What is planned maintenance?

Planned maintenance is any maintenance work prepared before it starts: the scope, steps, parts, tools, time and safety measures worked out in advance. It covers preventive work and repairs booked ahead, such as a worn bearing changed at the weekend.

By MaintensorUpdated

What makes a maintenance job planned, before anyone picks up a tool

A planned job is a prepared job. Before anyone picks up a tool, someone has worked out:

The scopeWhat exactly is being done, and to which asset.
The stepsA checklist, or the maker's procedure.
The partsWhich ones, and whether they are on the shelf or ordered.
The tools and helpSpecial tools, a lift, a contractor, a second person.
The timeAn estimate, and when the machine can be stopped.
The safetyLockout, permits, access.

Its opposite is unplanned work: the technician walks up to a stopped machine and works out the job on the spot. A small crew needs no full-time planner, just those answers the day before for any job that takes over an hour, needs a part or stops a machine. Maintenance planning and scheduling covers the weekly routine.

Planned vs preventive maintenance, job by job

Job Planned? Preventive? Why
Quarterly rooftop unit filter change, filters in stock, checklist attached Yes Yes Known in advance and prepared
Gearbox seal replaced Saturday, after a weekly check found it weeping on Tuesday Yes No, corrective A fault was found, then the repair was prepared
Conveyor belt torn mid-shift, replaced at once No No Started without preparation
Monthly service with no checklist, technician hunting for filters Partly Yes Preventive in purpose, but not prepared

Planned says how a job was prepared; preventive and corrective say whether it came before or after a fault. The second row is where planned maintenance earns its keep.

  • Not scheduled maintenance. Planning says what and how; scheduling says when and who.
  • Not only preventive. Repairs found by inspections are planned too; the preventive maintenance guide covers the scheduled work that finds them.

Planned maintenance example: a crew’s week, 70% planned

A made-up crew of three logs 120 hours in one week:

48 hPreventive jobs
filters, greasing, inspections
30 hRepairs found on inspections
booked ahead
36 hBreakdowns and urgent calls
not planned
70%Planned
(48 + 30 + 6) ÷ 120 h

The other 6 hours, installing a sink and moving a machine, were planned too. The preventive share is 48 ÷ 120 = 40%.

The planned share says how much of the week was under control; the preventive share, how much went into avoiding failures. A crew can plan most of its week and still break down often. Planned maintenance percentage covers the metric and the ways sites count it.

What a work order in Maintensor holds for a planned job

A work order in Maintensor holds what a plan needs: a description of the scope, procedures that become its checklist, planned parts from a chosen storeroom (with a warning when it holds fewer than the job needs), an estimate of the work time, and start and due dates. A recurring work order carries all of that forward to the next one.

There is no Planned flag. The Type of work is Reactive, Preventive or Other, so a planned repair is filed as Reactive like any other repair, and Reporting’s preventive ratio counts work orders by type, not planned hours.

Questions

What people also ask.

More in the glossary, or see the whole product on the features page.

What is unplanned maintenance?

Unplanned maintenance is work that starts without preparation, almost always because something broke or is about to: the technician goes to the machine without knowing the scope, the parts or the time it will take. Breakdowns and emergencies are unplanned. Some is unavoidable; the aim is to keep it a small enough share of the week that it does not push out the planned jobs.

What does PPM mean in maintenance?

PPM usually stands for planned preventive (or preventative) maintenance: preventive work booked in advance, such as a quarterly air handler service, and it often appears in building service contracts. Despite the word planned, a PPM schedule normally covers preventive work only, not planned repairs, so check what a contract's PPM list includes before you rely on it.