What is mean time to repair (MTTR)?

Mean time to repair (MTTR) is the average time it takes to get a failed machine working again: total hours from failure to back in service, divided by the number of failures. It measures how long each breakdown hurts.

By MaintensorUpdated

The MTTR formula, and when the clock starts and stops

MTTR = hours from failure to back in service ÷ number of failures

Clock starts
when the machine stops, or when someone noticed it if the stop time is not known
Clock stops
when the machine is running and doing its job again
MTTR calculatorType your own numbers and see the answer, with the sum shown.

Everything in between counts: waiting for a technician, finding the fault, waiting for parts, the repair, testing and restart. The dependability vocabulary, IEC 60050-192, defines MTTR as mean time to restoration and lists “mean time to repair” and “mean time to recovery” as deprecated names for it.

Two other clocks go by the same name: repair time, from when a technician starts to when the repair is done, and work order time, from when the work order is written to when it is closed. Pick one, write it at the foot of every report, and do not switch.

MTTR example: six assets at a small plant over one quarter

Six made-up assets over one quarter. Hands-on hours are the technicians’ working time within the hours down.

52 hHours down
12 failures
1.6 hHands-on, average
19 h ÷ 12
2.4 hWithout the dock door
26 h ÷ 11
4.3 hMTTR
52 h ÷ 12

About two thirds of the hours down (33 of 52) went to waiting, not working. Dock door 3 was down 26 hours, almost all of it waiting for a torsion spring that was not in stock: one missing part nearly doubled the average.

The quarter's numbers, line by lineFailures, hours down and hands-on hours for each of the six.
Asset Failures Hours down Hands-on hours MTTR
Air compressor 1 2 3.0 2.0 1.5 h
Conveyor CV-3 3 9.0 6.0 3.0 h
Dock door 3 1 26.0 2.0 26.0 h
Mixer M-2 2 10.0 6.0 5.0 h
Labeler 4 4.0 3.0 1.0 h
Boiler 0 0 0 none
All six 12 52.0 19.0 4.3 h

Every number is made up.

Report it with its longest repair

Put the longest repair beside every MTTR figure and ask where its hours went: the fix for a high MTTR is often on the storeroom shelf. The maintenance KPIs guide has a one-page monthly report.

What to include and what to leave out

  • Include every failure that stopped the asset or stopped it doing its job, above a threshold you set once, such as five minutes.
  • Leave out planned stops: preventive maintenance, changeovers, cleaning. Counting them punishes the crew for doing preventive work.
  • Decide whether hours the asset was not needed anyway count, such as the weekend between a Friday failure and a Monday fix, and say which.

MTTR vs MTBF, mean time to respond and first-time fix rate

  • Not MTBF or MTTF. MTBF is how often a machine fails, and MTTF how long a replaced part lasts.
  • Not mean time to respond. Borrowed from IT, it covers only the wait before work starts.
  • Not the first-time fix rate. The first-time fix rate says whether the repair held, which a fast MTTR can hide.

The guide to MTTR and MTBF together works both out on one machine over a quarter, with availability.

MTTR in Maintensor

Reporting in Maintensor, on Pro and Max and open to Admins, shows MTTR on the Work orders view: the average time reactive work orders completed in the date range spent Open, In progress and On hold, from when each was created, or its start date if later, to its completion.

That makes it the work order clock, not hands-on repair time and not machine downtime. The Time to complete card splits it by status, which shows how much was spent waiting to start or on hold.

Questions

What people also ask.

More in the glossary, or see the whole product on the features page.

What is a good MTTR?

There is no good MTTR in general: a belt splice and a compressor overhaul take different times. Compare an asset with its own MTTR in earlier periods, counted on the same clock, and look at where the hours went. If most of them were spent waiting for a technician or a part, the fix is in staffing or the storeroom, not in faster repairs.

Is a lower MTTR always better?

A lower MTTR is better only if the repairs hold. A crew under pressure to get running can patch a machine in twenty minutes and see it fail again the next day. Watch MTTR beside repeat failures on the same asset, and treat a falling MTTR with rising repeats as a warning.

How do you calculate MTTR in a spreadsheet?

Give each failure a row with the date and time it stopped and the date and time it ran again. In Excel or Google Sheets, a column of =(C2-B2)*24 turns each pair into hours, because the sheet stores times as fractions of a day. MTTR is then =AVERAGE() over that column for the period.

See your own numbers, not an example's.