Crane inspection checklist for overhead and gantry cranes

A crane inspection checklist follows OSHA 1910.179: frequent inspections of the fastest-wearing parts, daily to monthly; a monthly hook, chain and rope inspection with a signed record; and a periodic inspection of the whole crane every 1 to 12 months.

Free, no sign-up. Print it, or type into the Word file.

By MaintensorUpdated

Page 1 of the blank crane inspection checklist for overhead and gantry cranes: the crane and visit, the start-of-shift checks and the monthly record of hooks, chains and ropes, each with a box for OK and Fail and a line for a note.
Page 1 of 2

The checks, by inspection

The sheet holds the operator’s start-of-shift checks and the periodic inspection of the whole crane, which includes every frequent item. The monthly hook, chain and rope inspection has a record of its own, set out below. Your crane’s manual and your inspector come first.

Start of each shift10 checks

  • Controls (pendant or radio)
  • Upper limit switch, no load, block inched in slowly
  • Hoist, trolley and bridge stopping
  • Hook, visual
  • Hoist chain, visual
  • Wire rope, as it pays out
  • Air or hydraulic lines, tanks, valves (where fitted)
  • Warning signal
  • Rated load marking
  • Runway and travel path

Monthly, with a written record5 checks

  • Hooks: throat opening against the new figure, twist, cracks
  • Hoist chains and end connections
  • Running ropes
  • Operating mechanisms
  • Rope reeving

Periodic: every 1 to 12 months, the whole crane8 checks

  • Structure
  • Sheaves and drums
  • Pins, bearings, shafts, gears, rollers, locking and clamping devices
  • Brakes
  • Load, wind and other indicators
  • Power plant (electric, diesel, gasoline)
  • Chain drive sprockets
  • Electrical apparatus

Slings, before use3 checks

  • Wire rope
  • Synthetic web
  • Alloy chain

Slings are inspected too: 1910.184(d) has each sling and its fastenings inspected each day before use by a competent person the employer designates, and more often during use where conditions warrant. Damaged slings come out of service at once.

What counts as a fail, check by checkThe full tables, with the paragraph of the rule behind each, and the slings.

Paragraph numbers are those of 1910.179, and of 1910.184 for slings.

Start of each shift

Check What counts as a fail Rule
Controls (pendant or radio) A motion that sticks, drifts, runs the wrong way, or is labeled wrongly; labels unreadable (j)(2)(i), daily; (l)(3)(iii)(d)
Upper limit switch, no load, block inched in slowly Hook block does not stop before it reaches the trolley (n)(4)(i), each operator’s shift
Hoist, trolley and bridge stopping Hook or load drifts after release; bridge or trolley does not stop as usual (j)(2)(i), daily
Hook, visual Cracks, bending, an opening wider than usual, twist. Safety latch broken or missing (practice) (j)(2)(iii), daily
Hoist chain, visual Wear, twist, distorted links, stretch (j)(2)(iv), daily
Wire rope, as it pays out Kinks, crushing, birdcaging, broken wires, rope out of the drum grooves Practice; criteria in (m)(1)
Air or hydraulic lines, tanks, valves (where fitted) Leaks or deterioration (j)(2)(ii), daily
Warning signal Horn or bell silent (n)(3)(xi)
Rated load marking Not readable from the floor (b)(5)
Runway and travel path People or stock in the path, a runway stop missing, new noise or vibration Practice

When a load near the crane’s rating is lifted, (n)(3)(vii) has the operator test the brakes by raising it a few inches and applying them.

Monthly, with a written record

Item What to look for The record the rule asks for
Hooks Cracks; a throat opening more than 15% wider than normal; more than 10 degrees of twist from the plane of the unbent hook. A hook like that is discarded under (l)(3)(iii)(a) Date, inspector’s signature, hook serial number or other identifier: (j)(2)(iii)
Hoist chains and end connections Excessive wear, twist, distorted links, stretch beyond the maker’s figure Date, signature, chain identifier: (j)(2)(iv)
Running ropes Diameter below nominal; broken outside wires, how many and how bunched; worn outside wires; corroded or broken wires at end connections; corroded, cracked, bent, worn or wrongly fitted end connections; severe kinking, crushing, cutting or unstranding Date, signature, rope identifier: (m)(1)
Operating mechanisms Excessive wear of components None in the rule: (j)(2)(vi)
Rope reeving Not as the maker specifies None in the rule: (j)(2)(vii)

Periodic: every 1 to 12 months, the whole crane

The periodic inspection includes every frequent item, plus these from (j)(3):

Area What counts as a fail
Structure Deformed, cracked or corroded members; loose bolts or rivets
Sheaves and drums Cracked or worn
Pins, bearings, shafts, gears, rollers, locking and clamping devices Worn, cracked or distorted
Brakes Excessive wear on brake parts, linings, pawls and ratchets
Load, wind and other indicators Significant inaccuracy over their full range
Power plant (electric, diesel, gasoline) Not performing properly, or not meeting safety requirements
Chain drive sprockets Excessive wear; drive chain stretch
Electrical apparatus Pitting or deterioration of controller contactors, limit switches and pushbutton stations

Slings, each day before use

Sling Remove from service when
Wire rope 10 randomly distributed broken wires in one rope lay, or 5 in one strand in one lay; outside wires worn by a third of their diameter; kinking, crushing or birdcaging; heat damage; cracked, deformed or worn end attachments; a hook opened more than 15% or twisted more than 10 degrees; corrosion: (f)(5)
Synthetic web Acid or caustic burns; melting or charring; snags, punctures, tears or cuts; broken or worn stitches; distorted fittings: (i)(9)
Alloy chain Cracked or deformed master links, coupling links or other parts: (e)(9). Also a thorough inspection at least every 12 months, with a record of the month it was done: (e)(3)
Chain, web or fiber rope Identification tag missing or unreadable: (e)(1), (i)(1), (h)(1)

The monthly record: hooks, chains and ropes

Hooks, hoist chains and running ropes get a thorough inspection each month, with a record of the date, the inspector’s signature and an identifier for each item. What takes each out of service:

HookA throat opening more than 15% wider than normal, or more than 10 degrees of twist from the plane of the unbent hook: discarded under (l)(3)(iii)(a).
Hoist chainExcessive wear, twist, distorted links, stretch beyond the maker's figure: (j)(2)(iv).
Running ropeThe conditions in (m)(1): broken, worn or corroded wires, a diameter below nominal, damaged end connections, severe kinking, crushing, cutting or unstranding.

Measure each hook when it is new

Measure each hook’s throat opening when it is new and write the figure on its record. Without that baseline, nobody can say whether it has opened 15%.

The rule lists rope conditions without numbers; the crane maker’s manual and ASME B30.2 give the limits for removing a rope.

How often the whole crane is inspected

The rule sets the periodic interval by “activity, severity of service, and environment”.

ExampleThree cranes, three intervals

Made-up cranes, to show how the rule’s three factors play out.

Crane Use Setting Periodic interval chosen
5 ton bridge crane over a maintenance bay A few lifts a week Clean, heated 12 months
10 ton crane in a steel warehouse Most of every shift, often near its rating Dusty, unheated 3 months
2 ton gantry in an outdoor yard Daily Rain, road salt, cold 6 months

Cranes that sit idle have their own rules in (j)(4), and idle rope in (m)(2):

Idle 1 to 6 monthsA frequent inspection and a rope inspection before it is used.
Idle more than 6 monthsA complete inspection first.
Standby cranesInspected at least every six months.
Rope idle a month or moreInspected by an appointed person, whose approval is needed before use, with a record.

Before you start

Three people
The operator does the start-of-shift checks before the first lift, much like a forklift’s daily examination, and inspects slings before each day’s use. Maintenance, or someone the employer designates, does the monthly inspection and signs the record. A qualified crane inspector, often a contractor, does the periodic one.
The maker's service too
1910.179(l)(1) asks for a preventive maintenance program based on the crane maker’s recommendations, so its lubrication and service tasks go on the schedule.
Lock it out for repairs
Under (l)(2), run the crane to where it is least in the way, set the controllers to off, open and lock the main or emergency switch, and hang “out of order” signs on the crane and on the floor below or on the hook. The lockout/tagout procedure guide covers writing one.

When a check fails

The crane stops. Paragraph (l)(3)(i) says unsafe conditions found by inspection are corrected before operation resumes, and only designated personnel adjust or repair. If the upper limit switch does not work, (n)(4)(i) says the appointed person is told at once.

The rule is the floor, not the whole job: ASME B30.2 is the US consensus standard for overhead and gantry cranes, and ASME B30.9 for slings. In Canada, provinces set their own rules, and CSA B167 covers the design, inspection, testing, maintenance and safe operation of overhead cranes, gantry cranes, monorails, hoists and jib cranes.

No checklist replaces operator training or a qualified inspector.

Crane inspections in Maintensor: shift, monthly and periodic records

Build three procedures from the tables above. The start-of-shift check is a row of Inspection checks (Pass, Flag, Fail), on a work order that repeats daily or weekly on the days the crane runs, assigned to its operators.

  • The monthly inspection adds what the record needs: a Text step for the hook’s serial number and the chain or rope identifier, a Number step for the throat opening (with units and limits in its label: “Throat opening, inches, new 1.25”), a Photo step, a Text step for the inspector’s name, and a Signature step they draw.
  • The periodic inspection is a yearly (or every 3 or 6 months) work order assigned to whoever books the crane inspector, with their report attached as a PDF.
  • A failed check asks for a note and a photo, then offers a follow-up work order on the same crane and “Mark asset down”. A crane with two hoists can keep each hoist as an asset that is Part of the crane.
The history of this month's air handler service: created by the system on the day last month's was completed, then started by the technician, with a note about a belt that is starting to crack.
The history of a monthly job on another machine: created on the day last month's was completed, started by the technician, with a note on what was found.

The completed work order holds the date, who completed it, every answer and the signature. Whether that is the “certification record” the rule means is for you and your inspector to decide: the app records what was done; it certifies nothing.

What it does not do: the Signature step stores the drawn signature and its time, not which user signed, which is why the name step is there. Each reading stays on its own work order, so comparing this month’s throat opening with last month’s means opening last month’s job.

Only Full users and Admins answer checklists, so each operator who does it in the app needs a user seat. The equipment maintenance log explains what a crane’s history should hold, and the manufacturing page shows how a plant runs its recurring work in the app.

Questions

What people also ask.

More in the checklists, or see the whole product on the features page.

How often should an overhead crane be inspected?

Under OSHA 1910.179(j), frequent inspections run daily to monthly, and periodic inspections of the whole crane every 1 to 12 months, set by how hard it works, how severe the service is and its environment. Hooks, hoist chains and running ropes get a monthly inspection with a record. A crane idle for a month or more is inspected before it goes back into service.

What crane inspection records does OSHA require?

1910.179 asks for a monthly certification record for hooks, hoist chains and running ropes, with the date, the inspector's signature and an identifier for the item, plus a record for any rope idle a month or more and the reports of rated load tests. For alloy chain slings, 1910.184 asks for a record of the most recent month each was thoroughly inspected.

Who is allowed to inspect an overhead crane?

1910.179 does not name a qualification for most inspections. It says adjustments and repairs are done by designated personnel and that an idle rope is approved for use by an appointed person, and 1910.184 has slings inspected by a competent person the employer designates. A sensible split is the operator for shift checks and a qualified crane inspector for periodic ones.

What is the difference between a frequent and a periodic crane inspection?

A frequent inspection covers the parts that wear or fail fastest (controls, hooks, chains, air and hydraulic lines, rope reeving), daily to monthly, plus watching for defects during operation. A periodic inspection is a complete inspection of the crane, every 1 to 12 months: everything in the frequent one plus structure, bolts, sheaves, drums, brakes, indicators and electrical gear.