What is OEE (overall equipment effectiveness)?

Overall equipment effectiveness (OEE) measures how much of a machine's planned production time turned into good product at its ideal speed. It is availability times performance times quality.

By MaintensorUpdated

How to calculate OEE: the formula

OEE = availability × performance × quality

Availability
run time ÷ planned production time
Performance
ideal cycle time × total count ÷ run time
Quality
good count ÷ total count
OEE calculatorType your own numbers and see the answer, with the sum shown.

Planned production time is the shift minus planned stops, such as breaks. Whether planned maintenance counts against availability is each site’s choice: pick one rule, write it down and keep it. OEE is one of the indicators in ISO 22400-2.

OEE calculation example: one 8-hour shift worked out

A made-up packing line: 450 planned minutes, 45 minutes of stops, an ideal rate of one case a minute, 360 cases made and 18 rejected.

90%Availability
405 ÷ 450 min
88.9%Performance
360 ÷ 405 cases
95%Quality
342 ÷ 360 good
76%OEE
0.90 × 0.889 × 0.95
The shift's numbers, line by lineAnd the check: 342 good cases × 1 min ÷ 450 min = 0.76.
Item Figure
Shift 480 min
Planned breaks 30 min
Planned production time 450 min
Stops: a jam (25 min) and a changeover (20 min) 45 min
Run time 405 min
Ideal rate 1 case a minute
Cases made 360
Cases rejected 18
Good cases 342

The 24% lost is 108 minutes of the 450 at the ideal rate: 45 minutes stopped, 45 cases’ worth of slow running and short stops, and 18 rejected cases. Every number is made up.

What is a good OEE score?

Compare a machine with itself

No score is good for every machine: it rests on what each site counts as planned time and where it takes the ideal rate from. Write both down, hold them fixed, and set the target from your own last three months.

Then start with the lowest of the three parts: availability points at stops, performance at slow running and short stops, quality at scrap and rework.

The six big losses

Total productive maintenance sorts lost time into six kinds, two under each part of OEE.

Availability
Breakdowns, such as the 25-minute jam, and setups and adjustments, such as the changeover.
Performance
Small stops and idling, such as a photo eye that trips and resets, and reduced speed.
Quality
Defects and rework, such as cases rejected for bad seals, and startup losses after a changeover.

Maintenance owns the breakdowns, and often part of the small stops and the slow running. Total productive maintenance is the practice built around cutting all six.

What OEE is not

  • Not a maintenance number on its own. A changeover lowers it with nothing broken.
  • Not comparable between lines or plants unless the definitions match.
  • Not a cause. It says how much was lost; the stop log says why.

To track it, start with the one machine that limits output and log every stop with its reason and minutes; the maintenance KPIs guide covers which numbers a small team should report.

OEE and Maintensor: the downtime side only

Maintensor does not calculate OEE: it has no production counts, speeds or reject figures. It records the availability side from asset status: Down counts as unplanned downtime and In maintenance as planned, which Admins on Pro and Max see in the Assets view of maintenance reporting software.

Planned vs. unplanned downtime: 9 days 7 hours in all, 3 days 18 hours unplanned and 5 days 13 hours planned.
Planned against unplanned downtime: 9 days 7 hours in all, of which 3 days 18 hours were unplanned and 5 days 13 hours planned.

Questions

What people also ask.

More in the glossary, or see the whole product on the features page.

Can OEE be more than 100%?

Not when it is worked out correctly. A figure over 100% almost always means the ideal rate was set slower than the machine really runs, so performance comes out above 100%. Set the ideal rate from the maker's rated speed or the fastest rate the line has held, and the figure falls back under 100%.

Is OEE a maintenance metric?

OEE is a production metric that maintenance shares. Breakdowns, and some small stops and slow running, are maintenance's part. Changeovers, material shortages, staffing and most quality losses belong to production. Maintenance's own numbers sit under it: unplanned downtime, mean time between failures and mean time to repair.

What is the difference between OEE and availability?

Availability is one of the three parts of OEE: the share of planned production time the machine was running. OEE multiplies it by performance and quality, so a machine can be available 98% of the time and still have a low OEE if it runs slowly or makes scrap.