PM compliance formula
PM compliance = PM jobs done on time ÷ PM jobs due × 100
- PM jobs due
- every preventive job due in the period, done or not, unless taken off the schedule
- Done on time
- done by the due date, or inside the window your rule allows
How to calculate PM compliance
- Count the PM jobs due. Every preventive job due in the period, done or not.
- Pick your on-time rule. Then keep the same one every month.
- Count those done on time. Keep a list of the rest, with why.
Three rules for on time
PM compliance example: one month, three ways
A made-up building crew has 40 preventive jobs due in September.
31 ÷ 40
35 ÷ 40
36 ÷ 40
Twelve and a half points apart, from one month of work. That is why the rule has to stay fixed.
What your PM compliance tells you
- When it falls, look at hours. The crew is usually short of time for its schedule. Check the backlog in crew-weeks.
- Spread the load. The schedule maker shows which months hold too many jobs.
Keep the missed list beside the figure
Work it out monthly, with a reason for each missed job. The reasons are what you act on.