What is schedule compliance?

Schedule compliance is the share of the week's maintenance schedule that was done that week, counted in hours or jobs, leaving out anything that broke in. It tells a crew whether it can trust its own plan.

By MaintensorUpdated

Measuring schedule compliance, and four rules that keep it honest

schedule compliance = scheduled hours completed ÷ scheduled hours × 100

Scheduled hours
the week's work as the schedule was published, the Friday before
Scheduled hours completed
the hours of that work done during the week
Schedule compliance calculatorType your own numbers and see the answer, with the sum shown.

Counting jobs instead of hours is easier when estimates are rough. Hours are fairer, because a missed six-hour job weighs more than a missed bulb change; pick one and say which. Four rules make the number mean something:

Freeze the schedule when it is publishedJobs added during the week are not part of it.
Leave out work that broke inIt is in neither the top nor the bottom of the calculation.
Decide when a job counts as doneMost crews count any day that week; stricter ones only its scheduled day.
Decide what to do with half-finished jobsNot done is simplest; counting the hours worked is fairer.

A worked week

A made-up crew of three. On Friday the supervisor schedules 18 jobs for the next week, 96 hours in all. By the following Friday, 14 of them, 78 hours, are done as scheduled.

78%In jobs
14 ÷ 18
81%In hours
78 ÷ 96
The week, line by lineEvery number is invented.
Result Jobs Hours
Done as scheduled 14 78
Not started: hours went to a compressor failure 2 8
Not started: part did not arrive 1 4
Half done: estimate of 6 hours was too small 1 6
Scheduled 18 96

Counting the 3 hours worked on the half-done job gives 81 ÷ 96 = 84%. The compressor took 22 hours of the week: it counts nowhere in the figure, but it explains two of the four misses.

The number goes in the report. The reasons are what you act on: hold back more room for breakdowns, chase the part earlier, fix the estimate.

How it differs from PM compliance

Schedule compliance PM compliance
Counts Every job on the week’s schedule, preventive and repairs Preventive jobs due in the period
Judged against The week (or day) it was scheduled for Its due date, or a grace window
The question Can we trust our plan? Is preventive work done on time?

The two can disagree. A preventive job scheduled for the day after its due date, and done that day, is on schedule and still late. Maintenance KPIs covers how both fit with the other numbers a small team reports.

Schedule compliance at the Friday review, with a reason per miss

Work it out at the Friday review, before building next week, and write a reason beside each miss: broke in, part not there, equipment not released, estimate too small, someone out. How to build a weekly maintenance schedule walks through the review and the fix for each.

Do not punish a low figure

A crew blamed for misses learns to schedule less, and the number rises while the work done stays the same. Watch the trend over a few months, not one week.

Why Maintensor cannot rebuild last Friday’s schedule

Maintensor has no schedule compliance figure. On the planner, moving a job changes its start date, and a work order’s History does not record date changes, so the app keeps no copy of Friday’s schedule.

Write the list down when you publish the week, and count against it the next Friday. Reporting’s On time measures something else: work orders done by their due date, not by the day they were planned for.

Questions

What people also ask.

More in the glossary, or see the whole product on the features page.

Should emergency work count in schedule compliance?

No. Work that broke into the week was not on the schedule, so it is left out of both the top and the bottom of the calculation. Track it separately, as hours spent on breakdowns each week. If those hours keep pushing scheduled work out, hold back more room for them when you build the next week.

What is a good schedule compliance?

Compare your crew with itself rather than with a published target. A figure that stays low means the week is loaded with more than the crew can do, or the schedule is not protected from interruptions. A figure that is always 100% can mean the schedule is padded. Read the reasons for the misses before reading the number.

Plan next week against the hours people have.