Key points
- ROI is yearly cash savings minus yearly cost, divided by yearly cost.
- Saved hours are cash only when they replace overtime, a contractor or a hire.
- Savings come from less looking, less breakdown overtime, fewer stockouts and fewer repeat failures.
- In the example, $8,060 a year is the most the software can cost and still pay.
- Take a baseline before the first record goes in, then measure again at six and twelve months.
The formula, and three rules for filling it in
ROI = (yearly cash savings − yearly cost) ÷ yearly cost
payback in months = one-time costs ÷ monthly cash savings after running costs
What goes into it is where these sums usually go wrong, so three rules first.
Where the savings come from
The benefits of a CMMS that can be put in a sum come from four places, and each needs a number measured before you start (where to find each one is further down).
Some benefits are real and do not fit in a sum: requests that no longer get lost, a record of every inspection when an auditor or insurer asks, and a system that stays when the person who kept the spreadsheet leaves. Mention them beside the number, not inside it.
CMMS ROI example: a packaging plant with six technicians
A made-up food packaging plant runs one main line. Laura Bennett manages six technicians. Every number below is invented and round, to show the arithmetic.
| Input | Value |
|---|---|
| Technicians | 6, plus Laura: 7 users |
| Working days a year | 240 |
| A technician’s regular hour, with taxes and benefits | $50 |
| An overtime hour (time and a half on the wage, plus payroll taxes) | $60 |
| Laura’s hour | $60 |
| Margin lost per hour the main line stands still (from finance) | $400 |
The $60 overtime hour rests on time and a half. In the United States, the Fair Labor Standards Act requires overtime pay at no less than time and a half for non-exempt employees’ hours over 40 in a workweek; in Canada each province sets its own rules (Ontario’s overtime, also at time and a half, starts after 44 hours a week), and federally regulated workplaces follow the Canada Labour Code.
The savings
The four savings, with the arithmetic$12,680 in cash and 243 hours a year
| Saving | Before (measured) | After (expected) | Arithmetic | Cash a year | Hours a year |
|---|---|---|---|---|---|
| Looking for history and parts | 20 min per technician a day | 10 min | 10 min × 6 × 240 days = 14,400 min | $0 | 240 |
| Breakdown overtime | 300 hours a year | 225 hours | 75 h × $60 | $4,500 | 0 |
| Jobs stopped for a part | 8 a year | 4 a year | 4 × ($150 rush freight + 3 h × $400) = 4 × $1,350 | $5,400 | 0 |
| V-belt replaced on one conveyor | 10 times a year | 3 times | 7 × ($40 belt + 1 h × $400) = $3,080, less a $300 pulley to fix the cause | $2,780 | 3 (7 saved, 4 spent on the fix) |
| Total | $12,680 | 243 |
Keep the guesses stingy
Each expected figure is a guess, and it should be a stingy one. Avoiding a quarter of breakdown overtime assumes preventive work was being missed and now is not. Halving stockouts assumes the parts that ran out get a reorder level.
The costs
The costs, with the arithmetic$4,620 a year, plus the software
| Cost | Arithmetic | A year |
|---|---|---|
| Setup: locations, assets, recurring jobs | 24 h of Laura’s time × $60 | $1,440 |
| Training | 6 technicians × 1 h × $50 | $300 |
| Running it: reading closed jobs, approving requests | 1 h a week more than the whiteboard took × 48 weeks × $60 | $2,880 |
| Phones | The crew already carries them | $0 |
| Software | A year of your quote, for all 7 users | S |
| Total | $4,620 + S |
Hours spent are counted as money on the cost side, and hours saved are not counted as money at all. That is deliberately harsh. If the return holds up under it, it holds up.
The result
12,680 − 4,620
- The ceiling. The software pays for itself in the first year if a year of it, for all 7 users, costs less than $8,060. To compare a quote, divide the ceiling by 7 users and 12 months, and hold the quote’s price per user per month against the result.
- With the quote in:
ROI = (8,060 − S) ÷ (4,620 + S). - Payback. Leaving the software out, the $1,740 of setup and training is paid back in a little over two months: $1,740 ÷ ($9,800 ÷ 12 a month), where $9,800 is the $12,680 of savings less the $2,880 of costs that recur each year. In year two there is no setup or training to pay again.
- The hours. The 243 hours are on top. If Laura uses them to bring a quarterly fan service in-house instead of calling a contractor, the contractor’s bill moves into the cash column.
What moves the answer
Two inputs carry most of the weight: the margin lost per hour of downtime, and the share of breakdowns you expect to avoid. Take the first from production or finance, not from a guess; the guide to the cost of downtime shows how to work it out.
ExampleThe same plant, with downtime at $0
Set the line’s downtime to $0, as if there were a spare line or orders could wait.
4 × $150
7 × $40 = $280, less the $300 pulley
4,500 + 600 − 20
5,080 − 4,620
The return now rests on overtime alone, and $460 a year across 7 users is very little. Hold it against the price per user per month the same way: on these numbers, a paid plan of Maintensor would not pay for itself in the first year.
Measure before you start
A return you cannot check is a sales figure. Take the baseline before the first record goes in, and measure the same way at six and twelve months.
- Time spent looking: a tally each technician keeps of what they went looking for, and for how long, over one normal week.
- Breakdown overtime: payroll, overtime hours on call-ins and breakdowns, over the last 12 months.
- Stockouts: rush freight invoices, and the crew’s list of jobs that waited for a part, over the last 12 months.
- Repeat failures: the same part on the same machine three or more times, from the log, the parts invoices and whiteboard photos, over the last 12 months.
- Cost of downtime: production or finance, the margin lost per hour on each line. Ask once a year.
The guide to maintenance KPIs covers the monthly numbers worth keeping once the records exist.
When the return is small
A CMMS is not worth buying for every crew. The sum comes out thin when:
- One or two people, a short asset list, and a manager who remembers everything. A well-kept maintenance spreadsheet does the job for free.
- Most of the maintenance is contracted out, and the contractor keeps the records.
- No paid overtime and no costly downtime. A salaried crew and equipment with a spare behind it leave the cash lines near zero.
- The preventive work was already done on time and the storeroom already counted. The savings were taken before the software arrived.
- The crew does not use it. The costs stay, the savings never start, and the return is a loss. This is the case that choosing a CMMS by its technicians’ first hour is meant to avoid.
What Maintensor records toward these numbers
- Time, on every plan. Time runs from Start work until a job is put on hold or completed, and can be added or fixed by hand.
- Parts. Each work order lists its parts with their cost, and a line shows “short” when its storeroom holds less than the job needs.
- Repeat parts. An asset’s record warns when one part has been used on it three or more times this year, which is how the V-belt in the example would have surfaced.
- Downtime. On Pro and Max, Admins see Reporting: downtime and unplanned downtime from asset status, MTBF, and the most problematic assets with their repair cost.

What it does not do
It puts no price on an hour of downtime and does not separate overtime from regular hours. Downtime runs by the clock, nights and weekends included, because the app does not know your shifts, and the most problematic list shows the top five. Below Max, an asset’s costs, and so its repair cost, are parts only; Max adds hourly rates, labor cost, other costs such as contractors, and labor utilization. There is no export, so the figures are copied out by hand.
Prices per user per month are on the pricing page, and every new team starts with 30 days of Pro, long enough to take the baseline and see the first month.