Maintenance backlog formula
backlog in crew-weeks = backlog hours ÷ crew hours a week for backlog work
- Backlog hours
- the estimated hours of every approved job not yet finished
- Crew hours for backlog work
- paid hours less time off, training, daily rounds and the usual breakdowns
How to calculate your maintenance backlog
- Add up the backlog. Estimated hours of every approved job not finished.
- Work out the crew's free hours. Paid hours, less time off, rounds and usual breakdowns.
- Write it down each Friday. One number says little; six Fridays say more.
Maintenance backlog example: 280 hours of work for a crew of three
3 people × 40 h
120 − 30 for breakdowns and rounds
268 estimated + 12 placeholder
280 ÷ 90
The plant and its numbers are made up.
What the trend tells you
Split the total into ready work, which could start on Monday, and work still waiting.
Your own trend beats a quoted target
Quoted targets come from large plants with full-time planners. A total that grows for a month or more means work is arriving faster than the crew finishes it.