What is planned maintenance percentage (PMP)?

Planned maintenance percentage (PMP) is the share of all maintenance hours spent on work planned before it started: planned hours divided by total maintenance hours, times 100. A rising PMP means less of the week goes to breakdowns.

By MaintensorUpdated

The PMP formula, and what makes an hour planned

PMP = planned maintenance hours ÷ total maintenance hours × 100

Planned hours
work identified, scoped and scheduled before it started: preventive tasks, inspections, repairs found on an inspection and booked for later, overhauls
Unplanned hours
breakdowns, emergency calls and any job that broke into the week's plan
Total maintenance hours
planned and unplanned together
Planned maintenance percentage calculatorType your own numbers and see the answer, with the sum shown.

The Society for Maintenance & Reliability Professionals (SMRP) lists a metric of its own, Planned Work, in its Best Practices. Its metrics workshop material counts shutdowns and operators’ maintenance hours, where recorded, in the total and typically leaves out temporary contractors. Whatever you choose, write it down.

PMP example: planned and unplanned hours on six assets

The same six made-up assets as in the MTBF entry, over one quarter, in technicians’ labor hours:

59 hPlanned
43 work orders
40 hUnplanned
13 work orders
77%Planned, by count
43 ÷ 56 work orders
60%PMP, by hours
59 ÷ 99 hours

Same quarter, same crew, 17 points apart. The planned jobs are many and short, the breakdowns few and long: three conveyor repairs took 12 hours, more than its 13 planned jobs together. Counting work orders lets the short planned jobs outvote the long breakdowns.

The six assets, line by lineFour of them spend more hours on breakdowns than on planned work: the candidates for a better preventive task.
Asset Planned hours Unplanned hours PMP Planned work orders Unplanned work orders
Air compressor 1 18 4 82% 14 2
Conveyor CV-3 10 12 45% 13 3
Dock door 3 2 4 33% 2 1
Mixer M-2 8 12 40% 4 2
Labeler 5 6 45% 6 4
Boiler 16 2 89% 4 1
All six 59 40 60% 43 13

Each breakdown took two technicians, so its labor hours are twice the hands-on hours in the MTTR entry. The boiler’s one unplanned job, a noisy feed pump, did not stop it. Every number is made up.

PMP and a count-based preventive ratio

  • A count runs high when planned jobs are short and breakdowns long, as above.
  • Preventive is not the same as planned. A repair found on an inspection and booked for Saturday is planned but not preventive: it raises PMP and leaves a preventive ratio alone. The planned maintenance entry draws that line.
  • Pick one and keep it. Say which it is, and do not switch halfway through a year.

Reading PMP beside PM compliance, monthly or quarterly

A rise is good only if breakdowns fell

PMP can rise because breakdown hours fell, or because preventive work was padded with extra tasks. Read it beside PM compliance, and when it falls, the per-asset split shows which machine’s breakdowns grew.

The maintenance KPIs guide has a one-page monthly report to put it in.

The preventive ratio in Maintensor, and how it differs from PMP

Reporting in Maintensor, on Pro and Max and open to Admins, shows a preventive ratio, not PMP: the share of work orders created in the date range whose type is Preventive, on the Work orders by type card with its trend over six periods. It counts work orders, not hours, and reads the work type, not whether the job was planned.

Time is logged on work orders on every plan, but Reporting does not split it into planned and unplanned hours, so an hours-based PMP is worked out by hand.

Questions

What people also ask.

More in the glossary, or see the whole product on the features page.

What is a good planned maintenance percentage?

Published targets exist, but they vary by source and assume a definition of planned work and a way of logging hours that a small site rarely matches. The safer test is direction: is your PMP rising over the year, and is it rising because breakdown hours fell rather than because preventive work was padded? Read it beside PM compliance and downtime.

How is planned maintenance percentage different from PM compliance?

PMP tells you how the crew's hours were split between planned work and breakdowns. PM compliance tells you whether the preventive tasks that fell due were done on time. A site can score well on one and badly on the other: few PMs, all done on time, in a week swamped by breakdowns gives high compliance and a low PMP.