The PM compliance formula, and what counts as on time
PM compliance = PM jobs done on time ÷ PM jobs due × 100
- PM jobs due
- every preventive job due in the period, done or not, unless taken off the schedule
- Done on time
- done by the due date, or inside the window your rule allows
On time has three common rules:
The share rule scales: a day late matters more on a weekly job than on a yearly one. None of these is wrong. Changing rules from month to month is.
A worked month
A made-up building crew has 40 preventive jobs due in September: 20 weekly, 14 monthly, 4 quarterly and 2 yearly. The same month under each rule:
31 ÷ 40
35 ÷ 40
36 ÷ 40
Twelve and a half points apart, from one month of work.
The month, line by lineEach of the 40 jobs, and which rule counts it.
| What happened | Jobs |
|---|---|
| Done on or before the due date | 31 |
| Monthly jobs done 1 to 3 days late | 3 |
| Weekly jobs done 1 or 2 days late | 2 |
| A quarterly job done 6 days late | 1 |
| A monthly job done 8 days late | 1 |
| Not done by month’s end | 2 |
| Due | 40 |
The 10% rule adds the three monthly jobs (inside 3 days) and the quarterly one (inside 9); the weekly jobs fall outside a window of less than a day. The 3-day grace adds the three monthly and the two weekly jobs. Every number is made up.
PM compliance vs schedule compliance and planned maintenance percentage
- Schedule compliance asks whether the week’s plan was done, repairs included, against the week each job was scheduled for.
- Planned maintenance percentage is the share of maintenance hours spent on planned work. It can be high while preventive jobs run late.
PM compliance each month, with the missed jobs and why
Keep the missed list beside the figure
Work it out monthly, with a reason for each missed job, and watch for due dates moved to make a late job look on time. A figure built on pencil whipping is worse than a low one.
The maintenance KPIs guide covers reading the reasons, and building a preventive maintenance schedule spreading the load.
Recurring on time in Maintensor, the closest to PM compliance
Reporting in Maintensor, on Pro and Max for admins, shows an On time figure and an “On time vs. late” card for the work orders due in the date range, split into recurring and non-recurring work.

Recurring on time is the closest figure to PM compliance, with three differences:
- Recurring is not preventive. It counts work orders made by a repeat, whatever their type of work.
- On time means completed by the end of the due date, with no grace window, and open work not yet due counts as on time.
- Missed repeats are not counted one by one. A repeating job’s next work order is created only when the current one is completed, so a monthly job left undone for three months is one late work order, not three misses. Read the Overdue list next to the figure.