What is a maintenance backlog?

A maintenance backlog is the approved work your crew has not done yet, counted in hours. Divided by the hours the crew can give it each week, it becomes crew-weeks: how long it would take to clear.

By MaintensorUpdated

What counts in a backlog, and why it is measured in hours

backlog in crew-weeks = backlog hours ÷ crew hours a week for backlog work

Backlog hours
the estimated hours of every approved job not yet finished
Crew hours for backlog work
paid hours less time off, training, daily rounds and the usual breakdowns
Maintenance backlog calculatorType your own numbers and see the answer, with the sum shown.

The backlog holds repairs, preventive jobs that have come due and small projects. It leaves out requests nobody has approved and preventive jobs not due yet. Count hours, not jobs: a 15-minute bulb change and a two-day gearbox rebuild are each one job.

Backlog example: 280 hours of work for a crew of three

A made-up plant with three technicians and 52 open work orders.

120 hPaid hours a week
3 people × 40 h
90 hLeft for backlog work
120 − 30 for breakdowns and rounds
280 hBacklog
268 estimated + 12 placeholder
3.1Crew-weeks
280 ÷ 90

One number says little; six Fridays say more. The total grew by about 11 hours a week while the ready part stayed flat, so the new hours were jobs that cannot start: waiting on parts, a shutdown or a contractor. More people would not help. Chasing the parts would.

The numbers, line by lineThe 280 hours, and the backlog on six Fridays.

Forty-six of the 52 work orders have estimates, totaling 268 hours. Six have none, so each is counted at a placeholder of 2 hours: 12 hours.

Friday Backlog hours Crew-weeks Ready, in crew-weeks
Week 1 225 2.5 1.4
Week 2 234 2.6 1.5
Week 3 243 2.7 1.4
Week 4 252 2.8 1.3
Week 5 266 3.0 1.4
Week 6 280 3.1 1.3

Every number is made up.

Ready backlog and total backlog

Ready backlog is work that could start Monday: planned, parts on the shelf, the stop agreed. Total backlog adds everything still waiting.

  • Ready backlog too small: next week cannot be filled with planned work.
  • Waiting backlog growing: the problem is parts, contractors or access, not labor.
  • Both growing: the crew is short of hours. Cut work not worth doing, contract some out, or ask for another person.

Write it down every Friday

Each Friday, write the backlog total and its ready part on one line. Quoted targets come from large plants with full-time planners; your own trend is the better guide.

The weekly maintenance schedule guide builds that into a Friday review, and maintenance planning and scheduling covers turning the ready part into next week’s work.

Backlog vs overdue work, deferred maintenance and schedule compliance

  • Not overdue work. Overdue is the part past its due date: how late you are, not how much is waiting.
  • Not deferred maintenance. That is work put off on purpose, usually for lack of budget, and it often never reaches the backlog.
  • Not schedule compliance. A crew can hit its schedule every week and still watch the backlog grow, if it schedules less than arrives.

Reading the backlog from open work orders in Maintensor

The open work orders are the backlog, except a repeating job’s next work order, which is created as soon as the last one is completed: leave those out until they come due.

The Active list groups open work as Overdue, Today, Tomorrow, This week, Later and No due date, each work order can carry an estimate, and the planner’s Unscheduled panel holds open work with no date or no one assigned.

There is no backlog figure in hours or crew-weeks, and nothing to export, so the estimates are added up by hand. Reporting, for Admins on Pro and Max, counts open and overdue work orders against the period before.

Questions

What people also ask.

More in the glossary, or see the whole product on the features page.

What is a good maintenance backlog?

There is no number that suits every site. Ready backlog should be enough to fill next week's schedule. Beyond that, watch the trend: a total backlog that grows for a month or more means work is arriving faster than the crew finishes it, and something has to change.

What is the difference between backlog and overdue work?

Overdue work is only the part of the backlog past its due date. A crew can have a large backlog with nothing overdue, when the due dates are far off, or a small backlog that is mostly overdue.

Plan next week against the hours people have.