Key points
- The eight steps follow the order of OSHA's rule, 29 CFR 1910.147, from preparing to returning to service.
- Each machine's procedure names its own energy sources and isolating devices; one generic procedure cannot meet the rule.
- A stop button or an emergency stop is never the isolation point. Lock the disconnect, breaker or valve.
- OSHA requires an inspection of each procedure at least yearly, by an authorized employee who does not use it.
- In Canada, your province, territory or the federal government sets the rule; the national standard is CSA Z460-20.
Lockout tagout steps, in order
In the US, OSHA’s rule at 29 CFR 1910.147 requires a written procedure for most machines your crew services. These eight steps follow paragraph (d) of the rule, with the notice to affected employees that (c)(9) requires and paragraph (e)’s release at the end.
- Prepare. Know each energy source on the machine, its magnitude, its hazards and how to control it ((d)(1)).
- Notify. Tell the affected employees before the locks and tags go on ((c)(9)).
- Shut down. Stop the machine by its normal procedure, in an orderly shutdown ((d)(2)).
- Isolate. Operate every energy isolating device: the disconnect, the breaker, the valve ((d)(3)).
- Lock and tag. A lock and tag on each isolating device, each authorized person with their own. In a group lockout, each person’s own lock goes on the group lock box ((d)(4), (f)(3)).
- Release stored energy. Bleed, drain, block, discharge or let cool, and keep checking if it can build back up ((d)(5)).
- Verify zero energy. Before work starts, make sure everyone is clear, try the normal start, read the gauges, test for voltage where the work needs it, then return the controls to Off ((d)(6)).
- Return to service. Tools out, guards on, people clear, each person removes their own lock, and affected employees are told before the start ((e)(1) to (e)(3)).
This is the outline, not the procedure
Each machine’s written procedure fills every step in with its own devices, which is what the rest of this guide covers. Neither the outline nor the procedure replaces the training the rule requires.
Before you write: walk the machine
- Find every energy source. The main electrical supply, control power that may come from another panel, compressed air, hydraulics, steam or water under pressure, gas, gravity (a raised platen or a hopper), springs, heat, chemicals in lines, and capacitors in drives.
- Write down the magnitude. Volts and phase, psi, temperature, the weight of what could fall.
- Find each isolating device and tag it. The label on the disconnect, breaker or valve matches its name in the procedure.
- Check each one takes a lock. After January 2, 1990, new machines, and machines replaced, given a major repair, renovated or modified, must have isolating devices designed to accept a lockout device ((c)(2)(iii)).
- Look for what restarts on its own. Compressors on pressure switches, pumps on float switches, timers.
- Photograph each isolation point, locked and tagged, for the procedure and for training.
A stop button is never the isolation point
OSHA’s definition excludes push buttons, selector switches and other control circuit devices, so a stop button or an emergency stop is never the isolation point.
Electrical work has its own rules
Opening a disconnect and testing for voltage can themselves expose a person to shock and arc flash. Your electrical safety program decides who may open a disconnect. Have a person qualified for electrical work do the testing and any work on live or possibly live parts, under NFPA 70E in the US or CSA Z462 in Canada.
Lockout procedure template: the three parts
The header:
| Field | Fill in |
|---|---|
| Machine and tag | Name, tag number, size |
| Location | Building, area, room |
| Procedure number and version | Number, version, date |
| Purpose and scope | The jobs this covers, and the ones it does not |
| Authorized employees | Who may apply locks, by trade or name |
| Affected employees | Who is told before and after |
| Devices needed | Locks per person, hasps, valve lockouts, blocks, tags |
| Written, reviewed, approved | Names and dates |
The energy sources: one line for each source, numbered E1, E2 and on, with these columns.
The sequence: the eight steps above, each written for this machine, plus how protection passes from the off-going person to the oncoming one at a shift change ((f)(4)). Name the procedure on every work order for a job on that machine, so nobody has to remember to look for it.
Lockout procedure example: a rotary screw air compressor
Everything here is invented to show the shape: the plant, the compressor, its tags and its figures. Your machine’s manual and a walk-down of your own machine decide the content.
ExampleEC-C2: lockout for compressor C-2
| Field | Entry |
|---|---|
| Machine and tag | C-2, 25 hp (18.6 kW) rotary screw compressor, with receiver R-2, 240 gal (about 900 L) |
| Location | Compressor room, Riverside Plant |
| Procedure | EC-C2, version 2 |
| Scope | Oil, filter and separator changes, any work inside the enclosure, work on R-2. Not covered: the 480 V feeder (electricians’ procedure EC-MCC1). |
| Authorized | Maintenance mechanics trained in lockout: Ben Carter, James O’Neil |
| Affected | Line 1 and Line 2 leads, who lose air if C-1 cannot carry the load |
| Devices | One padlock per person per device, one hasp, one ball valve lockout, tags |
| # | Energy | Magnitude | Isolating device | Device | Release | Verify |
|---|---|---|---|---|---|---|
| E1 | Electrical, main and control | 480 V, 3-phase; 120 V control from C-2’s own transformer | Disconnect DS-12, wall left of C-2 | Hasp, padlocks, tags | This fixed-speed machine stores none. A variable-speed drive’s capacitors do: wait the time on its label | Start does nothing, then a voltage test by a qualified person |
| E2 | Compressed air: plant header and receiver R-2 | 125 psi (860 kPa) | Ball valve V-12, between R-2 and the header | Valve lockout | Open drain D-2 on R-2 | Gauge P-2 at 0 |
| E3 | Compressed air in the separator tank | up to 125 psi | None: blows down at stop | None | Wait for blowdown | Sump gauge at 0 |
| E4 | Heat | Oil and discharge piping hot after running | None | None | Let it cool for the time in the manual | Surface thermometer before hands go in |
| E5 | Automatic restart | Starts on its own when pressure falls | Controlled by E1 | Same as E1 | None | Covered by E1 |
- Prepare. Read EC-C2. Hazards: 480 V, air at 125 psi, hot oil, automatic start.
- Notify. Tell the Line 1 and Line 2 leads that C-2 is coming off. Confirm C-1 is running.
- Shut down. Press Stop on C-2’s panel and wait for the unload and blowdown to finish.
- Isolate. Open DS-12. Close V-12.
- Lock and tag. Each mechanic puts their own lock and tag on the DS-12 hasp and on the V-12 lockout.
- Release. Open D-2 until P-2 reads 0 psi, and leave it open. Confirm the sump gauge reads 0. Let the machine cool.
- Verify. With everyone clear, press Start: nothing runs. A dark display proves little, because a blown control fuse looks the same. P-2 and the sump gauge read 0. Return the start switch to Off. Before anyone touches electrical parts, a person qualified for electrical work tests for voltage.
- Restore. Tools and rags out, panels on, D-2 closed, start switch at Off, everyone clear. Each mechanic removes their own lock. Tell the line leads the locks are off, then open V-12 slowly so the empty receiver does not pull down plant air, close DS-12 and start C-2.
- Shift change. The off-going mechanic’s lock stays on until the oncoming mechanic’s lock is on.
The routine service on a machine like this is in our air compressor maintenance checklist, which starts with locking out.
What OSHA requires in a written lockout procedure (29 CFR 1910.147)
The rule covers servicing and maintenance where an unexpected start-up, or a release of stored energy, could injure someone ((a)(1)(i)).
Work during normal production is covered if someone removes or bypasses a guard, or puts part of their body in a danger zone ((a)(2)(ii)). Minor tool changes and adjustments are outside the rule only if they are routine, repetitive, integral to production and done with other measures that give effective protection. Cord-and-plug equipment is outside it when unplugging controls the hazard and the plug stays in the hands of the person doing the work ((a)(2)(iii)(A)).
Paragraph (c)(4)(ii) says each procedure must clearly and specifically outline its scope, purpose, authorization, rules and techniques, and how compliance is enforced, including at least:
| Paragraph | The procedure must include | In practice |
|---|---|---|
| (c)(4)(ii)(A) | A statement of what the procedure is for | The machine, its tag, and the jobs it covers |
| (c)(4)(ii)(B) | Steps to shut down, isolate, block and secure the machine | Each energy source, its isolating device and where it is |
| (c)(4)(ii)(C) | Steps to place, remove and transfer locks and tags, and who is responsible | Whose lock goes where; shift change; group lockout |
| (c)(4)(ii)(D) | How to test the machine to verify the locks work | The try-start, the meter, the gauge at zero |
The procedure leans on the rest of the program:
The one exception to writing it down
Paragraph (c)(4)(i) lets an employer skip the written procedure for a machine only when all eight listed conditions hold. Among them: a single, easily identified energy source, no stored or residual energy, and one lock that isolates it completely. Any machine with stored air, hydraulic pressure, springs or a raised load fails it.
OSHA’s own model, Appendix A to 1910.147, is a typical minimal procedure; the template above adds a table of energy sources for one machine.
This page is information about the rule, not legal advice. It does not replace your energy control program, the training the rule requires, or a qualified person’s review of each procedure. Check the rule that applies to you (federal OSHA, your state plan, or your province) and the machine maker’s manual.
Lockout rules in Canada
Canada has fourteen jurisdictions, federal, provincial and territorial, each with its own health and safety law, as the Canadian Centre for Occupational Health and Safety explains. Your lockout rule is in your province’s or territory’s regulation, or in the federal one if your workplace is federally regulated.
The national standard is CSA Z460-20, “Control of Hazardous Energy: Lockout and Other Methods”, which CCOHS cites in its lockout guidance. The template is about the machine, so it fits either side of the border; the rule you check it against differs.
Testing it, and the yearly inspection
Before the procedure goes into use, walk it down on the machine with a second authorized person. Check that every device in the table is where the procedure says, that each carries the matching tag and takes a lock, and that the verify step really proves the machine is dead. Then train each authorized person on it. Our guide to writing a standard operating procedure covers testing written steps with someone who has never done the job.
The yearly inspection under (c)(6)
Paragraph (c)(6) requires a periodic inspection of each energy control procedure at least once a year, by an authorized employee other than the ones using it, to correct any deviations or gaps found. For lockout, it includes a review with each authorized employee of their responsibilities. The employer keeps a certification naming the machine, the date, the employees included and the person who inspected.
In practice: watch a real job, compare each step with the paper, check the energy table against the machine as it is today, and update the procedure where they differ. Between yearly inspections, the monthly safety inspection checklist asks whether locks and tags are at hand and each serviced machine has its procedure.
Mistakes that make a procedure fail
- One generic procedure for the whole plant. “Turn off and lock out” names no isolating device, so it cannot meet (c)(4)(ii)(B).
- A missed energy source. Control power fed from another panel, air trapped downstream of a closed valve, a platen held up by hydraulics.
- No verification, or verification left switched on. Try the start, then return the control to Off before work begins.
- Tags that do not match. The procedure says V-12; the valve has no label, or a different one.
- Not updated after a change. A new receiver, a second compressor on the header, a rewired panel: each one changes the table.
- Someone else’s lock removed. Under (e)(3), each device comes off by the person who put it on, except under the documented procedure the rule allows.
Lockout procedures in Maintensor, and what the app does not do
Like any checklist in Maintensor’s maintenance checklist software, EC-C2 can be built as a procedure and attached to each work order on C-2, so the lockout steps arrive with the job, once someone has attached it: instructions for the energy table, a checkbox for each lock, a photo of each locked device, a number for each gauge and a signature for each mechanic. A Fail on the try-start asks for a note and a photo before the next step, and offers a follow-up work order and Mark asset down.
The yearly inspection can be its own work order, repeating yearly, with a procedure for the certification. Give the inspector’s name a Text step, because a Signature step stores the drawn signature and the time, not which user signed.
When the machine changes, publish a new version of EC-C2. The procedure’s history lists each earlier version with who published it and when, though not its steps, so keep the reason for each change in the procedure’s description.

What it does not do
Maintensor records what was done; it certifies nothing. It does not replace your energy control program, the training, the periodic inspection or the person who does it.
A required step does not block finishing: a person who may complete work can finish anyway, and the skipped step is written on the job’s history. It does not track who holds which lock, issue permits, or print the procedure to post at the machine. Steps hold words only, so keep the photos of each isolation point on the asset’s record.
It runs in a browser with no offline mode, so a compressor room with no signal still needs a copy posted at the machine, made outside the app.