What wrench time counts, and what it leaves out
wrench time = hands-on hours ÷ paid hours × 100
- Hands-on hours
- the work itself; many sites add diagnosis at the machine, the lockout and the test run
- Left out
- travel, waiting for parts or permits, fetching tools, meetings, breaks and paperwork
Write down where you draw the line, and keep it. A low figure is almost never about effort: it is parts not ready, a job that says “fix conveyor”, a machine nobody will release. Each delay found is an hour back, with no one hired.
How it is measured, and why small crews rarely do it
The usual method is work sampling: an observer notes what each technician is doing at hundreds of random moments over several weeks, and the hands-on share of moments stands for the share of time.
A crew of four rarely does it: the observer would be a supervisor who also turns wrenches, people work differently while watched, and one big breakdown can swing so small a sample.
A cheaper way to see where the time goes
One line on every job
For two to four weeks, have each technician note on every job what held it up and for how long, to the nearest 15 minutes. Tally them weekly, and fix the biggest group first.
Wrench time example: three weeks of delay notes from a crew of four
A made-up crew of four, after three weeks of delay notes:
4 people × 40 h
parts the biggest, at 14 h
103 ÷ 160
It is an upper bound, since people forget short delays, and the list matters more. Parts top it, so the supervisor starts pulling parts the day before and keeps common ones by the line. Three weeks later parts take 6 hours a week: 8 hours back, about a person-day.
The crew's numbers, line by lineWhat held the jobs up, as a weekly average.
| What held the job up | Hours a week |
|---|---|
| Waiting for parts, or fetching them | 14 |
| Waiting for equipment to be stopped or released | 8 |
| Looking for tools, a lift or keys | 6 |
| Walking between jobs across the site | 5 |
| Finding out what the job was, or which machine | 4 |
| Total delays | 37 |
160 − 20 − 37 = 103 hours, and 103 ÷ 160 = 64%. Every number is made up.
Wrench time vs labor utilization, schedule compliance and first-time fix
- Labor utilization counts hours logged on jobs, walking and waiting included.
- Schedule compliance asks whether the planned jobs got done. Low wrench time is often why not.
- First-time fix rate asks whether the first visit fixed it; a second trip for a missing part shows in both.
Maintenance planning and scheduling covers the job plans and parts kits that remove the biggest delays, and the planner job description whether a full-time planner pays for itself.
Logged time and labor utilization in Maintensor, not wrench time
Time in Maintensor runs from Start work until the job is put On hold or completed, and can be added or fixed by hand: time in someone’s hands, the walk to the storeroom included. On Max, Reporting’s labor utilization compares it with 8 hours every weekday per person, with no allowance for time off. Neither is wrench time.
When a job stops for a part, put it On hold with a note saying why: the time stops, and History keeps the status change and the note, so a month of them is the delay log above. The planner shows which jobs are short of parts before the day.