary go in the maintenance budget?

That depends on the chart of accounts: some sites put the manager in the maintenance cost center, others in plant overhead. Ask finance where each person sits and keep them there every year, so this year's budget and last year's actual spending compare like with like.

What should you do when the money runs out before the year ends?

Say so as soon as the monthly report shows it, with what is left to spend and to do. Do not cut preventive work first: skipped services come back as breakdowns, at overtime rates. Defer what can wait, list it with its price, and ask for more money or a written decision on what will not be done.