The 5 whys or the fishbone?
| 5 whys | Fishbone (Ishikawa) | |
|---|---|---|
| Use it when | The failure is on one machine and the first answers are plain | Several causes are believable, or a crew would run with the first idea |
| How it works | Each answer becomes the next question, straight down to a cause | Lays out the possibilities on six branches before anyone follows one |
| Keeps you from | A cause nobody can show at the machine | Settling too soon |
The two work together, which is why they share one sheet here. Where a system has a backup, such as a second pump or a standby generator, a stop means both failed, and a fault tree maps those combinations better. An injury or a near miss calls for a formal investigation, run by the person in charge of safety at your site.
Filling each part in wellWhat makes an answer good enough to act on.
- Say what happened, as a fact. Name the asset, when it happened, how often, and what anyone saw, heard or measured. "Compressor AC-1 shut down on high temperature twice this week, both times after 2 p.m." can be checked. "The compressor keeps overheating" cannot.
- Ask why, and back each answer. Write down only what you can show at the machine: a meter reading, a photo, the worn part, an old work order. Then ask why that happened. Stop when you reach something you can fix, most often something nobody was doing: a check, a step, a part kept on the shelf. The sheet takes up to seven whys.
- Spread the causes on the fishbone. When more than one thing could explain the problem, put each possible cause on its branch, then cross off the ones the evidence rules out. Run a chain of whys on each cause that is left.
- Write the actions. An action for every cause the evidence confirmed, each with an owner and a date, and a day set to see whether the failure has come back.
The example, read through
"Show an example" fills the sheet with pump P-2 from the 5 whys guide. Its motor tripped in the afternoon, 3 times in 2 weeks. The plant is made up, and so is every name and number in it.
How the example reads, part by partThe problem, the whys, the fishbone and the actions.
Laura Bennett, the supervisor, worked through it with Dan Kowalski, the electrician.
- The problem names the pump, the loop it feeds, how often it stopped and when. The afternoon matters: it comes back at the fourth why.
- The whys run from what the crew saw to what they can change: a tripped overload relay, then current out of balance, then a loose, overheated connection at the starter, then three years with no one looking at it in a cabinet the afternoon sun bakes, and last, a preventive maintenance plan that never opens a panel.
- The fishbone sorts those findings. The loose connection is a Machine cause and the hot cabinet an Environment cause. Three findings land on Method: no panel check, a checklist that covers only the seal and bearings, and no check since the starter went in. Material, People and Measurement stay empty: nothing pointed at a part, at anyone's skill, or at a gauge or a test, and the clamp meter readings are what found the fault. An empty branch is a fine result.
- The actions work at two levels. Dan re-terminates the connection today. Laura adds a check of the panels once a year, starting by the next shutdown: an infrared scan under load, and every connection checked for tightness.
The two actions are different kinds of work. The repair happens once. The check repeats, because the last why was a check that nobody did.
A live panel needs a qualified electrician
Taking readings inside a live panel, as in this example, is a job for a qualified electrician. Under OSHA's electrical work practices rule, 29 CFR 1910.333, only qualified persons may work on parts that are still energized. In Canada, look up your province's rule.
What to do with the result
- Turn repairs into work orders. A finished sheet is a list of work. In Maintensor, each action can be a work order with its assignee and due date, and the printed sheet, as a photo or a saved PDF, can go on it. The app has no root cause form of its own.
- Turn the last why into a check that repeats. It tends to name something nobody checks. Make it a step that plainly passes or fails, in a procedure on a repeating work order.
- Count whether it held. Pick a day 30 to 90 days after the fix and count how often the failure has come back. If it is back, the sheet missed a cause.
To fill one in by hand, the RCA record and the 5 whys worksheet are free to print, as PDF or Word files.
Where the methods come fromToyota, and OSHA and the EPA.
The 5 whys started at Toyota. Taiichi Ohno wrote about it in his book on the Toyota Production System. In one case he gives, a stopped machine leads back to a missing strainer, which let metal scraps in to wear down its lubrication pump (the Lean Enterprise Institute's summary).
In a joint fact sheet, OSHA and the EPA call a root cause a basic reason, tied to how a system works, that an incident happened and that can be corrected, and they point out that one incident often has more than one (their fact sheet on root cause analysis).