Schedule compliance calculator

Work out how much of the week's maintenance schedule was done as planned.

Free, no sign-up. Nothing you type leaves your browser.

Calculate schedule compliance

Showing the example from further down this page. Type your own numbers over it.

Only work that was on the schedule.

As published the Friday before.

Schedule compliance81%

78 h completed ÷ 96 h scheduled = 81%

18 of 96 scheduled hours were not done as scheduled.

Schedule compliance formula

schedule compliance = scheduled hours completed ÷ scheduled hours × 100

Scheduled hours
the week's work as the schedule was published, the Friday before
Scheduled hours completed
the hours of that work done during the week

How to calculate schedule compliance

  1. Write the schedule down on Friday. Jobs added later do not count.
  2. A week later, count what was done. Only the work on that list.
  3. Enter both, in hours. Then write a reason beside each miss.

Schedule compliance example: one week for a crew of three

On Friday a made-up supervisor schedules 18 jobs for next week, 96 hours in all. By the next Friday, 14 of them are done.

78%In jobs
14 ÷ 18
81%In hours
78 ÷ 96

Why jobs get missed, and the fix for each

Work broke in
Hold back more room for breakdowns when you build the next week.
The part was not there
Chase it earlier, or do not schedule the job until it is on the shelf.
The machine was not released
Agree the stop with production before the schedule goes out.
The estimate was too small
Fix the estimate for next time. That is a planning miss, not a crew miss.

Do not punish a low figure

A crew blamed for misses learns to schedule less, and the number rises while the work done stays the same. Watch the trend over a few months, not one week.

Schedule compliance questions

Can I count jobs instead of hours?

Yes. The boxes say hours, but the sum is the same: 14 jobs done out of 18 gives 78%. Jobs are easier when estimates are rough. Hours are fairer, because a missed six-hour job weighs more than a missed bulb change. Pick one and say which.

How do I count a job left half done?

Not done is simplest. Counting the hours worked is fairer: in the example, the 3 hours worked on a half-done job make it 81 ÷ 96 = 84%. Decide once and keep to it.

Should emergency work count?

No. Work that broke in was not on the schedule, so it is in neither number. Track it separately, and if it keeps pushing scheduled work out, hold back more room for it next week.