Time-based maintenance and its two clocks
NASA’s reliability-centered maintenance guide (2008, section 5.2) describes preventive maintenance at “pre-defined intervals (time, operating hours, or cycles)” and adds that “it is performed regardless of equipment condition.”
- Calendar time: every day, week, month or year.
- Running time or use: every so many hours, cycles or miles, also called usage-based or meter-based maintenance.
Where it works
- Parts that wear with age or use: filters, belts, brushes, lubricant, wear strips.
- Intervals a rule or maker sets, such as the monthly visual inspection and yearly maintenance check OSHA’s 29 CFR 1910.157 requires on portable fire extinguishers.
- Cheap checks and small crews: a two-minute look at a gauge costs less than deciding whether it is needed, and a calendar is all it takes.
Its limits
A fixed interval works only if failure follows age, and often it does not. The NASA guide (section 4) cites three studies, from 1968 to 1982, in which random failures made up 77 to 92 percent of all failures. No interval picks the right moment for those.
Taking a healthy machine apart on a schedule can also break it: the guide warns that scheduled overhaul can bring “a high infant mortality rate into an otherwise stable system.”
Time-based example: 2,000 running hours as a calendar repeat
A compressor’s manual calls for an oil and filter change every 2,000 running hours (made up: use your manual’s figure). It runs two 8-hour shifts, five days a week.
weeks between services = interval in running hours ÷ running hours a week
16 h × 5 days
2,000 ÷ 80
about 1,740 h between changes
In the slow season the plant drops to one shift, and the same 5 months is about 870 hours: the oil comes out with less than half its life used. Safe, but wasteful, so write the hour meter down at every service and stretch the repeat if it keeps coming in short.
The numbers, line by lineBoth seasons, from the manual's 2,000 hours.
| Item | Figure |
|---|---|
| Maker’s interval | 2,000 running hours |
| Running hours a week, two shifts | 16 × 5 = 80 |
| Weeks to 2,000 hours | 2,000 ÷ 80 = 25 |
| Calendar repeat chosen | 5 months, about 21.7 weeks |
| Hours between changes, two shifts | 21.7 × 80 ≈ 1,740 |
| Hours between changes, one shift | 21.7 × 40 ≈ 870 |
Every number is made up.
Time-based vs condition-based maintenance, clock by clock
- On the calendar: due on a date. Simple, but blind to how hard the machine worked.
- On running time: due after so many hours, cycles or miles. Someone must read the meter.
- Condition-based: due when a reading passes its limit. Someone must take and judge it.
- Scheduled maintenance is what a time-based rule produces: a date and a person.
Setting the first interval from the maker’s figure and adjusting it after a few cycles is in the preventive maintenance schedule guide.
Calendar repeats in Maintensor, and no run-hour triggers
Maintensor repeats preventive maintenance work on the calendar only: daily, weekly on chosen weekdays, monthly on a date or a weekday, or yearly, each every N, so “every 5 months” is a monthly repeat every 5. The next work order is created when the current one is completed, due on the schedule’s next date.

There are no run-hour, meter or mileage triggers. A Number step can record the hour meter on the checklist, but the reading stays on that work order and triggers nothing, so convert a usage interval to a calendar repeat as above.