MTTR vs MTBF: what each one measures, worked over one quarter

MTTR vs MTBF comes down to two questions: MTBF (mean time between failures) says how often a machine fails, and MTTR (mean time to repair) says how long each failure lasts. Together they give availability.

By MaintensorUpdated 8 min read

Key points

  • MTBF is operating hours divided by failures. Higher is better.
  • MTTR is hours down from failures divided by failures. Lower is better.
  • Availability from failures alone is MTBF ÷ (MTBF + MTTR).
  • Planned stops are not failures: counting them would cut the example's MTBF from 202 to 126 hours.
  • Much of a repair can be waiting: one stop waited 6 hours for a seal.

The difference in one table

MTBF MTTR MTTF
Stands for Mean time between failures Mean time to repair Mean time to failure
Answers How often does it fail? How long does each failure last? How long does a part last before it fails?
Formula Operating hours ÷ failures Hours down from failures ÷ failures Operating hours of the parts ÷ failures
Used for Machines you repair Machines you repair Parts you replace, not repair
Better when Higher Lower Higher

Together, MTBF and MTTR give availability:

availability = MTBF ÷ (MTBF + MTTR)

The MTTR entry and the MTBF entry give each formula on its own.

How to calculate MTTR and MTBF

To calculate MTBF, divide operating hours by failures. To calculate MTTR, divide the hours from stop to back in service by failures.

A made-up bottle filler, Filler 2, shows both. It runs two 8-hour shifts, Monday to Friday: 80 hours a week, 1,040 scheduled hours over a 13-week quarter.

Here is every stop it had, planned and unplanned. For each failure, the hours down are split into waiting (for a technician, a part or a decision), repair, and test and restart.

The eight stops, with the hoursFive failures, 21.5 hours down, and three planned stops, 10 hours
Date What happened Type Waiting Repair Test and restart Hours down
Jan 9 Capping head jammed, worn chuck Failure 0.5 1.5 0.5 2.5
Jan 15 Monthly lubrication Planned 2.0
Jan 28 Drive motor tripped on overload Failure 1.0 2.0 0.5 3.5
Feb 12 Monthly lubrication Planned 2.0
Feb 17 Fill valve seal leaking Failure 0.5 3.0 0.5 4.0
Mar 4 Same seal leaking again; none in stock Failure 6.0 3.0 1.0 10.0
Mar 12 Quarterly preventive maintenance Planned 6.0
Mar 26 Bottle sensor fault Failure 0.5 0.5 0.5 1.5
Failures 5 8.5 10.0 3.0 21.5

Working it out

Figure Arithmetic Result
Scheduled hours 80 × 13 1,040 h
Downtime from failures 2.5 + 3.5 + 4.0 + 10.0 + 1.5 21.5 h
Planned downtime 2.0 + 2.0 + 6.0 10.0 h
Operating hours 1,040 − 21.5 − 10.0 1,008.5 h
MTBF 1,008.5 ÷ 5 202 h
MTTR, stop to back in service 21.5 ÷ 5 4.3 h
Hands-on repair only, average 10.0 ÷ 5 2.0 h
Availability, failures only 202 ÷ (202 + 4.3) 97.9%
Availability, all stops 1,008.5 ÷ 1,040 97.0%

Half a shift, every two and a half weeks

Filler 2 fails about every two and a half weeks of running (202 hours at 80 a week), and each failure takes about half a shift. Less than half of that half shift is hands-on repair. The rest is waiting and restarting.

Filler 2’s stops show two more things that the averages hide:

One long wait
One stop, March 4, is 10 of the 21.5 hours, and 6 of those hours were spent waiting for a seal. Without that wait, MTTR would be 15.5 ÷ 5 = 3.1 hours.
The same seal, twice
Two of the five failures were the same seal, which no average will tell you. That pattern is where a root cause analysis starts.

To work out your own:

MTTR calculatorType your own numbers and see the answer, with the sum shown. MTBF calculatorType your own numbers and see the answer, with the sum shown.

MTTF: the seals

A fill valve seal is not repaired; it is thrown away and replaced. For parts like that, the measure is MTTF.

ExampleTwo seals, one MTTF

The seal fitted at December’s preventive maintenance ran 640 operating hours before it leaked on February 17. Its replacement ran 170 hours before it leaked on March 4. From these two alone, MTTF is (640 + 170) ÷ 2 = 405 hours. The seal now running is not counted, so this reads low.

Two failures make a hint, not a measurement. But a seal that lasts a quarter as long as the one before it points at the fitting or the part, not at bad luck.

The mean time to failure entry shows how to treat parts that are still running.

Why each one matters

MTBF points at the machine, and MTTR points at the crew and what supports it.

MTBF is about the machine
It moves when the machine changes. If you fix the seal problem, Filler 2’s MTBF should rise next quarter. If it does not, the fix did not work.
MTTR is about the crew and its support
It moves when parts, people and paperwork change, and production feels it on every stop.

Availability needs both, and the same availability can hide very different machines:

MTBF MTTR Availability
Machine A 50 h 1 h 50 ÷ 51 = 98.0%
Machine B 500 h 10 h 500 ÷ 510 = 98.0%

Machine A stops ten times as often for short repairs. Machine B stops rarely, but each stop takes more than a shift. A needs its cause found; B needs spares and a faster repair.

Kinds of availability

Reliability engineers name several. A NASA reliability note on availability sets out the types: inherent availability counts only the corrective work, and leaves out preventive maintenance and logistics and administrative delays. Operational availability includes them all.

Filler 2’s 97.9% sits between the two: it leaves out the planned stops but counts the waiting for parts and people. The availability in OEE is closer to the operational kind, because every stop during planned production time counts against it.

How to improve MTTR and MTBF

Improve MTBF by removing the causes of repeat failures, and improve MTTR by cutting the waiting around each repair.

  • MTBF: find the root cause when a failure comes back, change the preventive task that missed it, fit and lubricate parts correctly, and train operators to keep the machine within its limits.
  • MTTR: split each stop into waiting, repair and restart, and start with the longest. Keep spares for the failures you see most, write procedures for the hard repairs, and train a second person on the machine.

Common mistakes

  1. Mixing response time and repair time. Filler 2 shows why it matters: 4.3 hours from stop to back in service, 2.0 hours of hands-on repair. Write down which clock you use.
  2. Counting planned stops as failures. Count the three planned stops as failures and Filler 2 has 8 failures, an MTBF of 1,008.5 ÷ 8 = 126 hours, and a crew that looks worse for doing its preventive work. Changeovers, no-order idle time and cleaning are not failures either.
  3. Using calendar hours for a machine that does not run around the clock. Over the quarter’s 13 × 168 = 2,184 calendar hours, Filler 2’s MTBF would come out at (2,184 − 21.5) ÷ 5 = 432.5 hours, more than twice the 202. Fine for comparing the machine with itself; wrong next to a compressor that runs all week.
  4. Averaging unlike machines. One MTBF for the whole site mixes a compressor that fails twice a year with a labeler that fails twice a week. Work it out per machine, or per group of identical machines.
  5. Trusting a handful of failures. With 5 failures, one more or one fewer moves MTBF by 17% to 25%. For machines that fail rarely, use a year of history. When there were no failures, say “no failures in 1,008 operating hours” rather than inventing a number.

What the standard calls MTTR

The international vocabulary for dependability, IEC 60050-192, defines MTTR as mean time to restoration: the time from failure until the item works again, waiting included. It lists “mean time to repair” as a deprecated name for it, and keeps hands-on mean repair time as a separate term.

How Maintensor counts MTTR and MTBF, and why it differs

Reporting in Maintensor shows both, on the Pro and Max plans, to Admins. Each is counted from what the app knows for certain, which is not quite the textbook.

Textbook Maintensor Reporting
MTTR clock starts When the machine stopped When the reactive work order was created, or its start date if later
MTTR clock stops When the machine runs again When the work order is completed
MTTR covers Failures of the machine or group measured Every reactive work order completed in the range and filters, stop or no stop
MTBF hours Operating hours Every hour of the range, nights and weekends included, less the asset’s unplanned downtime. For an asset with units, the range times the unit count, with every unit’s stops and downtime pooled
MTBF failures Failures The times the asset was marked Down in the range
MTBF shown for Any machine The five assets with the most unplanned downtime

In MTTR, a reactive work order for a dripping tap that waited three days counts as much as one for a stopped line. The Time to complete card splits the figure by status, which pulls out much of the waiting: Open is time before anyone started, On hold is usually parts or access. Even In progress is not hands-on repair time.

For MTBF, the app does not know your shifts, and it does not subtract planned downtime (In maintenance). If Filler 2 were among those five, the app’s MTBF for the same 13 weeks would be the 432.5 hours of mistake 3, shown as 18 days. Compare an asset with its own earlier periods.

Reporting in Maintensor, the Assets view for the last 30 days: downtime, 72 reactive work orders, and the most problematic assets, led by the CNC machine.
The Assets view of Reporting: downtime, unplanned downtime, and the most problematic assets, each with its unplanned downtime, reactive work orders, MTBF and repair cost.

Keep the status honest

MTBF and the downtime figures depend on asset status; MTTR depends only on the work orders. Mark a machine Down when it stops and Operational when it runs again.

If it is switched from Down to In maintenance halfway through a repair, the app keeps one stretch and counts all of it as planned. Leave it Down until it runs.

There is no MTTF or availability figure, and no export.

Questions

What people also ask.

More in the blog, or see the whole product on the features page.

Is a higher MTBF better?

Yes. A higher MTBF means more operating hours between failures, so the machine stops less often. Compare it with the same machine's MTBF in earlier periods, counted the same way. A manufacturer's MTBF figure rests on its own assumptions and test conditions, which are rarely your floor, your dust and your operators.

What is a good MTTR?

There is no single good MTTR, because it depends on the machine, where it sits and how the clock is defined. Watch your own figure month by month, read the longest repairs, and split the time into waiting and working. The waiting, for a part, a person or a decision, is often the easiest part to cut.

Does an MTBF of 200 hours mean the machine runs 200 hours before it fails?

No. MTBF is an average, not a promise. If failures strike at random, at a steady rate, about 63% of the gaps between failures are shorter than the MTBF, and some are much shorter. MTBF tells you how often to expect trouble over many hours, not when the next failure comes.

What is the difference between MTBF and MTTF?

MTBF is for things you repair and put back into service, such as a filler, a pump or a forklift. MTTF is for things you throw away and replace when they fail, such as a seal, a bearing or a lamp. The arithmetic is the same: operating hours divided by failures. What changes is what you count.