How to read the plan for workload
The total at the foot of each month is that month's load. A month with far more than its neighbors is where work starts to slip.
The example, read through
"Show an example" fills the list with six assets of a made-up plant. Most months hold 6 or 7 checks, and no month is far above the rest, which is the point of spreading the dates.
The six assetsWhat each one shows about how the plan works.
- Two air compressors, each serviced monthly, one on the 5th and one on the 19th, so they never take the same day.
- A conveyor, walked every week from the 2nd. That puts 4 or 5 checks in every month, depending on how the weeks fall.
- A forklift, serviced every 3 months from the second month, so it shows in the plan four times.
- A boiler, serviced once a year in the fourth month.
- The floor line markings in the warehouse, repainted every 3 years and last done a year before the plan starts. They are not due in these 12 months, so they are listed under the plan with their next date instead of in it.
Read the totals at the foot: the conveyor's 4 or 5 and the two compressors make 6 or 7. Every third month the forklift adds one, and the boiler adds one in its month.
What it does not do
About the filesThe calendar file, the CSV, and a job due on the 31st.
The calendar file follows the iCalendar standard, RFC 5545: one repeating all-day event for each row. The CSV has one line for each date a job falls due in the 12 months, with the date written out, such as Nov 3, 2026, and a cell that starts with =, +, - or @ is written so a spreadsheet does not run it as a formula.
A job due on the 29th, 30th or 31st falls on the last day of a month that is shorter. The plan and the CSV count it that way, and the calendar file asks for the same dates with a standard repeat rule. Check the first few dates after you import it.