Wrench time formula
wrench time = hands-on hours ÷ paid hours × 100
- Hands-on hours
- the work itself; many sites add diagnosis at the machine, the lockout and the test run
- Left out
- travel, waiting for parts or permits, fetching tools, meetings, breaks and paperwork
How to calculate wrench time
- Take one week's paid hours. People × hours, for the whole crew.
- Work out the hands-on hours. Paid hours, less meetings, breaks, paperwork and delays.
- Enter both. Then look at the delays, not the percentage.
Wrench time example: a crew of four, from three weeks of delay notes
4 people × 40 h
parts the biggest, at 14 h
103 ÷ 160
It is an upper limit, since people forget short delays. Everything here is made up.
What your wrench time tells you
- Fix the biggest delay first. In this crew that is parts, so the supervisor starts pulling them the day before. Parts drop to 6 hours a week: 8 hours back, about a person-day.
- Then check the plan holds. Low wrench time is often why the schedule compliance is low too.
Measure it to find delays, not to rate people
People work differently while watched, and notes dry up once they are used against anyone. Say at the start what the notes are for.