The first-time fix rate formula and three choices behind it
First-time fix rate = repairs fixed on the first attempt ÷ all repairs closed × 100
- All repairs closed
- which jobs count: usually the reactive work orders closed in the period
- Fixed on the first attempt
- what counts as a miss: a job is fixed first time if it is not reopened, and not followed by a new work order for the same fault on the same asset within a set window, such as 14 or 30 days
The third choice is what to do with a planned second visit, when a first look finds a part must be ordered. Some crews count it as a miss, because a better-stocked shelf would have avoided it; others leave it out. Either works if it is written down and kept the same every month.
First-time fix example: 60 repairs in one month, counted two ways
A made-up crew of four closes 60 reactive work orders in a month. Five are reopened because the fault came back, three more are followed by a new work order for the same fault on the same machine within 14 days, and four need a second visit because the part was not in stock.
(60 − 8) ÷ 60
(60 − 12) ÷ 60
The 12 misses matter more than either rate: 4 were parts, 5 were one conveyor that kept losing its tracking while nobody looked at the worn pulley, and 3 were faults misread from a one-word request.
That points to three fixes: stock those parts, find the cause on the conveyor (a 5 whys is a fair start), and ask for more detail on requests.
Read the misses, not the rate
With 20 repairs a month, one miss moves the rate by 5 points. Never use it to grade people: if a reopened job counts against a technician, jobs stop being reopened, the number improves and the machines do not.
First-time fix rate vs MTTR, MTBF and repeat failures
- Mean time to repair measures how long repairs take; first-time fix rate, whether they hold. A crew that patches fast can improve MTTR while its first-time fix rate falls.
- Mean time between failures shortens when a repair does not hold, which is a first-time fix miss at the same time.
- Repeat failures look across months; first-time fix rate looks only at the days just after a repair.
The maintenance KPIs guide puts it beside the other numbers a small crew might keep.
Reopened work orders in Maintensor, counted by hand
A completed work order can be reopened with Reopen. The reopen is written to its History, and any parts it used go back into stock. When a fault comes back within the window, reopen the work order rather than writing a new one, so the miss is on the record.
Maintensor has no first-time fix figure in Reporting and no filter for reopened work orders, so the count is by hand: read the month’s done reactive work, or keep a tally as jobs are reopened.
An asset’s Work orders tab lists the jobs recently done on it, where a repeat on the same machine shows, and the asset warns when one part has been used on it three or more times this year.