What is wrench time?

Wrench time is the share of a technician's paid hours spent on hands-on work: tools on the job, not walking, waiting or paperwork. It is measured to find delays, not to rate people.

By MaintensorUpdated

What wrench time counts, and what it leaves out

wrench time = hands-on hours ÷ paid hours × 100

Hands-on hours
the work itself; many sites add diagnosis at the machine, the lockout and the test run
Left out
travel, waiting for parts or permits, fetching tools, meetings, breaks and paperwork
Wrench time calculatorType your own numbers and see the answer, with the sum shown.

Write down where you draw the line, and keep it. A low figure is almost never about effort: it is parts not ready, a job that says “fix conveyor”, a machine nobody will release. Each delay found is an hour back, with no one hired.

How it is measured, and why small crews rarely do it

The usual method is work sampling: an observer notes what each technician is doing at hundreds of random moments over several weeks, and the hands-on share of moments stands for the share of time.

A crew of four rarely does it: the observer would be a supervisor who also turns wrenches, people work differently while watched, and one big breakdown can swing so small a sample.

A cheaper way to see where the time goes

One line on every job

For two to four weeks, have each technician note on every job what held it up and for how long, to the nearest 15 minutes. Tally them weekly, and fix the biggest group first.

Wrench time example: three weeks of delay notes from a crew of four

A made-up crew of four, after three weeks of delay notes:

160 hPaid a week
4 people × 40 h
20 hMeetings, breaks, paperwork
37 hDelays noted
parts the biggest, at 14 h
64%Wrench time, at most
103 ÷ 160

It is an upper bound, since people forget short delays, and the list matters more. Parts top it, so the supervisor starts pulling parts the day before and keeps common ones by the line. Three weeks later parts take 6 hours a week: 8 hours back, about a person-day.

The crew's numbers, line by lineWhat held the jobs up, as a weekly average.
What held the job up Hours a week
Waiting for parts, or fetching them 14
Waiting for equipment to be stopped or released 8
Looking for tools, a lift or keys 6
Walking between jobs across the site 5
Finding out what the job was, or which machine 4
Total delays 37

160 − 20 − 37 = 103 hours, and 103 ÷ 160 = 64%. Every number is made up.

Wrench time vs labor utilization, schedule compliance and first-time fix

  • Labor utilization counts hours logged on jobs, walking and waiting included.
  • Schedule compliance asks whether the planned jobs got done. Low wrench time is often why not.
  • First-time fix rate asks whether the first visit fixed it; a second trip for a missing part shows in both.

Maintenance planning and scheduling covers the job plans and parts kits that remove the biggest delays, and the planner job description whether a full-time planner pays for itself.

Logged time and labor utilization in Maintensor, not wrench time

Time in Maintensor runs from Start work until the job is put On hold or completed, and can be added or fixed by hand: time in someone’s hands, the walk to the storeroom included. On Max, Reporting’s labor utilization compares it with 8 hours every weekday per person, with no allowance for time off. Neither is wrench time.

When a job stops for a part, put it On hold with a note saying why: the time stops, and History keeps the status change and the note, so a month of them is the delay log above. The planner shows which jobs are short of parts before the day.

Questions

What people also ask.

More in the glossary, or see the whole product on the features page.

What is a good wrench time?

There is no figure that fits every site, and the ones passed around come from large plants measured in different ways. Compare your crew with itself, fix the delays you find, and the share of hands-on time rises as they go.

Is wrench time the same as labor utilization?

No. Labor utilization compares the hours logged on work orders with the hours available, so a job left running during a walk to the storeroom counts in full. Wrench time counts only the hands-on part. A crew can log nearly all its time on jobs and still spend much of it waiting.

Plan next week against the hours people have.