Key points
- It takes a way to measure, a baseline per machine, limits, someone to read it and a way to act.
- The inspection interval must be no longer than the P-F interval; many teams check at about half.
- Vibration, oil, infrared and ultrasound find different faults, and none of them replaces preventive work.
- For a small team it pays on a few critical machines, once the preventive basics are done well.
- In the made-up compressor example, monitoring saves about $3,700 a year; change one assumption and it can stop paying.
What predictive maintenance is
Predictive maintenance replaces “service it every three months” with “measure it, and service it when the measurements say so.” It is one of the types of maintenance.
The official definition
NASA’s guide to reliability-centered maintenance for facilities calls it predictive testing and inspection. It “replaces arbitrarily timed maintenance tasks with maintenance that is scheduled only when warranted by equipment condition” (NASA RCM Guide, section 5.3).
The work itself is ordinary: a bearing replaced, a coupling realigned, a connection tightened. What changes is when it happens: when a measurement shows something starting to go wrong, early enough to order the part and pick the day. The measurement is one of four:
The distinction people get wrong is with condition-based maintenance:
Many sources use the two words for the same thing, so predictive maintenance is also called condition-based maintenance. NASA’s guide treats predictive maintenance and condition monitoring as other names for its predictive testing and inspection.
It is also not the same as sensors or artificial intelligence: a program can be a person with a handheld instrument, on a route.
Predictive vs preventive vs reactive maintenance
| Reactive | Preventive | Predictive | |
|---|---|---|---|
| When the work is done | After the machine fails | On a schedule (a date, or hours, miles or cycles of use), before a failure, whether the machine needs it or not | When a reading of vibration, oil, heat or sound crosses its limit, before the machine stops |
| What it needs | People on call, and parts on the shelf or a fast supplier | A list of tasks and intervals, from the maker’s manual and your own history | Instruments or a contractor, a baseline for each machine, limits, and someone trained to read the results |
A site can run all three at once: preventive maintenance for wear parts and simple tasks, predictive work on a few critical machines, and cheap items with a spare on the shelf run to failure on purpose.
Is predictive maintenance worth it for a small team?
It pays on a few critical machines, once the preventive basics are done well.
- The preventive schedule runs late or gets skipped: not yet. Get the PMs done on time. Monitoring a machine nobody greases finds the same faults, later.
- The machine has a running spare, or a stop costs little: rarely. Simple checks on rounds, or let it run to failure and keep the part on the shelf.
- The failure gives no warning, as with much electronics: no. A spare, a backup, or a design change.
- Nobody will read the reports or act on them: no. Contract the route, and name the person who turns findings into work orders.
- One critical machine, no backup, an expensive stop, and failures that build slowly: probably. Price it with the example below.
Predictive maintenance cost example: one compressor, no backup
On one compressor with no backup, monitoring saves about $3,700 a year in this made-up case, and one changed assumption can erase it.
ExampleOne compressor, no backup
Every number here is made up to show the arithmetic. A plant runs on one 100 hp (75 kW) rotary screw air compressor, with no backup. When it stops, most of the plant stops. Its history suggests a major bearing failure in the air end about once every 4 years.
12 h × $2,000 lost + $16,000 repair
on a weekend, no lost output
The unplanned repair has parts flown in and overtime. To work out the hourly figure for your own site, see the cost of downtime.
The monitoring is the machine’s share of a contractor’s quarterly vibration route ($1,200), four oil samples ($200), its starter and panel on the yearly infrared scan ($300), and 12 hours of in-house time at $50 an hour ($600).
Assume the program catches 3 of every 4 developing failures in time to plan the repair. The fourth fails anyway.
| Without monitoring | With monitoring | |
|---|---|---|
| Failures starting each year | 0.25 | 0.25 |
| Expected failure cost a year | 0.25 × $40,000 = $10,000 | 0.25 × (0.75 × $8,000 + 0.25 × $40,000) = $4,000 |
| Monitoring cost a year | $0 | $2,300 |
| Total a year | $10,000 | $6,300 |
Monitoring saves about $3,700 a year on this machine.
Change one assumption and the answer moves. At one failure in 10 years it barely pays. With a backup compressor, or a program that catches only 1 failure in 4, it does not.
Each changed assumption, worked outThe yearly cost without monitoring and with it, for each case
| What changes | Without | With | Does it pay? |
|---|---|---|---|
| The failure comes once in 10 years, not 4 | 0.1 × $40,000 = $4,000 | 0.1 × (0.75 × $8,000 + 0.25 × $40,000) + $2,300 = $3,900 | Barely |
| A backup compressor covers the stop, so a failure costs only the $16,000 repair | 0.25 × $16,000 = $4,000 | 0.25 × (0.75 × $8,000 + 0.25 × $16,000) + $2,300 = $4,800 | No |
| The program catches 1 failure in 4, not 3 | $10,000 | 0.25 × (0.25 × $8,000 + 0.75 × $40,000) + $2,300 = $10,300 | No |
Four things, all of them
Predictive maintenance pays when the stop is expensive, the failure is frequent enough, the failure gives warning, and someone acts on the findings. Take away any one and the case falls apart.
The same arithmetic works for any machine, and the monitoring cost per machine falls when one route covers several.
The cheaper steps that come first
Before buying an instrument, start with these:
- Do the preventive work you already have, on time. Lubrication, filters, belts and cleaning prevent many of the faults monitoring would find.
- Run route inspections that take readings, not ticks. With an infrared thermometer, a mechanic’s stethoscope and the machine’s own gauges, a technician can record a bearing temperature, a discharge pressure and an oil level each month. Numbers written down the same way each time start a trend, and the first ones on a machine in good order are its baseline.
- Rank the machines. List the few whose stop would hurt most: no backup, long lead time on parts, safety or production at stake. Predictive work goes there, if anywhere.
- Buy a survey before buying tools. One contracted vibration and infrared survey of the critical machines shows what is there and what a route would cost.
Predictive maintenance techniques: vibration, oil, infrared and ultrasound
| Technique | What it finds | Tool | Who reads it |
|---|---|---|---|
| Vibration analysis | Imbalance, misalignment, looseness, bearing and gear wear in rotating machines | Vibration data collector or meter; mounted sensors on a few critical machines | A trained analyst, in house or contracted |
| Oil analysis | Wear metals, dirt, water, and oil that is worn out or the wrong type, in gearboxes, hydraulics, compressors and engines | A sample bottle, a clean sampling point, a lab | The lab’s report, read by a technician who knows the machine |
| Infrared thermography | Loose or overloaded electrical connections, hot bearings, failed steam traps, missing insulation | Infrared camera; a spot infrared thermometer for single readings | A trained thermographer for panels; anyone for a spot reading |
| Ultrasound | Compressed air and gas leaks, bearings short of grease, electrical arcing, leaking valves and steam traps | Handheld ultrasonic detector | A trained technician, comparing against the last reading |
The U.S. Department of Energy’s O&M Best Practices Guide and NASA’s guide (chapter 6 in each) describe every technique and where it applies. Both add electrical tests of motors, and NASA’s adds nondestructive testing, such as measuring pipe wall thickness.
None of them replaces the others, and none replaces preventive work: NASA’s guide says predictive testing “should not be the sole type of maintenance practiced.”
What a predictive program takes
A predictive program needs five things, and the instrument is the easy one.
- A way to measure. Handheld instruments on a route, a contractor who brings theirs, or sensors mounted on the machine.
- A baseline for each machine. What normal looks like, measured in good condition. NASA’s guide asks for baselines early in the machine’s life, under similar conditions each time, and again after a major repair or a change in how the machine is used (section 7.1).
- Limits. A level at which to look closer and a level at which to act, from the machine’s maker, published standards or the machine’s own history.
- Someone to read it. A vibration spectrum or an oil report is useless until someone who understands it says what it means.
- A way to act. A finding becomes a planned work order, with the part ordered and a stop booked. A report that says “bearing defect, replace within 6 weeks” and then sits in an inbox has cost money and saved nothing.
What the government guides advise
NASA’s guide describes setting an alert at a statistically significant distance from the mean of past readings, usually two standard deviations, and an alarm at three (section 6.2).
The DOE guide (Release 3.0, chapter 6) advises against buying predictive equipment without a serious commitment to training and to acting on the results. It suggests contracting the service out instead.
The P-F interval
The P-F interval sets how often to measure: the inspection interval must be the same as or shorter than it.
Most failures do not happen all at once. There is a point, P, where a failure can first be detected, and a later point, F, where the machine no longer does its job. The time between them is the P-F interval, and the P-F curve draws it.
Check at about half the P-F interval
Many teams check at about half the P-F interval, so that one check lands inside the window. The least warning you get is the P-F interval less the time between checks, so check more often if acting takes longer than that.
The theory, with its sourcesA potential failure defined, a brake pad worked through, which technique sees a fault first, and what to do at an alert
Nowlan and Heap’s 1978 report for the U.S. Department of Defense, Reliability-Centered Maintenance, defines a potential failure as “an identifiable physical condition which indicates a functional failure is imminent.”
The Defense Department’s RCM manual (DoDM 4151.22-M, 2011, since reissued as DoDM 4151.25) puts the rule plainly: the inspection interval must be the same as or shorter than the P-F interval. Its example is a brake pad:
1.6 mm of pad left
every year
Different techniques see the same fault at different points. On a rolling bearing, vibration analysis and ultrasound usually pick up a defect first, and wear metal in the oil follows. Noise you can hear and heat you can feel come last, when little time is left. The earlier a technique sees the fault, the longer the P-F interval it gives you, and the less often you need to look.
When a reading crosses its alert level, look more often. NASA’s guide says to cut the monitoring interval to between a third and a quarter of what it was: a machine read quarterly is read every 3 to 4 weeks until the trend settles or the repair is done (section 4.1).
What Maintensor records, and what it does not
Maintensor has nothing predictive. What it can hold is the manual side of the program, the part that preventive maintenance software is for.
- The route. A work order that repeats by the calendar, with a procedure as its checklist.
- The readings. A Number step records a reading, such as a bearing temperature. It has no unit and no limits, so write both into its wording.
- The checks. An Inspection check is answered Pass, Flag or Fail. A Fail asks for a note and a photo before the next step, then offers a follow-up work order and a button to mark the asset down. It does not stop the job being closed.
- The report and the repair. A contractor’s report can be attached to the route’s work order as a PDF. That work order and the repair that follows are both listed on the asset’s record.

What it does not do
No sensors connect to it, it keeps no meter readings or trends, and nothing in it comes due because a reading changed.
A Number step’s value shows only on that work order’s checklist: not on the asset, not in a report, and not as a trend. If you want the trend, keep the readings in a spreadsheet as well, or rely on the contractor’s report.