What is asset lifecycle management?

Asset lifecycle management is looking after a piece of equipment from the decision to buy it to its disposal, at the lowest total cost. Maintenance is the longest stage, but choices made before buying fix much of that cost.

By MaintensorUpdated

Asset lifecycle management under ISO 55000, one asset at a time

ISO 55000 defines asset management as the coordinated activity of an organization to realize value from its assets. The Institute of Asset Management describes an asset’s life cycle as running from recognizing the need for it to its disposal. Lifecycle management applies that to each machine, judged on its total cost over its life:

life-cycle cost = buying + installing + running + disposal − resale

Buying and installing
the price, then installing and commissioning it
Running
energy, maintenance, repairs and downtime, every year it runs
Disposal and resale
the cost of taking it out, minus any resale or scrap value

The stages, and what to keep from each

Stage Maintenance’s part Records worth keeping
Plan Say what fails on the current machine; ask for room to service it The reason for buying, the specification
Buy Ask for manuals, a spare parts list and training Purchase order, warranty terms, spare parts list
Install and commission Check it goes in right; set up its preventive work Nameplate photo, drawings, start-up readings
Operate and maintain Preventive work, inspections, repairs Work orders, parts used, downtime, cost
Modify or overhaul Plan the rebuild, upgrade or move What changed, the new parts list
Retire and dispose Isolate and drain it safely; keep useful spares The date, the reason; keep its history

The early stages weigh the most. NASA’s reliability-centered maintenance guide for facilities, citing an older study, says planning and conceptual design fix about two-thirds of a facility’s life-cycle cost.

A small team needs no written lifecycle plan, only habits: the asset register guide covers adding a machine the day it arrives and retiring it rather than deleting it, and the maintenance strategy guide what its work in service should be.

Life-cycle cost example: a compressor over 10 years

A made-up air compressor kept for 10 years. Every figure is invented.

$29,000Buying and installing
$25,000 + $4,000
$80,000Energy
$8,000 a year
$21,000Maintenance
routine, plus a rebuild
$129,000Life-cycle cost
less $1,000 scrap
The numbers, line by lineThe purchase is about a fifth of the total.
Cost Amount
Buying $25,000
Installing $4,000
Energy, $8,000 a year for 10 years $80,000
Routine maintenance, $1,500 a year for 10 years $15,000
A rebuild in year 8 $6,000
Scrap value at the end minus $1,000
Life-cycle cost $129,000

A model that costs $2,000 more but uses 10% less energy saves $800 a year, $8,000 over the ten years, and comes out $6,000 ahead. That comparison is made at the planning stage or not at all.

Lifecycle management vs asset management, useful life and a CMMS

  • Asset management is the organization-wide system across all assets. Lifecycle management is one asset, stage by stage.
  • Useful life is how long the operate-and-maintain stage is expected to last; finance has its own version for depreciation.
  • A CMMS is the system for the longest stage: the work orders, parts and history between installation and retirement.

The operate-and-maintain stage in Maintensor, through retirement

Maintensor covers the operate-and-maintain stage: each asset keeps its work orders with their parts cost, and its status changes. At the end, a Retired status keeps the asset on the list; an Admin can also archive it, which moves it to the Archived view, read only, from where it can be restored. Either way its history stays.

It has no fields for purchase date, purchase cost, warranty or depreciation, so planning, buying and disposal records stay with purchasing and accounting. A warranty end date can go in the asset’s Description.

Questions

What people also ask.

More in the glossary, or see the whole product on the features page.

What are the stages of the asset lifecycle?

The usual stages are planning (deciding what is needed), buying, installing and commissioning, operating and maintaining, modifying or overhauling, and retiring and disposing. Some models merge or split them, but the order is always the same, and maintenance has a part in every one.

What is the difference between asset management and asset lifecycle management?

Asset management, as the ISO 55000 standard describes it, is how a whole organization gets value from all its assets, balancing cost, risk and performance across them. Asset lifecycle management applies the same idea to one asset, stage by stage. A small maintenance team mostly does the second.

Start with the machine that gives you the most work.

Start the trial, add that one asset with its location and nameplate, and write its first work order. Its history builds from there, job by job.