Measuring schedule compliance, and four rules that keep it honest
schedule compliance = scheduled hours completed ÷ scheduled hours × 100
- Scheduled hours
- the week's work as the schedule was published, the Friday before
- Scheduled hours completed
- the hours of that work done during the week
Counting jobs instead of hours is easier when estimates are rough. Hours are fairer, because a missed six-hour job weighs more than a missed bulb change; pick one and say which. Four rules make the number mean something:
A worked week
A made-up crew of three. On Friday the supervisor schedules 18 jobs for the next week, 96 hours in all. By the following Friday, 14 of them, 78 hours, are done as scheduled.
14 ÷ 18
78 ÷ 96
The week, line by lineEvery number is invented.
| Result | Jobs | Hours |
|---|---|---|
| Done as scheduled | 14 | 78 |
| Not started: hours went to a compressor failure | 2 | 8 |
| Not started: part did not arrive | 1 | 4 |
| Half done: estimate of 6 hours was too small | 1 | 6 |
| Scheduled | 18 | 96 |
Counting the 3 hours worked on the half-done job gives 81 ÷ 96 = 84%. The compressor took 22 hours of the week: it counts nowhere in the figure, but it explains two of the four misses.
The number goes in the report. The reasons are what you act on: hold back more room for breakdowns, chase the part earlier, fix the estimate.
How it differs from PM compliance
| Schedule compliance | PM compliance | |
|---|---|---|
| Counts | Every job on the week’s schedule, preventive and repairs | Preventive jobs due in the period |
| Judged against | The week (or day) it was scheduled for | Its due date, or a grace window |
| The question | Can we trust our plan? | Is preventive work done on time? |
The two can disagree. A preventive job scheduled for the day after its due date, and done that day, is on schedule and still late. Maintenance KPIs covers how both fit with the other numbers a small team reports.
Schedule compliance at the Friday review, with a reason per miss
Work it out at the Friday review, before building next week, and write a reason beside each miss: broke in, part not there, equipment not released, estimate too small, someone out. How to build a weekly maintenance schedule walks through the review and the fix for each.
Do not punish a low figure
A crew blamed for misses learns to schedule less, and the number rises while the work done stays the same. Watch the trend over a few months, not one week.
Why Maintensor cannot rebuild last Friday’s schedule
Maintensor has no schedule compliance figure. On the planner, moving a job changes its start date, and a work order’s History does not record date changes, so the app keeps no copy of Friday’s schedule.
Write the list down when you publish the week, and count against it the next Friday. Reporting’s On time measures something else: work orders done by their due date, not by the day they were planned for.