What is unplanned downtime?

Unplanned downtime is the time a machine is stopped when nobody scheduled it to stop: a breakdown or a trip, and the wait for a technician or a part that follows. Planned downtime is the stop you chose.

By MaintensorUpdated

When unplanned downtime starts and stops, and its share of the hours

It runs from the moment an asset stops, or is taken out of service as unsafe, to the moment it is back in service. Finding the fault, the waits, the repair and the test run all count.

unplanned downtime % = unplanned downtime hours ÷ scheduled hours × 100

Unplanned downtime hours
stop to back in service, for every stop nobody chose
Scheduled hours
the hours the asset was meant to run in the period

Planned downtime is agreed in advance, such as a preventive maintenance window. Between the two:

  • A service that runs over its window: the window is planned, the overrun unplanned.
  • A fault found on an inspection: unplanned if the machine must stop at once; planned if it runs safely to a repair booked for Saturday.
  • A changeover, or no operator or material: production’s downtime, not the equipment’s.

How to count it

Record when each stop began and when the asset was back in service. Clock time counts every hour it was out; scheduled time only the hours it was meant to run.

A two-shift machine that fails at 10 p.m. on Friday, an hour before its second shift ends, and is fixed at 8 a.m. on Monday, an hour into the first, was out 58 hours but cost 2 scheduled hours. Use scheduled time to put a price on it, as the downtime cost guide does.

Unplanned downtime example: a packaging line’s month

A made-up packaging line: two 8-hour shifts on 21 working days, so 336 scheduled hours.

336 hScheduled
16 h × 21 days
8 hUnplanned, in 3 stops
planned: 4 h, 1.2%
2.4%Unplanned downtime
8 ÷ 336 × 100

The sealer heater was 6 of the 8 hours, a third of it waiting for the part: a spare heater on the shelf is the cheapest fix. The same records give the line’s MTBF, 108 hours, and a plain mean time to repair, 2.7 hours a stop.

The month's numbers, line by lineFour stops, 12 hours, in 336 scheduled hours.
Stop Type Scheduled hours
Monthly service, in its window Planned 4.0
Case sealer heater failed; 2 hours waiting for the part Unplanned 6.0
Infeed conveyor motor tripped Unplanned 1.5
Labeler sensor failed Unplanned 0.5
Total 12.0

Unplanned: 8 ÷ 336 = 2.4%. Planned: 4 ÷ 336 = 1.2%. A stop: 8 ÷ 3 = 2.7 hours. Between failures: (336 − 12) ÷ 3 = 108 running hours. Every number is made up.

How it relates to other numbers

Unplanned downtime is one of the losses inside the availability part of OEE, and its causes are where a root cause analysis starts. A rising share of planned stops can be good news: preventive work catching problems before they become breakdowns.

Down and In maintenance: how Maintensor splits the downtime

In Maintensor, setting an asset’s status to Down starts a stretch of unplanned downtime, In maintenance a stretch of planned downtime, and Operational ends it. The change can take a Reason, which the asset’s History keeps.

Moving between Down and In maintenance keeps one stretch with the type of the latest status, so leave a broken machine at Down until it runs again.

Planned vs. unplanned downtime: 9 days 7 hours in all, 3 days 18 hours unplanned and 5 days 13 hours planned.
Planned vs. unplanned downtime: 9 days 7 hours in all, 3 days 18 hours unplanned and 5 days 13 hours planned.

Reporting (Pro and Max, for Admins) adds the stretches up for a period, with the most problematic assets by unplanned downtime and their MTBF. It counts clock time, nights and weekends included, not your shifts, and puts no price on the hours.

Questions

What people also ask.

More in the glossary, or see the whole product on the features page.

Does waiting for parts count as unplanned downtime?

Yes. The clock starts when the asset stops and runs until it is back in service, so waiting for a technician, a part or a contractor all counts. Write the wait down separately in the work order's notes: if most of a stop was spent waiting for a part, the fix is a spare on the shelf, not a faster repair.

What is the difference between downtime and unplanned downtime?

Downtime is all the time an asset is not available, planned or not. Unplanned downtime is the part nobody scheduled. A machine that was down 12 hours in a month, 4 of them for its monthly service, had 8 hours of unplanned downtime. Tracking the two apart shows whether stops are being chosen or forced.

Start with the machine that gives you the most work.

Start the trial, add that one asset with its location and nameplate, and write its first work order. Its history builds from there, job by job.

30-day free trial. No credit card.