Key points
- Its best-known part is autonomous maintenance: operators clean, inspect, lubricate and tighten their own machines daily.
- JIPM names eight pillars; a small plant can start with autonomous maintenance, planned maintenance and training.
- Cleaning and lubricating are servicing: operators need lockout training before the first cleaning.
- The six big losses fall into the three parts of OEE: availability, performance and quality.
- A small plant starts with one machine, one cleaning day and a daily check that takes ten minutes.
What TPM is
TPM is a way of running equipment that production owns as much as maintenance does. Preventive maintenance is the maintenance department’s schedule; in TPM, the care is shared:
A TPM program that lives only in the maintenance office is preventive maintenance with a new banner. TPM also appears in lists of the types of maintenance.
The Japan Institute of Plant Maintenance (JIPM) says it proposed the method in 1971 and that it was first established at Nippondenso, now DENSO. JIPM describes it as a method for improving productivity toward zero losses that “focuses on equipment and people.”
The same aims, in a British guide
The British Standards Institution’s PAS 1918:2022, written in consultation with JIPM, describes the same aims: everyone takes part, small groups work on losses, and the target is zero accidents, defects and failures.
TPM is usually drawn as a house: eight pillars standing on a base of 5S, the workplace routine of five steps:
The eight pillars of TPM
JIPM’s TPM Awards application guide (in Japanese) names eight pillars. English names vary; these are close translations.
- Focused improvement. Small teams remove one loss at a time on one machine or line. In a small plant: pick the biggest loss on one line and work it for a month.
- Autonomous maintenance. Operators clean, inspect, lubricate and tighten their own machines. In a small plant: a ten-minute daily check by the operator, to a written standard.
- Planned maintenance. Maintenance’s own preventive and condition work, lubrication control, spare parts. In a small plant: a planned maintenance schedule that is done on time.
- Quality maintenance. Keeping the machine conditions that make good product. In a small plant: list the settings and worn parts that cause scrap, and check them.
- Development management. Products and machines designed to be easy to run and maintain. In a small plant: write what you learned into the next purchase specification.
- Administrative and support departments. TPM in purchasing, planning, stores and the office. In a small plant: stores and purchasing stop being the reason repairs wait.
- Education and training. Skills for operators and technicians. In a small plant: one-page lessons on one skill each, taught at the machine.
- Safety, health and environment. Zero accidents and a clean workplace. In a small plant: a safe way to clean, with lockout, before anyone cleans.
JIPM itself lets a site enter its award with six pillars, leaving out development management and the administrative pillar where the site’s organization makes them hard to apply. A small plant can leave out more at first: autonomous maintenance, planned maintenance and training are a sensible place to start.
Autonomous maintenance: the operator’s part
Autonomous maintenance is the operator’s share of TPM: the operator cleans, inspects, lubricates and tightens to a standard, and reports what is beyond them. Operators are the first to hear the new noise, see the drip and feel the heat.
It is usually taught as seven steps. Masaji Tajiri and Fumio Gotoh’s book Autonomous Maintenance in Seven Steps names them:
- Initial cleaning. With the machine locked out (see the safety section below), clean it thoroughly, inside the guards, with the operators. Cleaning is inspection: every abnormality found gets a tag.
- Countermeasures to sources of contamination. Stop the dirt, leaks and chips at their source, and make hard-to-reach points easier to clean and check.
- Cleaning and lubricating standards. Write down what the operator does, how, and how often.
- Overall inspection. Teach operators how each system of the machine works (drives, hydraulics, pneumatics, electrics), so they inspect with understanding.
- Autonomous maintenance standards. Revise them with what step 4 taught, so the daily check is complete and fits its time.
- Process quality assurance. Extend the operator’s checks to the conditions that make good product. Some programs call this step standardization.
- Autonomous supervision. The team runs and improves its own standards.
What JIPM's award and operator certificate askThe step a site must have reached, the tags it reports, and four abilities
A site applying for JIPM’s first-level award must have finished step 3 and be working on step 4. It also reports how many tags went on and came off.
JIPM’s certification for operators, the Autonomous Maintenance Specialist (in Japanese), sums up the skill in four abilities: to see an abnormality as an abnormality, to deal with it correctly and quickly, to set measurable standards for normal and abnormal, and to keep to the rules once they are set.
Safety comes before the first cloth
In the US, OSHA’s lockout/tagout rule, 29 CFR 1910.147, defines servicing and maintenance to include lubricating, cleaning and unjamming where someone could be hurt by an unexpected start-up.
During normal production, the rule applies when a person has to remove or bypass a guard or put part of their body in the danger zone. A narrow exception covers minor servicing that is routine, repetitive and integral to production, done with other measures that protect as well.
Lockout training before the first cleaning
Operators doing autonomous maintenance need training on each machine’s lockout procedure, and the cleaning standard should say which tasks need lockout. Check the rule against your own work; in Canada, your province’s occupational health and safety rules apply.
The six big losses and OEE
The six big losses, as Seiichi Nakajima listed them in his Introduction to TPM, are breakdowns, setup and adjustment, idling and minor stops, reduced speed, defects and rework, and startup losses. They fall into the three parts of overall equipment effectiveness (OEE): the first two are availability, the next two performance and the last two quality.
ExampleOne shift on a packaging line
A made-up packaging line, one shift: 480 minutes, a 30-minute break, so 450 minutes planned to run.
The six losses, in minutes140 minutes lost out of 450 planned to run
| Loss | OEE part | Minutes lost | What happened |
|---|---|---|---|
| 1. Breakdowns | Availability | 35 | The filler drive tripped on overload |
| 2. Setup and adjustment | Availability | 45 | Changeover to the next bottle size |
| 3. Idling and minor stops | Performance | 25 | Caps jammed at the chute, a minute at a time |
| 4. Reduced speed | Performance | 20 | Ran slow for part of the shift because the labeler drifts |
| 5. Defects and rework | Quality | 10 | Underfilled bottles pulled and rerun |
| 6. Startup losses | Quality | 5 | Scrap until the line settled after the changeover |
| Total | 140 |
The six took 140 minutes, which leaves 310 minutes of good product at full speed out of 450 planned: 310 ÷ 450 is about 69%. The same answer comes from multiplying the three parts:
370 ÷ 450 min
325 ÷ 370 min
310 ÷ 325 min
310 ÷ 450 min
The list matters more than the number. Changeovers and breakdowns are 80 of the 140 lost minutes, so the first improvement team goes there.
How to implement TPM in a small plant, one machine first
- Pick one machine: the bottleneck, or the one with the most breakdowns. It becomes the model.
- Put production and maintenance in one room. Agree who does what: operators the daily care, maintenance the repairs, planned work and teaching (how a small plant splits it).
- Hold the initial cleaning. Lock out, then clean every surface with the operators, with a technician there to explain what they find.
- Tag every abnormality. A tag on the machine and a line on a list: what, where, who, when. Use one color for what operators can fix and another for maintenance.
- Fix the tags, fast. Agree a time for maintenance tags and keep to it.
- Stop the dirt at its source: drip trays, guards, fixed leaks. Then make checking easy: marks on gauges, lubrication points that can be reached.
- Write the daily standard. One page with photos: what to check, how, what good looks like, and how many minutes. Teach each new skill with a one-page lesson.
- Run it daily, review it weekly. The supervisor walks the machine with the operator, reads the checks and tags, and fixes what the standard got wrong.
- Then the next machine.
A daily check that fits in ten minutes
ExampleMade up for a small injection molding machine
| Check | How | Good looks like | Minutes |
|---|---|---|---|
| Hydraulic oil level | Sight glass | Between the marks | 1 |
| Oil temperature | Machine display | Inside the range marked on the standard | 1 |
| Leaks | Look under the machine and along the hoses | No fresh oil, drip tray dry | 2 |
| Mold water lines | Look and feel | No drips, no kinked hoses | 1 |
| Safety gate | Open the gate in manual mode | Machine will not cycle | 1 |
| Emergency stop | Press it | Machine stops | 1 |
| Tie bars and platen | Look from outside the guards. Any wiping waits for a locked-out clean | Clean, lightly oiled, no scoring | 2 |
| Anything new | Listen through the first cycles | No new noise; tag anything new | 1 |
Where TPM programs go wrong
- No time on the shift. If the daily check is not in the production plan, it gets done on paper. That is pencil whipping, and it is worse than no check.
- Tags nobody fixes. Operators soon stop tagging if their tags sit.
- Work handed over without training. Operators given a grease gun and no lesson can over-grease bearings and skip the hard-to-reach points.
- Measuring before improving. Months go into an OEE dashboard while the filler keeps tripping.
- A program owned by one department. If production managers do not give the time, it stops after the first cleaning.
Running the operator check in Maintensor
In Maintensor, the maintenance checklist software makes the daily standard a procedure of Checkbox, Inspection check (Pass, Flag or Fail), Number and Photo steps. When the standard changes, publish a new version; new work orders get it.
Attach it to a work order that repeats Weekly on Monday to Friday, or Daily. The next is created when the last is completed, so a check nobody did stays open and shows as Overdue, and missed days add no extra jobs.
A Fail is the tag. It asks for a note and a photo before the next step, then offers a follow-up work order on the machine and to mark it down. The job can still be closed without them.

Only Admins and Full users answer checklists, so every operator who does the daily check in the app needs a Full user seat (pricing).
Requesters are free on every plan, but a requester can only report a problem, with no photo, for an admin to approve into a work order or decline with a reason.
Keep the seat count down
Seats are the catch here. If line leads do the checks to save seats, and other operators report as requesters, the operator is no longer the one checking, which is a step away from autonomous maintenance.
On Pro and Max, an admin’s Reporting counts how many inspection checks passed, were flagged or failed in a date range.
What it does not do
There is no OEE, no production count and no tag board in the app.