Key points
- Rank the assets on safety, operations, repair and history, and start with tier A, not the whole site.
- Write each task from the manual, last year's breakdowns and how the machine usually fails.
- A small crew builds it in phases over about a quarter, each starting once the last runs on time.
- Each quarter, read PM compliance, reactive share, repeat failures and findings per PM together.
- Prune PMs that find nothing, but keep tests of hidden functions such as a relief valve.
Program, plan, schedule and checklist
A preventive maintenance program is the plan plus how you measure it and change it. The words get used loosely, so on this page the plan is which assets get PMs, which tasks, how often and who does them (steps 1 to 4). The dates are the schedule, and the steps at the machine are the checklist.

Whether preventive work is worth doing at all is in what preventive maintenance is and when to run to failure.
1. Rank the assets with a short criticality pass
Score each asset from 1 to 3 on four questions. It takes an afternoon with the crew and someone from production or operations in the room.
| Question | 1 | 2 | 3 |
|---|---|---|---|
| Safety: what can its failure do to people or the environment? | Nothing | A minor injury, a small spill | A serious injury, a fire, a release |
| Operations: what stops when it fails? | Nothing | Work slows, or there is a workaround | A line, a building system or shipping stops |
| Repair: how long and how costly to get it back? | Under a day, parts on the shelf | A few days, or a costly part | Weeks, or a part with a long lead time |
| History: how often did it fail in the last 12 months? | Never | Once | Twice or more |
Add the four, and the total puts each asset in a tier:
Asset criticality analysis has a simpler score on two scales.
ExampleThe pass at a made-up plastics plant
Here is the pass for part of the plant. Every score is invented.
| Asset | Safety | Operations | Repair | History | Total | Tier |
|---|---|---|---|---|---|---|
| Injection press 4 | 2 | 3 | 2 | 3 | 10 | A |
| Air compressor (the only one) | 1 | 3 | 3 | 2 | 9 | A |
| Process chiller | 1 | 3 | 3 | 1 | 8 | A |
| Overhead crane, mold shop | 3 | 2 | 2 | 1 | 8 | A |
| Granulator | 2 | 1 | 2 | 2 | 7 | B |
| Dock door 2 | 1 | 1 | 1 | 1 | 4 | C |
Anything a regulation requires to be inspected goes on the program, whatever it scores.
Cranes and forklifts: what the rules ask
In the US, overhead cranes in regular service need frequent inspections at daily to monthly intervals and periodic ones at 1 to 12 months under 29 CFR 1910.179(j). Forklifts need an examination before use, at least daily, under 29 CFR 1910.178(q)(7).
Provinces in Canada have their own rules. Check the rule that applies to you, and the maker’s manual.
2. Choose the tasks: the manual, the history and the failures
Write the tasks for each tier A asset from three sources, in this order.
- The manual. Follow the maker’s tasks and intervals while the asset is under warranty, since the warranty may depend on it. After that, keep the tasks that fit how you run the machine, with a note on the rest saying why.
- The history. For each breakdown on the asset in the last 12 months (work orders, whiteboard photos, invoices), ask what check, done when, would have caught it.
- How it fails. Ask the technician who knows the machine. Match each failure with a task that either prevents it (lubricate or replace before the wear-out) or finds it early (look, listen, measure).
For press 4 at the plastics plant, last year’s breakdowns gave three of its tasks:
| Last year’s breakdown | Task that would have caught it |
|---|---|
| Hydraulic hose burst at the clamp unit | Look along the hoses for chafing, bulges and weeping fittings |
| Oil overheated, press tripped in July | Read the oil temperature at full cycle; clean the cooler strainer |
| Heater band failed on the barrel | Read each heater zone’s current and compare the zones |
Every task needs an answer: a pass or a fail, a reading, or a yes or no. “Check hydraulics” cannot be failed. “Oil temperature at full cycle above the manual’s limit is a fail” can.
3. Set how often each task is done
How often depends on the kind of task:
The usual convention is to inspect at no more than half the warning time a failure gives. The P-F curve shows how to set this, and why.
Then group the tasks on one asset that share an interval into one PM, so the guard comes off once. Press 4’s tasks became three PMs:
4. Name who does each task
Give each task to the person the work calls for:
- The operator: daily look, listen and clean; fluid levels; safety device checks before use. They notice a change first.
- A technician: weekly and monthly inspections with readings, lubrication routes, adjustments, part swaps. The work needs tools, training and often a lockout.
- A specialist or contractor: vibration routes, infrared scans, oil sample analysis, boiler and fire system inspections, licensed trades. The work needs instruments, a certification or a license.
Then give each PM one named person or team and an estimate in hours, so the rollout can be counted against the crew’s real week.
5. Roll it out over a quarter: a worked example
The made-up plastics plant has 46 assets and a crew of three: Laura Bennett runs maintenance, with Mike Sullivan and Carlos Rivera. Breakdowns take most of their week. The criticality pass put 9 assets in tier A, 14 in tier B and 23 in tier C. Every number below is made up.
The quarter, step by stepFrom no assets with PMs to 23, with 38 PMs running and 60 hours a month
| Weeks | What gets done | Assets with PMs | PMs running | PM hours a month | Move on when |
|---|---|---|---|---|---|
| 1 to 2 | Asset list, criticality pass, last year’s breakdowns gathered | 0 | 0 | 0 | Production agrees with the ranking |
| 3 to 4 | Tasks written for the 9 tier A assets; their PMs start | 9 | 16 | 30 | Every PM has a name, an estimate and a checklist |
| 5 to 8 | First runs: fix vague steps and wrong estimates; add 6 tier B assets | 15 | 26 | 44 | The first PMs are being done on time |
| 9 to 12 | Add the other 8 tier B assets; operators start daily checks on the 4 presses | 23 | 38 | 60 | On time holds as the hours grow |
| 13 | The quarter’s review (step 6) | 23 | 38 | 60 | Decide what to add, stretch or cut |
Three things make it work:
6. Measure whether it works
At the end of the quarter, and every quarter after, look at four numbers. The results below are the made-up plant’s third month.
- PM compliance:
PMs done by their due date ÷ PMs due. Result: 46 of 52, 88%. It tells you whether the crew can carry the program. - Reactive share:
reactive work orders ÷ all work orders. Result: 41 of 103, 40%. It tells you whether breakdowns are giving way to planned work. - Repeat failures: the same failure on the same asset within 90 days. Result: 3, down from 7. It tells you whether the tasks address the real causes.
- Findings per PM:
PMs that found a problem ÷ PMs completed. Result: 9 of 49, 18%. It tells you whether each PM earns its time.
PM compliance explains how to settle what “on time” means. Keep every definition the same from quarter to quarter, and read the numbers together:
- When compliance drops, the program is bigger than the crew. Cut it, spread it or staff it before adding assets.
- When the reactive share falls, breakdowns may have fallen, or you may simply have added PMs. Watch the breakdown count on tier A assets too.
- When the same failures keep coming back, the task does not fit the failure, and changing the interval will not fix it.
7. Prune the tasks that find nothing
A PM that never finds anything is either doing its job or wasting an hour. Once a task has run enough times to judge (four runs for a monthly, a year for a quarterly), sort it:
| What the record shows | What to do |
|---|---|
| Never finds anything, and it tests something that only matters when needed (a standby pump, a relief valve, an emergency stop) | Keep it. A test of a hidden function is expected to pass |
| Never finds anything, and the failure would give plenty of warning | Stretch it, say from monthly to every two months, and watch |
| Never finds anything because the step is vague | Rewrite it with a reading or a clear fail |
| Finds the same problem nearly every time | Fix the cause, or shorten the interval |
| The asset failed between PMs in a way the PM should have caught | Shorten the interval or change the method |
| Repeats another PM or an operator check | Merge them |
Electrical maintenance has this in writing
Chapter 9 of the 2023 edition of NFPA 70B, the standard for electrical equipment maintenance (a 2026 edition has since come out, so check the one you work to), keeps a starting interval for two maintenance cycles before it is changed, unless there are unexpected failures (section 9.1.2).
It allows a longer interval than its table once more than two inspections find no problems, and has the cause of an unexpected failure decide whether the interval should be shortened.
Cut a task only with a note saying why, so nobody adds it back out of habit.
Each PM as a repeating work order in Maintensor, and how to measure it
In Maintensor, each PM is a work order with a repeat on it: daily, weekly, monthly or yearly, each every 1, 2 or more. When one is completed, the next is created on its schedule, with the same people, estimate, parts and procedures, and its checklist blank. The preventive maintenance page shows the whole feature.
To measure the program: on Pro and Max, Reporting shows admins the preventive ratio, work done on time against late with recurring and non-recurring apart, and the count of Pass, Flag and Fail answers to inspection checks. A category on a group of work orders, such as a lubrication route, filters Reporting to that group.
For findings, filter the work order list by the origin “From a failed inspection step”. That finds follow-ups made from a finished work order’s Checklist tab. One created at the failed step during the run counts as “Created manually”, so that filter misses it.
What it does not do
There is no criticality field on an asset, so keep the ranking from step 1 where the team can see it. Nothing comes due from meter readings or run hours. Only Admins and Full users can answer checklists, so an operator who does a daily check in the app needs a Full user account.
The Free plan holds 5 recurring work orders and 3 procedures, and Pro has no limit on either, so the made-up plant’s 38 PMs would need a paid plan.