PM compliance calculator

Work out what share of the preventive jobs due in a period were done on time.

Free, no sign-up. Nothing you type leaves your browser.

Calculate PM compliance

Showing the example from further down this page. Type your own numbers over it.

By the due date, or in your grace window.

Every preventive job due, done or not.

PM compliance77.5%

31 jobs done on time ÷ 40 jobs due = 77.5%

9 of 40 jobs were late or not done.

PM compliance formula

PM compliance = PM jobs done on time ÷ PM jobs due × 100

PM jobs due
every preventive job due in the period, done or not, unless taken off the schedule
Done on time
done by the due date, or inside the window your rule allows

How to calculate PM compliance

  1. Count the PM jobs due. Every preventive job due in the period, done or not.
  2. Pick your on-time rule. Then keep the same one every month.
  3. Count those done on time. Keep a list of the rest, with why.

Three rules for on time

By the due date
On or before it: the simplest and strictest rule.
A fixed grace period
Within a set number of days after it, such as 3, for every job alike.
A share of the interval
Often 10%: about 3 days for a monthly job, 9 for a quarterly one.

PM compliance example: one month, three ways

A made-up building crew has 40 preventive jobs due in September.

77.5%By the due date
31 ÷ 40
87.5%Within 10% of the interval
35 ÷ 40
90%A fixed 3-day grace
36 ÷ 40

Twelve and a half points apart, from one month of work. That is why the rule has to stay fixed.

What your PM compliance tells you

  • When it falls, look at hours. The crew is usually short of time for its schedule. Check the backlog in crew-weeks.
  • Spread the load. The schedule maker shows which months hold too many jobs.

Keep the missed list beside the figure

Work it out monthly, with a reason for each missed job. The reasons are what you act on.

PM compliance questions

Which on-time rule should I use?

Any of the three, as long as it stays the same from month to month. A share of the interval scales best, since a day late matters more on a weekly job than on a yearly one. By the due date is the simplest.

Does a job that was never done count?

Yes. It stays in the jobs due, unless it was taken off the schedule, and it is not in the jobs done on time.

Can a crew make this number look better than it is?

Yes, by moving due dates so a late job looks on time, or by ticking jobs off without doing them. Keep the list of missed jobs and their reasons next to the figure, and watch for either.