What counts in a backlog, and why it is measured in hours
backlog in crew-weeks = backlog hours ÷ crew hours a week for backlog work
- Backlog hours
- the estimated hours of every approved job not yet finished
- Crew hours for backlog work
- paid hours less time off, training, daily rounds and the usual breakdowns
The backlog holds repairs, preventive jobs that have come due and small projects. It leaves out requests nobody has approved and preventive jobs not due yet. Count hours, not jobs: a 15-minute bulb change and a two-day gearbox rebuild are each one job.
Backlog example: 280 hours of work for a crew of three
A made-up plant with three technicians and 52 open work orders.
3 people × 40 h
120 − 30 for breakdowns and rounds
268 estimated + 12 placeholder
280 ÷ 90
One number says little; six Fridays say more. The total grew by about 11 hours a week while the ready part stayed flat, so the new hours were jobs that cannot start: waiting on parts, a shutdown or a contractor. More people would not help. Chasing the parts would.
The numbers, line by lineThe 280 hours, and the backlog on six Fridays.
Forty-six of the 52 work orders have estimates, totaling 268 hours. Six have none, so each is counted at a placeholder of 2 hours: 12 hours.
| Friday | Backlog hours | Crew-weeks | Ready, in crew-weeks |
|---|---|---|---|
| Week 1 | 225 | 2.5 | 1.4 |
| Week 2 | 234 | 2.6 | 1.5 |
| Week 3 | 243 | 2.7 | 1.4 |
| Week 4 | 252 | 2.8 | 1.3 |
| Week 5 | 266 | 3.0 | 1.4 |
| Week 6 | 280 | 3.1 | 1.3 |
Every number is made up.
Ready backlog and total backlog
Ready backlog is work that could start Monday: planned, parts on the shelf, the stop agreed. Total backlog adds everything still waiting.
- Ready backlog too small: next week cannot be filled with planned work.
- Waiting backlog growing: the problem is parts, contractors or access, not labor.
- Both growing: the crew is short of hours. Cut work not worth doing, contract some out, or ask for another person.
Write it down every Friday
Each Friday, write the backlog total and its ready part on one line. Quoted targets come from large plants with full-time planners; your own trend is the better guide.
The weekly maintenance schedule guide builds that into a Friday review, and maintenance planning and scheduling covers turning the ready part into next week’s work.
Backlog vs overdue work, deferred maintenance and schedule compliance
- Not overdue work. Overdue is the part past its due date: how late you are, not how much is waiting.
- Not deferred maintenance. That is work put off on purpose, usually for lack of budget, and it often never reaches the backlog.
- Not schedule compliance. A crew can hit its schedule every week and still watch the backlog grow, if it schedules less than arrives.
Reading the backlog from open work orders in Maintensor
The open work orders are the backlog, except a repeating job’s next work order, which is created as soon as the last one is completed: leave those out until they come due.
The Active list groups open work as Overdue, Today, Tomorrow, This week, Later and No due date, each work order can carry an estimate, and the planner’s Unscheduled panel holds open work with no date or no one assigned.
There is no backlog figure in hours or crew-weeks, and nothing to export, so the estimates are added up by hand. Reporting, for Admins on Pro and Max, counts open and overdue work orders against the period before.