Key points
- Count margin, not revenue: the price less the materials, packaging and energy never spent.
- Output made up later costs the overtime, not the margin. Count each unit once.
- Rent, depreciation and fixed salaries stay off the worksheet: the stop did not cause them.
- In the first example, a 6-hour stop cost $12,044, about $2,000 an hour.
- Your own last three stops persuade better than a dollars-per-hour figure from a report.
What counts, and what does not
A stop’s cost is lines A to G below, with the repair kept beside them, and each line has a source you can look up, so the worksheet never needs a guess.
| Line | What it is | Working and source |
|---|---|---|
| A. Lost margin | The margin on output lost for good | Units lost for good × margin per unit, from sales or finance |
| B. Idle labor | Wages for people who could do nothing useful | People × idle hours × hourly cost, from payroll |
| C. Overtime to catch up | Extra hours to make up output or finish the repair | People × overtime hours × overtime rate, from payroll |
| D. Scrap and restart | Product ruined by the stop and the restart | Units scrapped × their cost, plus cleaning or checks, from production records |
| E. Rush parts and freight | What you paid above the normal price for speed | Rush fees + expedited shipping, from invoices |
| F. Outside help and rentals | Contractor call-outs and hours, rented equipment | From the invoices |
| G. Penalties and credits | Late delivery charges, rent credits | From contracts and leases |
| Repair | The fix itself | Parts at normal price + your crew’s hours, from the work order |
Three rules keep it honest:
So line B is for places with no product to price, such as office staff sent home from a hot building. It is also for wages you paid on top: a crew held on paid standby, call-in pay.
What stays off the worksheet: rent, depreciation and salaries you pay whether the line runs or not. The stop did not cause them.
Downtime cost calculatorType your own numbers and see the answer, with the sum shown.What overtime costs, by law
In the United States, non-exempt employees are owed at least one and a half times their regular rate for hours over 40 in a workweek under the Fair Labor Standards Act (US Department of Labor). In Canada, overtime rules are set by each province, or federally for federally regulated work.
Use your real overtime cost, with benefits and payroll taxes.
Example 1: a packaging line
This 6-hour stop cost $12,044, plus $2,870 for the repair: $14,914 in all. The numbers are made up. A food plant’s Line 2 stops on a Tuesday when the case packer’s gearbox fails:
The line makes 600 cases an hour. A 4-hour overtime shift on Saturday makes up some of the output; the rest is lost for good, and the retailer’s order ships short.
6 h × 600
4 h × 600
3,600 − 2,400
A case sells for $22 and takes $15 of materials, packaging and energy, so the margin is $7 a case.
| Line | Working | Cost |
|---|---|---|
| A. Lost margin | 1,200 cases × $7 | $8,400 |
| B. Idle labor | Operators cleaned the line and helped on Line 1; their wages are inside line A or not extra | $0 |
| C. Overtime | 8 operators × 4 h × $42 (1.5 × $28), plus 1 technician × 4 h × $67.50 (1.5 × $45) | $1,614 |
| D. Scrap and restart | 60 cases crushed in the jam and the first restart × $15 | $900 |
| E. Rush parts and freight | Same-day courier $380 + rush fee $150 | $530 |
| F. Outside help | None, the plant’s own crew did the work | $0 |
| G. Penalties | The retailer’s short-shipment charge | $600 |
| Cost of the stop | $12,044 | |
| Repair | Gearbox at normal price $2,600 + 2 technicians × 3 h × $45 | $2,870 |
| Total | $14,914 |
About $2,000 an hour, for this stop
This stop cost about $2,000 for each of its 6 hours ($12,044 ÷ 6). That is Line 2’s own number, for a Tuesday when most of the output could be made up. On a sold-out Friday before a holiday, nothing could be made up, and the same 6 hours would cost more.
Half of the stop, 3 hours, was spent waiting for the gearbox. At this stop’s average that is roughly $6,000, and likely more, because a stop half as long could mostly have been made up. A spare gearbox on the shelf costs $2,600.
The spare parts inventory guide covers how to decide what to stock, and the same figure defends the spare’s line when the maintenance budget is cut.
Example 2: a chiller in July
This chiller stop cost $7,650, plus $1,570 for the repair: $9,220 in all. These numbers are made up too. A three-story office building is owned by a company that uses the first two floors, with its call center on the second, and leases the third floor to a tenant.
At 1:00 p.m. on a Thursday in July, with 92 °F (33 °C) outside, the chiller trips. The building engineer finds a burned compressor contactor and a failed condenser fan motor and calls the service contractor. Cooling is back at 6:00 p.m. on Saturday.
The chiller stop, line by line$9,220 in all: $7,650 for the stop and $1,570 for the repair
| Line | Working | Cost |
|---|---|---|
| A. Lost margin | No product to price | $0 |
| B. Idle labor | 25 call center staff sent home at 3:00 p.m. Thursday × 2 h × $30; on Friday they worked from home, so nothing is counted | $1,500 |
| C. Overtime | Building engineer on Saturday, 8 h × $60 (1.5 × $40) | $480 |
| D. Scrap and restart | Nothing spoiled | $0 |
| E. Rush parts and freight | Fan motor shipped overnight, freight and rush fee | $300 |
| F. Outside help and rentals | Emergency call-out $450 + 12 contractor hours × $185 + portable cooling for the tenant floor and the server closet, 2 days, $1,600 | $4,270 |
| G. Credits | Rent credit owed to the tenant under the lease’s cooling clause | $1,100 |
| Cost of the stop | $7,650 | |
| Repair | Contactor $180 + fan motor $1,150 at normal price + engineer 6 h × $40 | $1,570 |
| Total | $9,220 |
A building’s downtime cost is mostly outside help, rentals and what you owe tenants. Line D would carry the weight in a building with a commercial kitchen, a lab or a server room that lost its cooling.
Read the leases
A cooling clause turns a hot weekend into a line on the worksheet. Then make the obvious comparison: what a pre-season chiller service and a spare contactor on the shelf cost, against $9,220.
Why not use a dollars-per-hour figure from a report
A number from your own last three stops, with the arithmetic written down, will persuade a plant manager or an owner far better, because they can check every line.
Large per-hour figures for downtime circulate in survey reports and articles. Most do not show their method, and most come from large plants. None of them knows your margin, your customers’ terms, or whether you can make the output up on Saturday.
Keeping a running tally
You do not need to cost every stop. Cost the big ones, and keep a short record of every unplanned downtime event so the big ones stand out.
- For every unplanned stop, write down the asset, when it stopped, when it ran again, and the cause in a few words.
- For any stop over an agreed threshold, such as two hours or any stop on a bottleneck machine, fill in the worksheet within the week, while the invoices and the overtime sheet are easy to find.
- Each month, add up the costed stops by asset. Put the total downtime on the worst assets into the monthly report described in the maintenance KPIs guide.
- Each quarter, rank the assets by what their stops cost. That ranking is a fair first draft of an asset criticality list, and the cost per stop is the figure to set against a spare part, a service contract, a rebuild or replacement.
The same figures make the case for spending on maintenance at all, which the guide to CMMS ROI works through.
How Maintensor records downtime and cost
Maintensor keeps the maintenance side of the worksheet: when an asset was down, and what the work on it cost.
- The status. On an asset, or on one unit of an asset with units, set the status to Down for an unplanned stop or In maintenance for planned work, with a reason if you like.
- The record. The asset’s History lists each change with who made it and when. The downtime runs until the status goes back to Operational.
- The checklist. A failed inspection check on a checklist offers Mark asset down.
- The totals. On Pro and Max, Reporting (open to Admins) adds the downtime up, planned and unplanned, over time and for the five locations with the most. It ranks the five assets with the most unplanned downtime, with their repair cost. All of it runs by the clock, nights and weekends included, because the app does not know your shifts.

On Max, a work order also carries labor cost at each person’s hourly rate, and other costs typed as Contractor, Equipment rental, Travel or Other, with a photo or PDF of the receipt if you have one.
The chiller’s call-out goes under Contractor and the portable cooling under Equipment rental, and both add into the asset’s cost. Below Max, an asset’s costs are its parts only.
What it does not do
The app does not price downtime. Lost margin, production overtime, scrap and penalties stay on your worksheet, and there is no export to carry them out of the app.