Maintenance backlog calculator

Turn your backlog hours into crew-weeks: how long the approved work would take to clear.

Free, no sign-up. Nothing you type leaves your browser.

Calculate your backlog in crew-weeks

Showing the example from further down this page. Type your own numbers over it.

Estimates for approved jobs not finished.

Paid hours, less time off and rounds.

Backlog3.1 crew-weeks

280 h ÷ 90 h a week = 3.1 crew-weeks

With nothing new coming in, the crew would clear it in about 3.1 weeks.

Maintenance backlog formula

backlog in crew-weeks = backlog hours ÷ crew hours a week for backlog work

Backlog hours
the estimated hours of every approved job not yet finished
Crew hours for backlog work
paid hours less time off, training, daily rounds and the usual breakdowns

How to calculate your maintenance backlog

  1. Add up the backlog. Estimated hours of every approved job not finished.
  2. Work out the crew's free hours. Paid hours, less time off, rounds and usual breakdowns.
  3. Write it down each Friday. One number says little; six Fridays say more.

Maintenance backlog example: 280 hours of work for a crew of three

120 hPaid hours a week
3 people × 40 h
90 hLeft for backlog work
120 − 30 for breakdowns and rounds
280 hBacklog
268 estimated + 12 placeholder
3.1Crew-weeks
280 ÷ 90

The plant and its numbers are made up.

What the trend tells you

Split the total into ready work, which could start on Monday, and work still waiting.

Ready backlog too small
Next week cannot be filled with planned work.
Waiting backlog growing
The problem is parts, contractors or access, not labor. More people would not help.
Both growing
The crew is short of hours. Cut work not worth doing, contract some out, or ask for another person.

Your own trend beats a quoted target

Quoted targets come from large plants with full-time planners. A total that grows for a month or more means work is arriving faster than the crew finishes it.

Maintenance backlog questions

What do I do about jobs with no estimate?

Give each one a placeholder, such as 2 hours, and say so. In the example, 46 work orders have estimates totaling 268 hours, and 6 without one add 12 hours. A rough total you can repeat every Friday beats an exact one you never work out.

How many crew hours should I enter?

Not the paid hours. Take off time off, training, daily rounds and the usual breakdowns, and enter what is left. Three people at 40 hours is 120 paid; with 30 going to breakdowns and rounds, 90 are left for the backlog.

What goes in the backlog?

Repairs, preventive jobs that have come due and small projects, once approved. Leave out requests nobody has approved and preventive jobs not due yet.