Downtime cost: how to work out what a breakdown really cost

Downtime cost is what an unplanned stop takes from the business: lost margin, idle and overtime wages, scrap, rush parts, outside help and penalties. Work it out one stop at a time, with your own numbers.

By MaintensorUpdated 8 min read

Key points

  • Count margin, not revenue: the price less the materials, packaging and energy never spent.
  • Output made up later costs the overtime, not the margin. Count each unit once.
  • Rent, depreciation and fixed salaries stay off the worksheet: the stop did not cause them.
  • In the first example, a 6-hour stop cost $12,044, about $2,000 an hour.
  • Your own last three stops persuade better than a dollars-per-hour figure from a report.

What counts, and what does not

A stop’s cost is lines A to G below, with the repair kept beside them, and each line has a source you can look up, so the worksheet never needs a guess.

Line What it is Working and source
A. Lost margin The margin on output lost for good Units lost for good × margin per unit, from sales or finance
B. Idle labor Wages for people who could do nothing useful People × idle hours × hourly cost, from payroll
C. Overtime to catch up Extra hours to make up output or finish the repair People × overtime hours × overtime rate, from payroll
D. Scrap and restart Product ruined by the stop and the restart Units scrapped × their cost, plus cleaning or checks, from production records
E. Rush parts and freight What you paid above the normal price for speed Rush fees + expedited shipping, from invoices
F. Outside help and rentals Contractor call-outs and hours, rented equipment From the invoices
G. Penalties and credits Late delivery charges, rent credits From contracts and leases
Repair The fix itself Parts at normal price + your crew’s hours, from the work order

Three rules keep it honest:

Margin, not revenue
Margin per unit is the price minus the costs you did not pay because the unit was never made: materials, packaging, energy. Wages are not subtracted, because you paid them anyway.
Lost for good, or made up?
If Saturday’s overtime shift makes up the output, the stop cost you the overtime (line C), not the margin (line A). Count each unit in one line only.
Wages once
In a plant, the operators’ wages for output lost for good are already inside the lost margin. Their regular wages for output made up later are not extra.

So line B is for places with no product to price, such as office staff sent home from a hot building. It is also for wages you paid on top: a crew held on paid standby, call-in pay.

What stays off the worksheet: rent, depreciation and salaries you pay whether the line runs or not. The stop did not cause them.

Downtime cost calculatorType your own numbers and see the answer, with the sum shown.

What overtime costs, by law

In the United States, non-exempt employees are owed at least one and a half times their regular rate for hours over 40 in a workweek under the Fair Labor Standards Act (US Department of Labor). In Canada, overtime rules are set by each province, or federally for federally regulated work.

Use your real overtime cost, with benefits and payroll taxes.

Example 1: a packaging line

This 6-hour stop cost $12,044, plus $2,870 for the repair: $14,914 in all. The numbers are made up. A food plant’s Line 2 stops on a Tuesday when the case packer’s gearbox fails:

9:00 a.m.Line 2 stops. Two technicians diagnose the gearbox in an hour.
10:00 a.m.The gearbox is not on the shelf, so a distributor 60 miles (about 100 km) away sends one by courier.
1:00 p.m.It arrives three hours later, and the technicians fit it in two.
3:00 p.m.The line runs again.

The line makes 600 cases an hour. A 4-hour overtime shift on Saturday makes up some of the output; the rest is lost for good, and the retailer’s order ships short.

3,600Cases not made
6 h × 600
2,400Made up on Saturday
4 h × 600
1,200Lost for good
3,600 − 2,400

A case sells for $22 and takes $15 of materials, packaging and energy, so the margin is $7 a case.

Line Working Cost
A. Lost margin 1,200 cases × $7 $8,400
B. Idle labor Operators cleaned the line and helped on Line 1; their wages are inside line A or not extra $0
C. Overtime 8 operators × 4 h × $42 (1.5 × $28), plus 1 technician × 4 h × $67.50 (1.5 × $45) $1,614
D. Scrap and restart 60 cases crushed in the jam and the first restart × $15 $900
E. Rush parts and freight Same-day courier $380 + rush fee $150 $530
F. Outside help None, the plant’s own crew did the work $0
G. Penalties The retailer’s short-shipment charge $600
Cost of the stop $12,044
Repair Gearbox at normal price $2,600 + 2 technicians × 3 h × $45 $2,870
Total $14,914

About $2,000 an hour, for this stop

This stop cost about $2,000 for each of its 6 hours ($12,044 ÷ 6). That is Line 2’s own number, for a Tuesday when most of the output could be made up. On a sold-out Friday before a holiday, nothing could be made up, and the same 6 hours would cost more.

Half of the stop, 3 hours, was spent waiting for the gearbox. At this stop’s average that is roughly $6,000, and likely more, because a stop half as long could mostly have been made up. A spare gearbox on the shelf costs $2,600.

The spare parts inventory guide covers how to decide what to stock, and the same figure defends the spare’s line when the maintenance budget is cut.

Example 2: a chiller in July

This chiller stop cost $7,650, plus $1,570 for the repair: $9,220 in all. These numbers are made up too. A three-story office building is owned by a company that uses the first two floors, with its call center on the second, and leases the third floor to a tenant.

At 1:00 p.m. on a Thursday in July, with 92 °F (33 °C) outside, the chiller trips. The building engineer finds a burned compressor contactor and a failed condenser fan motor and calls the service contractor. Cooling is back at 6:00 p.m. on Saturday.

The chiller stop, line by line$9,220 in all: $7,650 for the stop and $1,570 for the repair
Line Working Cost
A. Lost margin No product to price $0
B. Idle labor 25 call center staff sent home at 3:00 p.m. Thursday × 2 h × $30; on Friday they worked from home, so nothing is counted $1,500
C. Overtime Building engineer on Saturday, 8 h × $60 (1.5 × $40) $480
D. Scrap and restart Nothing spoiled $0
E. Rush parts and freight Fan motor shipped overnight, freight and rush fee $300
F. Outside help and rentals Emergency call-out $450 + 12 contractor hours × $185 + portable cooling for the tenant floor and the server closet, 2 days, $1,600 $4,270
G. Credits Rent credit owed to the tenant under the lease’s cooling clause $1,100
Cost of the stop $7,650
Repair Contactor $180 + fan motor $1,150 at normal price + engineer 6 h × $40 $1,570
Total $9,220

A building’s downtime cost is mostly outside help, rentals and what you owe tenants. Line D would carry the weight in a building with a commercial kitchen, a lab or a server room that lost its cooling.

Read the leases

A cooling clause turns a hot weekend into a line on the worksheet. Then make the obvious comparison: what a pre-season chiller service and a spare contactor on the shelf cost, against $9,220.

Why not use a dollars-per-hour figure from a report

A number from your own last three stops, with the arithmetic written down, will persuade a plant manager or an owner far better, because they can check every line.

Large per-hour figures for downtime circulate in survey reports and articles. Most do not show their method, and most come from large plants. None of them knows your margin, your customers’ terms, or whether you can make the output up on Saturday.

Keeping a running tally

You do not need to cost every stop. Cost the big ones, and keep a short record of every unplanned downtime event so the big ones stand out.

  1. For every unplanned stop, write down the asset, when it stopped, when it ran again, and the cause in a few words.
  2. For any stop over an agreed threshold, such as two hours or any stop on a bottleneck machine, fill in the worksheet within the week, while the invoices and the overtime sheet are easy to find.
  3. Each month, add up the costed stops by asset. Put the total downtime on the worst assets into the monthly report described in the maintenance KPIs guide.
  4. Each quarter, rank the assets by what their stops cost. That ranking is a fair first draft of an asset criticality list, and the cost per stop is the figure to set against a spare part, a service contract, a rebuild or replacement.

The same figures make the case for spending on maintenance at all, which the guide to CMMS ROI works through.

How Maintensor records downtime and cost

Maintensor keeps the maintenance side of the worksheet: when an asset was down, and what the work on it cost.

  • The status. On an asset, or on one unit of an asset with units, set the status to Down for an unplanned stop or In maintenance for planned work, with a reason if you like.
  • The record. The asset’s History lists each change with who made it and when. The downtime runs until the status goes back to Operational.
  • The checklist. A failed inspection check on a checklist offers Mark asset down.
  • The totals. On Pro and Max, Reporting (open to Admins) adds the downtime up, planned and unplanned, over time and for the five locations with the most. It ranks the five assets with the most unplanned downtime, with their repair cost. All of it runs by the clock, nights and weekends included, because the app does not know your shifts.
Planned vs. unplanned downtime: 9 days 7 hours in all, 3 days 18 hours unplanned and 5 days 13 hours planned.
Planned vs. unplanned downtime in Reporting: 9 days 7 hours in all, of which 3 days 18 hours unplanned and 5 days 13 hours planned.

On Max, a work order also carries labor cost at each person’s hourly rate, and other costs typed as Contractor, Equipment rental, Travel or Other, with a photo or PDF of the receipt if you have one.

The chiller’s call-out goes under Contractor and the portable cooling under Equipment rental, and both add into the asset’s cost. Below Max, an asset’s costs are its parts only.

What it does not do

The app does not price downtime. Lost margin, production overtime, scrap and penalties stay on your worksheet, and there is no export to carry them out of the app.

Questions

What people also ask.

More in the blog, or see the whole product on the features page.

How do you calculate the cost of downtime per hour?

Add up the cost of one stop (lost margin, overtime, scrap, rush parts, outside help and penalties) and divide by the hours it lasted. Do it for a few real stops rather than once in theory. The hourly figure changes with the time of day, the day of the week and the season, so keep the per-stop totals and treat the hourly number as a rough guide.

Should the cost of downtime use revenue or profit?

Use margin, not revenue. If a case sells for $22 and the materials, packaging and energy to make it cost $15, a case you never make loses you $7, not $22. And count only output that is lost for good. Output you make up on an overtime shift costs you the overtime, not the margin.

Is planned downtime a cost?

Planned downtime costs output too, but you choose when it happens: a quiet shift, a weekend, a slow season, with the parts and people ready. That is why it is usually far cheaper than the same hours of unplanned downtime, and why the two are counted separately. The worksheet on this page is for unplanned stops.

What is the difference between downtime cost and repair cost?

Repair cost is what the fix itself took: parts at their normal price and your own crew's hours. Downtime cost is what the stop cost everyone else: lost output, idle or overtime wages, scrap, rush charges, contractors and penalties. Keep them apart on the worksheet and add them at the end, so each dollar is counted once.

Start with the machine that gives you the most work.

Start the trial, add that one asset with its location and nameplate, and write its first work order. Its history builds from there, job by job.

30-day free trial. No credit card.