Planned maintenance percentage formula
PMP = planned maintenance hours ÷ total maintenance hours × 100
- Planned hours
- preventive tasks, inspections, repairs booked for later, overhauls
- Unplanned hours
- breakdowns, emergency calls and any job that broke into the week's plan
- Total maintenance hours
- planned and unplanned together
How to calculate planned maintenance percentage
- Pick a month or a quarter. One bad week swings a shorter period.
- Add up the planned hours. Work scoped and scheduled before it started.
- Add up all maintenance hours. Planned and unplanned together.
Planned maintenance percentage example: six assets over one quarter
A made-up plant, in technicians' labor hours:
43 work orders
13 work orders
43 ÷ 56 work orders
59 ÷ 99 hours
What your planned maintenance percentage tells you
- Split it by asset. A machine that takes more breakdown hours than planned hours is a candidate for a better preventive task.
- Read it beside PM compliance. A site can score well on one and badly on the other.
A rise is good only if breakdowns fell
The figure can rise because breakdown hours fell, or because preventive work was padded with extra tasks. Check which before you report it as progress.