What are failure codes?

Failure codes are short, fixed answers recorded when a repair is closed: what the problem was, what caused it and what was done. Because everyone picks from one list, the answers can be counted and repeat causes stand out.

By MaintensorUpdated

Failure codes as three lists: problem, cause and remedy

A common scheme has three lists, each picked from when a repair work order is closed: the problem (what was seen), the cause (why it happened) and the remedy (what was done). Some schemes add a fourth for the component that failed, such as bearing, seal or belt.

ExampleOne closed job, coded

What the technician wrote Code
Problem Pump P-4 seal dripping steadily, puddle at the base LEAK
Cause Seal faces scored; the pump had been run dry when the tank was drained USE
Remedy Replaced the mechanical seal REPLACE

The note is still the most useful thing for the next technician. The three codes are what let you count.

A starter list of 8 cause codes

WEARNormal wear at the end of a part's life.
LUBEToo little, too much, wrong or dirty lubricant.
ALIGNMisaligned or out of adjustment, such as a belt off track.
DIRTDust, water or debris got in.
ELECElectrical supply or connection: a loose lug, a lost phase.
USERun outside its design: overload, impact, wrong setting.
WORKFitted, set up or repaired wrong last time.
UNKNOWNCause not found: fine once; investigate if it repeats.

USE is not “operator error”: it says the equipment was run outside its design, and the next question is why that was easy to do.

Start with the cause list

Say a crew of four closes 40 repairs a month (a made-up figure). Spread over 60 cause codes, nothing stands out; over 8, a cause with 10 of the 40 jobs is impossible to miss. If you keep only one list, make it cause: it is the one that points at a fix.

ISO 14224, the reference taxonomy

The international reference is ISO 14224 (2016 edition), on reliability and maintenance data, written for the petroleum, petrochemical and natural gas industries. Problem, cause and remedy codes are a simpler version of its scheme.

As a public summary by its technical editor sets out, its failure data separates the failure mode, mechanism, cause and detection method, and its maintenance data records what was done.

How a small team uses them

Pick the cause code when the repair is closed, while the technician still remembers. Once a month, count codes by asset: the same cause on the same asset three times is a candidate for a root cause analysis, and a code climbing across many assets points at a routine.

Codes also explain a falling MTBF, and they only work if work orders are closed with words in them.

Failure codes in Maintensor: a closing note as the stopgap

Maintensor has no failure codes, and a work order has no cause or remedy field. Categories on a work order, such as Electrical, Mechanical or HVAC, group work for filters and Reporting, but they are not failure codes: nothing asks for one when a job closes.

The stopgap is a note added when the job is closed that starts with the code (“LUBE: gearbox low on oil, fill plug loose”), which the work order’s History keeps. Search does not read notes, so the monthly count is done by reading each asset’s finished work orders.

Questions

What people also ask.

More in the glossary, or see the whole product on the features page.

What is the difference between a failure mode and a failure cause?

The failure mode is how the failure shows itself: leaking, will not start, overheating. The cause is why it happened: wear, a missed grease point, a part fitted wrong. ISO 14224 adds a third idea between them, the failure mechanism, which is the physical process involved, such as fatigue or corrosion. A small crew can usually get by with mode and cause.

How many failure codes should a small crew use?

Fewer than you think: 8 to 12 per list is a good start. Every code should be one that two technicians would pick the same way for the same job. If Other or Unknown is chosen for more than about one job in ten, read what was written for those jobs and add the code that is missing.