MTTF calculator

Work out mean time to failure for parts you replace, such as bearings, seals and lamps.

Free, no sign-up. Nothing you type leaves your browser.

Calculate MTTF

Showing the example from further down this page. Type your own numbers over it.

Every part in the group, failed or still running.

How many of them failed.

MTTF13,250 h

53,000 h ÷ 4 failures = 13,250 h

About 3.2 years at 4,160 running hours a year.

MTTF formula

MTTF = total operating hours ÷ number of failures

Total operating hours
hours run by every item in a group of identical parts, failed or running
Failures
the items in the group that failed

How to calculate MTTF

  1. Pick identical parts. The same part, in the same kind of duty.
  2. Add up their hours. Every one of them, failed or still running.
  3. Count those that failed. Parts changed early on a schedule are not failures.

MTTF example: six conveyor bearings, two still running

53,000 hHours on all six
30,600 failed + 22,400 running
4Failures
7,650 hFailed bearings only
30,600 ÷ 4, too low
13,250 hMTTF
53,000 ÷ 4

The conveyors and their hours are made up.

What your MTTF tells you

  • Size your spares. Six bearings that each run 4,160 hours a year need about 6 × 4,160 ÷ 13,250 = 1.9 replacements a year. The reorder point calculator turns that into a shelf count.
  • Choose how to replace. If a part wears out and its failure stops a line, replace it on a schedule shorter than its typical life. If not, keep a spare and run it to failure.

An outlier is a cause to find

A bearing that lasts a third as long as the others had something shorten it: a belt that tracks to one side, a misaligned drive, a missed grease point. That is a job for the root cause worksheet.

MTTF questions

Should I count the parts that have not failed yet?

Yes. Their hours go in the total. Leaving them out understates the life, because each one has already outlasted some of those that failed. Counting them is the usual simple estimate, and it assumes a steady failure rate, so treat a small group as rough.

MTTF or MTBF: which do I use?

Use MTTF for a part you throw away and replace, such as a bearing, seal or lamp. Use MTBF for a machine you repair and put back into service. A conveyor has an MTBF; the bearing in its head pulley has an MTTF.

Is MTTF the same as a bearing's rated life?

No. A bearing's L10 life is the point where 10% of a group have failed, not the average. A lamp's rated average life is usually where half of a test group is still burning. Neither is an MTTF.

More free tools

All tools
  • MTBF calculator

    Mean time between failures

    Operating hours ÷ failures

  • Reorder point and safety stock calculator

    When to order, and how many extra to keep

    Use in the lead time + safety stock

  • EOQ calculator

    Economic order quantity

    √(2 × use × order cost ÷ holding cost)

Keep the trail each part leaves.

Start the trial: each asset lists the parts it uses and its work orders, and each work order lists the parts that went into it, so the dates give you the gaps between replacements.

30-day free trial. No credit card.