Work request vs work order: what is the difference?

A work request is someone telling maintenance that something is wrong. A work order is maintenance deciding to do something about it: what, by whom, by when and with which parts.

By MaintensorUpdated 9 min read

Key points

  • A work request reports a problem; a work order commits the crew's hours and parts to fix it.
  • Anyone can ask; only someone who can see the crew's whole week writes the work order.
  • The asker says how urgent it feels; maintenance sets the priority.
  • Every request is approved or declined, and the asker hears which, with a reason for a no.
  • A purchase order is the third document: it commits money to a vendor.

The difference, line by line

A request asks and a work order authorizes.

Work request Work order
Written by Anyone who notices: an operator, a teacher, a front desk clerk, a tenant Maintenance: a supervisor, a planner or a technician
Written in The asker’s words: “the mixer squeals” The technician’s words: “M-2 drive belts slipping at start-up, check tension and wear”
Urgency or priority How urgent it feels to the asker A priority set by maintenance, against everything else that is open
Names a person and a date No person, no date Yes: who does it, and when it is due
Spends anything No, nothing yet Labor hours and parts, sometimes a contractor
Can be turned down Yes, with a reason It can be canceled, but a decision was already made
Ends when It is approved into a work order, or declined The job is done and closed
Leaves behind A record that someone asked, when, and what they were told The asset’s history: what was found and done, the parts, the time
Counts toward Demand: how many asked, and how fast they heard back Backlog, on-time work, repair time, planned against unplanned

Between the two sits one decision, yes or no, and the person who asked should always hear which. What a work order is covers the work order itself.

An approved request: approved by the maintenance manager at 7:05, with a link to the work order it became, which is in progress.
An approved request: approved by Maria Chen at 7:05, with a link to the work order it became, which is in progress.

Two differences cause most of the confusion.

Urgency is not priority
The person asking knows how much the problem bothers them. They do not know that another line is down, or that the part is on a truck until Thursday. Let them say how urgent it feels. Maintenance sets the priority.
A request is not a promise
Sending one tells maintenance about a problem. It does not book a technician. A site that treats every request as a work order ends up with a list nobody can finish, ordered by whoever writes the most.

Who writes each

Requests come from the people closest to the problem and furthest from the toolbox. They see the symptom first, and nobody expects them to know the cause, the part number or the tag on the air handler.

Work orders come from maintenance: the planner where there is one, from approved requests and the preventive schedule. In a crew of three, the lead writes them, and technicians write their own when they find something on rounds. Making a technician file a request about their own finding adds a step and saves nothing.

The line is not rank

It is who can see the crew’s whole week. Anyone can ask. Only someone who knows what else is open can commit the crew’s hours.

What authorizes the work

Approving the work order is what authorizes the work, even where nobody calls it that. It says four things.

The job is worth the hours
A crew of four has about 160 hours a week before meetings, breaks and walking. Every approved job takes some of those hours from something else.
The parts and the money are allowed
A filter off the shelf needs nobody’s signature. A new motor or a contractor’s visit may need a manager’s, and the work order is where that approval is written down.
The equipment can be stopped
Taking a line, a room or a loading door out of service is a decision for maintenance and the people who run it, not for the person who reported the noise.
The job is safe to start
Whoever writes the work order decides whether it needs a lockout, a hot work permit, a second person or a licensed contractor. The person asking cannot judge that, and should not have to.

Without the split, whoever has the crew’s phone number sets the crew’s day.

From request to work order, step by step

  1. Report. The asker says what is wrong, where, and how urgent it seems.
  2. Decide. Someone who reads new requests each working day approves it, declines it with a reason, or asks one question first (“which restroom, second floor or third?”).
  3. Write the work order. Rewrite the title in the technician’s words, set the priority, attach the asset, add the steps and the parts, and give it a person and a due date.
  4. Tell the asker. Approved and roughly when, or declined and why. When the work order is done, they hear that it is fixed.

Setting up a request process people will use covers the form, the queue and the answers, and planning and scheduling covers getting the work order ready. Emergencies skip the queue on the way in: the fix comes first and the paperwork after, as emergency maintenance explains.

ExampleDock door 6, as requested and as a work order

What changes between the request and the work order, for a made-up warehouse dock door:

As requested As a work order
Title “Dock door 6 stuck” “Dock door 6: stops a foot short of closed and reverses; check photo eyes and bottom limit”
Urgency, then priority Urgent Medium: the door closes on a second try, and door 5 is free for that trailer
Where “Shipping, door 6” Overhead door OD-6, shipping dock
Who and when Not said Greg Thompson, due tomorrow
Parts Not said One set of photo eyes, in stock
Safety Not said Lock out the door operator before working on the limit switch

Two examples: a building and a hotel

Both are made up, and the names belong to no real site. In the building, three requests about one problem become one work order, and a no with a reason and a next step keeps tenants reporting. In the hotel, a part is not on the shelf, so a purchase order joins the chain.

A building: three requests, one problemThree tenants report the same heat, and one work order comes of it

Between 1:10 and 1:45 p.m., three tenants on the third floor of an office building send requests. Susan Clarke, who runs the building, answers each one.

Request Susan’s answer
“too hot” Approved as one work order: “RTU-4: 3rd floor west above setpoint, unit running, check condenser and filters.” Priority High, due today, assigned to Jason Miller.
“AC not working” Declined: “Already being worked on as WO-3104. Jason is on the roof now, and we will post on the third floor when it is fixed.”
“it’s 80 degrees in here” Declined, with the same reason
The same week, a tenant asks for the lobby to be repainted Declined: “Painting is on next spring’s building refresh. I have added the lobby to that list.”
A hotel: the loud air conditioner and a purchase orderA night request, a morning work order, and a motor on order
  1. The request, 10:15 p.m. Megan Doyle at the front desk sends a request: “Room 214, guest says the AC is very loud. Urgent.”
  2. A look that night. Alex Turner, the night technician, hears a fan motor bearing on its way out. The guest moves to room 220.
  3. The work order, next morning. Frank Morris, the chief engineer, approves it: “Room 214: PTAC fan motor bearing noisy, replace motor.” Priority High, and the room stays out of order.
  4. A purchase order. With no spare motor on the shelf, Frank sends a purchase order to the hotel’s HVAC supplier. The work order goes on hold, so anyone looking at the list can see why it is not moving.
  5. Fixed on Friday. The motor arrives, Alex fits it that afternoon, and the room goes back on sale.

Where the purchase order fits

A purchase order is the third document: an order to a vendor for what you are buying, how many, and at what price.

  • Written by maintenance or purchasing, and approved by whoever holds the budget.
  • Commits money, at an agreed price. A work order commits the crew’s hours and parts from stock.
  • Closes when the goods are received and the bill matches.

The counts do not have to match. Several requests can point to one work order, a work order can need no purchase order or several, and a purchase order can serve no single job, as when it restocks a shelf of filters.

How much to keep on hand, so fewer jobs wait on an order, is the subject of spare parts inventory management.

Mistakes that blur the line

  • Requests nobody answers. The asker cannot tell a request that was read from one that was lost, so they send it again, or stop sending.
  • The asker’s words stay as the title. “Broken” in the work order list sends the technician out to ask what is broken.
  • Too much approval for small jobs. If a light bulb needs a manager’s sign-off, people will skip the process and find a technician.

When not to bother

If the same one or two people both report and fix, as in a small shop where the owner spots the problem and the technician fixes it that day, a shared list of jobs is enough. The split earns its keep once more people ask than fix.

How Maintensor handles requests and work orders

In Maintensor, maintenance requests and work orders are two lists, with the decision between them.

A requester signs in with a code sent to their email and presses Report a problem. The form asks What is wrong? (the only required field), How urgent (Not sure, Can wait, Soon or Urgent), Any detail and Where is it?, and tells them that maintenance sets the real priority. While a request is still waiting, they can edit it or withdraw it, and they follow everything they sent on My requests.

An Admin decides. Approving opens a new work order from the request, with its title, description, priority, due date, asset and location to set before Create work order. Declining needs a reason, and the requester reads it. There is no question back in the app, so ask by phone or in person. A work order made this way names the request it came from for an Admin.

Limits worth knowing

  • Only Admins see the request queue. A Full user, usually a technician, has no Requests screen and writes a work order instead.
  • Only Admins and Requesters submit requests. A Requester reports and follows, nothing else: running a checklist takes a Full user seat.
  • A Requester’s Where is it? picker lists every location and asset, so a tenant sees the names across the site, not only their own floor.
  • There is no public or guest form and no photo on a request.

On Pro and Max, a requester who scans the QR label on an asset or a location gets Report a problem with it filled in. Requesters are free on every plan. Email notices to the asker are on Pro and Max, and purchase orders are on Max.

Questions

What people also ask.

More in the blog, or see the whole product on the features page.

Is a maintenance request the same as a work request?

Yes. Work request, maintenance request, service request, repair request and trouble call are names for the same thing: someone outside the crew reporting a problem. The name matters less than the rule behind it. A request asks for work, and only maintenance turns it into a work order that commits the crew's time.

Who approves a work request?

Usually the maintenance supervisor or manager, or in a small crew the lead technician. Name one person who reads requests every working day and one backup for when they are out. Routine approvals should take seconds. The point is that someone who can see the crew's whole week decides, not whoever asked the loudest.

Should every work request become a work order?

No. Some requests repeat a job that is already open, some are already on the schedule, some belong to another department, and some are wishes that need a budget first. Those are declined with a reason that says what happens next. Approving everything turns the work order list into an inbox nobody can finish.

Do technicians need to write a work request?

Usually not. A technician who finds a problem on rounds knows what the job needs, so most sites let the crew write work orders directly. The request step is for people outside maintenance, who see the symptom first but cannot judge the job or commit the crew's hours.