What is PM compliance?

PM compliance is the share of preventive jobs due in a period that were done on time: by the due date, or inside a grace window you set. When it falls, the crew is short of hours for its schedule.

By MaintensorUpdated

The PM compliance formula, and what counts as on time

PM compliance = PM jobs done on time ÷ PM jobs due × 100

PM jobs due
every preventive job due in the period, done or not, unless taken off the schedule
Done on time
done by the due date, or inside the window your rule allows
PM compliance calculatorType your own numbers and see the answer, with the sum shown.

On time has three common rules:

By the due dateOn or before it: the simplest, strictest rule.
A fixed grace periodWithin a set number of days after it, such as 3, for every job alike.
A share of the intervalWithin a share of it, often 10%: about 3 days for a monthly job, 9 for a quarterly one, less than a day for a weekly one.

The share rule scales: a day late matters more on a weekly job than on a yearly one. None of these is wrong. Changing rules from month to month is.

A worked month

A made-up building crew has 40 preventive jobs due in September: 20 weekly, 14 monthly, 4 quarterly and 2 yearly. The same month under each rule:

77.5%By the due date
31 ÷ 40
87.5%Within 10% of the interval
35 ÷ 40
90%A fixed 3-day grace
36 ÷ 40

Twelve and a half points apart, from one month of work.

The month, line by lineEach of the 40 jobs, and which rule counts it.
What happened Jobs
Done on or before the due date 31
Monthly jobs done 1 to 3 days late 3
Weekly jobs done 1 or 2 days late 2
A quarterly job done 6 days late 1
A monthly job done 8 days late 1
Not done by month’s end 2
Due 40

The 10% rule adds the three monthly jobs (inside 3 days) and the quarterly one (inside 9); the weekly jobs fall outside a window of less than a day. The 3-day grace adds the three monthly and the two weekly jobs. Every number is made up.

PM compliance vs schedule compliance and planned maintenance percentage

  • Schedule compliance asks whether the week’s plan was done, repairs included, against the week each job was scheduled for.
  • Planned maintenance percentage is the share of maintenance hours spent on planned work. It can be high while preventive jobs run late.

PM compliance each month, with the missed jobs and why

Keep the missed list beside the figure

Work it out monthly, with a reason for each missed job, and watch for due dates moved to make a late job look on time. A figure built on pencil whipping is worse than a low one.

The maintenance KPIs guide covers reading the reasons, and building a preventive maintenance schedule spreading the load.

Recurring on time in Maintensor, the closest to PM compliance

Reporting in Maintensor, on Pro and Max for admins, shows an On time figure and an “On time vs. late” card for the work orders due in the date range, split into recurring and non-recurring work.

On time vs. late: 93% on time, 201 work orders on time and 14 late, with recurring work 100% on time and non-recurring 93%.
On time vs. late: 93% on time, 201 work orders on time and 14 late, with recurring work 100% on time and non-recurring 93%.

Recurring on time is the closest figure to PM compliance, with three differences:

  1. Recurring is not preventive. It counts work orders made by a repeat, whatever their type of work.
  2. On time means completed by the end of the due date, with no grace window, and open work not yet due counts as on time.
  3. Missed repeats are not counted one by one. A repeating job’s next work order is created only when the current one is completed, so a monthly job left undone for three months is one late work order, not three misses. Read the Overdue list next to the figure.

Questions

What people also ask.

More in the glossary, or see the whole product on the features page.

What is a good PM compliance rate?

Compare your crew with itself before comparing it with anyone else, because the on-time rule changes the number a lot. Pick one rule and report it the same way every month.

Does a PM done early count as compliant?

Under a simple by-the-due-date rule, yes: early is on time. Sites that use a window often apply it both ways, because a job done well before its date shortens the gap since the last one, and for wear items the gap is the point. Decide which you mean and keep to it.